OpenConstruction Academy
Вход / Регистрация
BG

Теория преди задача 4 · 8 мин

A deposit within the cap, a schedule that adds up

Плащателният график: лимит на аванса и етапни плащания

След тази лекция ще можете да

  1. Set the deposit at no more than 10% of the contract price including GST.
  2. Make the final payment the balance, so all payments add up to the price.
  3. Enter a claim in the ERP without GST.
1 / 4

The deposit cap in NSW

Under the Home Building Act 1989 (NSW), a deposit for residential building work may not be more than 10% of the contract price, and the contract price includes GST. Where the work needs home building compensation cover, take no deposit until the owners have the certificate.

Пример. On $94,600 including GST the deposit may be up to $9,460.00. Taking 10% of the price before GST would give you less than the law allows.
Contract price including GST$94,600
Deposit cap, 10%$9,460.00
2 / 4

Stage payments follow the work

The NSW guide to home building contracts allows payments as fixed stages, as work is performed, or both. A stage payment is due when that stage is reached: slab, lock-up, linings, fit-off. Each amount is an agreed sum, not a share of time gone by.

3 / 4

The last payment closes the schedule

The deposit and the stage payments are fixed. The payment at practical completion is the balance: the contract price less everything before it. Then the payments add up to the price exactly, and nothing is paid twice or left over.

4 / 4

Claims in the ERP are without GST

The schedule is written in amounts including GST, because that is what the owners pay. A progress claim in the ERP takes the period value without GST, and the GST is added on the invoice. Divide by 1.10 before you type.

Set a schedule

A different price and different stages from your task. Type your answer first.

Не е в мащаб
Задачата
  • Contract price $94,600 including GST.
  • Stage payments, including GST: slab $23,000, lock-up $32,000, fit-off $14,000.
  • Deposit at the legal maximum. The final payment is the balance.
Contract price$94,600
Deposit, 10%?
Contract price$94,600
Deposit, 10%$9,460.00
Стъпка 1 от 3

Deposit

The most the deposit may be. How much, including GST?

10% of $94,600 = $9,460.00.

All payments
?
All payments
$94,600 ($9,460 + $69,000 + $16,140)
Стъпка 2 от 3

Final payment

The price less the deposit and the three stages. How much?

$94,600 − $9,460.00 − $23,000 − $32,000 − $14,000 = $16,140.00.

??
  • Claim, without GST ?
  • GST on the invoice ?
$8,600
  • Claim, without GST $8,600
  • GST on the invoice $860
Стъпка 3 от 3

Deposit claim in the ERP

The ERP takes the claim without GST. What do you type?

$9,460.00 ÷ 1.10 = $8,600.00. GST is added on the invoice.

Накратко. Cap the deposit on the price with GST, close the schedule with the balance, and claim without GST.

Проверете се

Въпрос 1 от 3

The price is $77,000 excluding GST. What is the largest deposit you may ask for, including GST?

77,000 × 1.10 = 84,700. 10% is $8,470.00.
Въпрос 2 от 3

The stage amounts in your template do not add up to the contract price. What do you change?

  • Deposit and stages are fixed; the last payment closes the schedule.

  • The deposit is capped by law.

  • A schedule that does not add up invites a dispute.

Въпрос 3 от 3

Your deposit is $9,460 including GST. What goes into the ERP claim?

  • That includes GST. The ERP claim is without GST.

  • 9,460 ÷ 1.10. The GST is added on the invoice.

  • That takes 10% off. Divide by 1.10.