Construction Pricing: Overhead, Profit & Contingency

How do I turn a direct cost into a bid price with overhead, profit and contingency and send it safely?

Add overhead, profit and contingency as separate markup lines on the direct cost, each with its own switch (in the example 12%, 8% and 5%). Run Validate and review what it flags, such as missing MasterFormat codes or unit warnings. Save a version before the price is sent, use Create Revision and Compare when scope changes, and export the PDF for the client.

The estimate says what the job costs. The price says what you charge. Turn a direct cost into a bid price with overhead, profit and contingency, then check it, save a version and export it.

In this video

  • Add overhead (12%), profit (8%) and contingency (5%) as separate markup lines, each with its own switch.
  • Validate the estimate and read what the checks find, such as missing MasterFormat codes and unit warnings.
  • Use the cost breakdown to see where your pricing risk sits.
  • Save a version before a price leaves the office, start a revision when the scope changes, and compare the two line by line.
  • Export to Excel, PDF or CSV, and read the PDF the way your client will.

You will produce

A bid price with overhead, profit and contingency, validated, saved as a version and exported to PDF

Markups & taxEstimatingEstimate & cost plan

Transcript

0:00 Markups

The estimate says what the job costs. The price says what you charge. In this lesson you turn the Maple Street direct cost into a price you can send. You add overhead, profit and contingency, check the result, save a version, and export it. Here is the plan. You add the markups, validate the estimate and read what it finds, and look at the cost breakdown. You save a version before you send anything, and start a revision when the scope changes. Then you export, and see exactly what the client receives. A price is a team decision. The estimator prepares it. The owner of the company sets overhead and profit, the project manager checks it against the job, and the client receives the final PDF. Markups sit on top of the direct cost. Overhead covers running your company: the office, the trucks and the insurance. Profit is what you keep. Contingency is money for the things you cannot see yet. Each one is a percentage of the direct cost, and each one stays a separate line in the estimate. Markups live below the table, under Markups and Overheads. Apply Regional Template loads a starting set for your country, and the United States is on the list. Here we type our own. Click Add Markup and name it Overhead, at 12%. Then Profit, at 8%. And Contingency, at 5%, in its own category. Each line shows its amount and has its own switch, and the grand total is the direct cost plus all three.

1:28 Checks

Before a price leaves the building, validate it. The Validate page runs over a hundred checks against your standard and lists what it finds. Here, every position is missing its MasterFormat code. That is why the score is low, and it is the first thing to fix. The warnings are questions: a rate five times above the typical one, a metric unit in an imperial job, a division with nothing in it. Read each one before you send the price. Cost Breakdown shows the same money as a picture: material, labor and equipment, with the top resources underneath. If one resource carries a large part of the job, that is where your pricing risk is. Here it is the metal roofing, so check that rate twice.

2:10 Versions

Before you send it, save a version. Open Version History, type a label, Sent to client, and click Save. That snapshot keeps the estimate exactly as you sent it. Save one every time a number leaves your office, and there is never an argument later about which price was sent. When the client changes the scope, do not overwrite the price you sent. Create Revision makes a copy and opens it, and the one you sent stays as it was. Make the change in the copy, here more drywall. Then click Compare and pick the estimate you sent, and you see exactly what moved, line by line.

2:46 Export

Now export. Choose Excel if your client or your team wants to work with the numbers, PDF for a clean document to send, or CSV for any other software. For the client, it is the PDF. Open the PDF. This is what lands in your client's inbox. Read it once the way the client will: the project name, the sections, the markups and the final price. If a line would confuse you, it will confuse them too, so fix it in the estimate and export again. Every number in this price traces back. Each markup goes back to a percentage you chose, and each position to a database item or a quote you typed in. Each rate goes back to its resources, and the labor to your own crews. So when a client asks why, you can show them. That is the whole path: a cost database you have checked, an estimate built from it, and a price in your client's inbox. Take a real bid you are working on, build it next to your spreadsheet, and compare the two. OpenConstructionERP is free and open source. Download it, start with your next bid, and I will see you in the next episode.

The same question in another country

  1. 4:49 EN · Canada · Ontario Price a Construction Job Every bid on a Toronto job comes down to one number: your contract price, in Canadian dollars, with markups and bond, before HST. Price six stacked townhomes and turn their cost into that number.
  2. 4:17 FR · Canada · Québec Estimer un projet de construction How do I price a Montréal job with markups, and where do GST, QST and my RBQ licence number go?
  3. 5:53 EN · GB How to Price a Construction Tender (NRM 2) We price a UK construction tender in OpenConstructionERP, starting with the bill of quantities and working through to the tender sum. The example follows an NRM 2 structure and includes measured work, subcontract quotes, preliminaries, risk, overheads and profit.
  4. 5:03 ZH · CN 工程量清单投标价怎么算:四大块与增值税陷阱 How do I build a bid price in four blocks under the new Chinese standard without charging VAT twice on a provisional sum?
  5. 2:40 ES · ES Importar BC3 y preparar una oferta de obra: PEM, gastos y baja How do I import the BC3 from a tender, add overheads and profit, and prepare a bid with a baja without losing the original budget?
  6. 1:57 BG · BG КСС и оферта: импорт от Excel, проверка на цените и ДДС How do I import a bill of quantities from Excel, check the prices and add VAT to get a bid total?

Related videos

  1. 6:36 DE Einheitspreise und Kosten nachvollziehen How is a unit rate built from labour, material and equipment, and how does a change in labour time change the price?
  2. 7:35 DE Kostenquellen und Ressourcen anpassen How do I take a rate from a regional cost database, check its origin and scope, and reprice it with my own labour and plant rates?
  3. 10:14 DE · Germany Vom vollständigen LV zur Kostenbasis How do I turn a fully priced bill into a checked, locked cost base and budget before tender award?
  4. 3:46 FR · Canada · Québec Démarrer avec OpenConstructionERP en français How do I use the software in French and map its France-French terms to Québec site vocabulary?
  5. 5:06 FR Budget de chantier : justifier chaque coût How can I explain every line of my project budget before we commit to the site?
  6. 4:25 IT · IT Come leggere il computo metrico prima di fare l'offerta How do I check a computo metrico estimativo line by line before I bid, and which part of the total can be discounted?