Bid Leveling: Three Quotes, One Job

How do I compare three subcontractor quotes for the same job and pick the real low bid?

Build a trade package from the estimate so every sub prices the same three framing lines, publish it, invite three subs and record each bid, then compute the leveling and check for blank lines: a line with no price adds nothing, so Sub A's lowest total covered only one of three lines: price its gaps at Sub B's rates and Sub A's total climbs above Sub B's, so Sub B is the best value. Totals never price a note, so read each sub's exclusions too. Award to Sub B to draft a contract and a purchase order.

Compare three framing bids in OpenConstructionERP using the same scope of work. This bid-leveling example follows a trade package from the estimate through quotations and adjustments to the subcontractor award.

In this video

  • Build a trade package from your estimate: one trade (here the wood framing), so every sub bids the exact same lines and the bids can be compared.
  • Bid Management sits under Procurement and needs Advanced mode. Create a package with a code, a title, a deadline and the framing budget from your estimate.
  • Add the framing line from the estimate with its quantity, then the lines the subs must price on their own (the wall sheathing and the blocking).
  • Publish the package and invite three framing subs from your directory.
  • Record each bid: a unit price on every line, with the line totals and the bid total worked out as you type.
  • Close the bidding and compute the leveling. The matrix puts the subs side by side, and a blank line is the first thing to look for.
  • Level like for like: a line with no real price adds nothing to the total, so price each gap at another sub's rate. Sub A's total climbs above Sub B's.
  • Read every sub's exclusions. The totals never price a note, and a clause that pushes a cost back to you can outweigh a lower price.

You will produce

A framing package with three levelled bids, where the gaps in Sub A's bid are priced at Sub B's rates, and an award to Sub B that drafts a contract and a purchase order.

Transcript

0:00 The package

On bid day, three quotes land for the same job, and none of them line up. The lowest is not always the cheapest. By the end of this lesson, you pick the right one. Here's the plan. First, invite three subs to bid on the framing package. Then record their bids and compare them side by side. Then level them, and find the lines a sub left out. Finally, award the work. Bidding is team work. The estimator prepares the package from the estimate. Three subcontractors send their bids. The project manager levels them, and you award the work. A trade package is one trade, built from your estimate. Here it is the wood framing. Every sub bids the exact same lines, so the bids can be compared. Bid Management sits under Procurement, and it needs Advanced mode. If your sidebar does not show it, switch to Advanced in Settings. Open it, and create a new package for the framing. Give it a code, a title, a deadline, and the framing budget from your estimate. Open the package, and add the framing line from your estimate. It comes in with its quantity. Then type two lines the subs must price on their own, the wall sheathing and the blocking. Now every sub bids the same three lines.

1:14 Compare

Publish the package. Then pick three framing subs from your directory, and invite each one. The bids come back. For each sub, record a unit price on every line. The app works out the line totals and the bid total as you type. Sub A prices only the wall framing, leaves the other two lines blank, and its note says it excludes the sheathing and the blocking. Close the bidding, and compute the leveling. The matrix puts the three subs side by side. The app ranks Sub A first, with the lowest total in green. But look at Sub A's column. Two of its lines are blank.

1:50 Level

A line with no real price adds nothing to the total. So a total is only the lowest if it covers every line. Level the bids, price each gap at another sub's rate, and compare like for like. Sub A left two lines blank, the sheathing and the blocking. Price them at Sub B's rates, and Sub A's total climbs above Sub B's. It is no longer the low bid. Sub A said it plainly in its note: it excludes the sheathing and the blocking. The totals never price a note. So read each sub's exclusions when the bid comes in, because a clause that pushes a cost back to you can outweigh a lower price.

2:29 Award

Now compare like for like. At the same scope, Sub B is the lowest bid, and the best value. A ranking is only as good as the scope behind it. Award the package to Sub B. The amount is already filled in. Add a short decision summary, and confirm. The award drafts a contract and a purchase order for Sub B, so the commitment is on record from day one. That is bid day: one package, three bids, leveled to the same scope, and the work awarded on value. Take a trade on a job you are bidding now, get three quotes, and level them the same way. OpenConstructionERP is free and open source. Download it today and start working.

The same question in another country

  1. 3:04 DE · Germany Angebote prüfen und Vergabe vorbereiten How do I compare bids on the same scope when the lowest one is missing an item, and record the award rationale?
  2. 4:23 EN · Canada · Ontario Tender Work to Subcontractors Three drywall subtrades priced your townhomes, and one came in more than a fifth lower. In Canada, carry the wrong sub's price in your bid and you may be held to it.
  3. 4:30 FR · Canada · Québec Soumissions et BSDQ Can I accept the lowest BSDQ bid if it arrived without the required bid bond?
  4. 6:01 EN · GB How to Compare Subcontractor Bids We compare subcontractor bids for the same work package in OpenConstructionERP. Before looking at the totals, we check exclusions, missing scope and the assumptions behind each quotation.
  5. 4:59 IT · IT Subappalto: confrontare le offerte e scegliere l'impresa How do I compare three subcontractor bids fairly when the lowest one leaves out a line?
  6. 2:10 ES · ES Comparativo de ofertas de obra: precio, alcance y adjudicación Is the cheapest of three subcontractor bids really the cheapest once the scope is the same, and how do I award it with its purchase order?
  7. 1:58 BG · BG Избор на подизпълнител: сравнение на оферти по цена и срок How do I choose between three subcontractor bids when the cheapest one does not fit the schedule?
  8. 3:43 DE · Germany Vergabe im Bauwesen How do I compare three bids for the Rohbau, clarify a suspiciously low price under VOB/A and prepare the award?
  9. 5:20 ZH · CN 暂估价招标:比价、清标、定标,最低价未必最省 How do I compare three bids for a provisional-sum package when the lowest one leaves out a room?

Related videos

  1. 5:34 DE · Germany GAEB-Dateien kontrolliert austauschen How do I export a bill as GAEB X83, get priced X84 back and check that the exchange really worked?
  2. 7:01 DE Material und Teillieferung verfolgen How do I track an order, a partial delivery and the remaining quantity, and book what actually arrived into site stock?
  3. 4:36 FR Achats et stock : suivre les quantités Why do 1,000 ordered bags leave only 600 in stock, and how do I trace every difference?
  4. 4:25 IT · IT Come leggere il computo metrico prima di fare l'offerta How do I check a computo metrico estimativo line by line before I bid, and which part of the total can be discounted?
  5. 4:39 IT · IT Ribasso d'offerta: analisi prezzi e margine How far can I lower my bid before the job loses money, once site overheads are counted?
  6. 5:03 ZH · CN 工程量清单投标价怎么算:四大块与增值税陷阱 How do I build a bid price in four blocks under the new Chinese standard without charging VAT twice on a provisional sum?