Преместване на земните маси, безплатен превоз и свръхтранспорт
След тази лекция ще можете да
Read where cut balances fill on a mass haul diagram, and mark the loops.
Work a loop's average haul distance from its area and volume.
Turn the haul beyond the free haul into overhaul, and read the surplus.
1 / 5
A running total of earth
A mass ordinate is the running total of cut less fill along the road, all in bank-equivalent m³. Where the road is in cut, the line rises. Where it is in fill, the line falls. A peak is where cut turns to fill; a trough is where fill turns to cut.
Пример. Each column is the change over 35 m. Follow their tops and you trace the curve: up to a peak of 660 m³, back to zero at 0+140, down to −250 m³, back to zero at 0+210, and up again.
1 0+035, in cut
2 0+070, in cut
3 0+105, in fill
4 0+140, in fill
5 0+175, in fill
6 0+210, in cut
7 0+245, in cut
2 / 5
Loops: where cut balances fill
Each time the curve comes back to zero, everything dug since the last zero has gone into fill in between. That stretch is a balanced loop. Above the zero line, earth moves forward; below it, earth moves back. Each loop is a job of its own.
Пример. A loop's volume is its largest ordinate, the peak or the deepest trough. A loop below the line is measured by its size, ignoring the minus sign.
3 / 5
Average haul distance
The area of a loop, between the curve and the zero line, is volume times distance. Divide it by the loop's volume and you get the average distance each m³ travels. Find the area by trapezoids between the ordinates.
Пример. A loop with an area of 80,000 m³·m and a volume of 500 m³ moves its earth 160 m on average.
4 / 5
Free haul and overhaul
The excavation rate pays for moving earth up to the free haul distance. Haul beyond it is paid as overhaul, in m³·station: volume times the extra distance, divided by the length of a station. A loop whose average haul is under the free haul earns nothing, and it never takes anything away from another loop.
Пример. Your contract defines the station. If free haul is 120 m and a station is 100 m, the loop above earns 500 × (160 − 120) ÷ 100 = 200 m³·station.
5 / 5
Surplus at the end
If the curve ends above zero, that much cut has nowhere to go on this road: it is surplus, to be hauled away. If it ends below zero, fill is short and must be borrowed. Read the last ordinate, the whole of it.
Пример. A curve ending at +200 m³ leaves 200 m³ of surplus, whatever happened in the loops before it.
Two loops and a tail
The curve from the first section of this lecture, with its own free haul. Predict each figure first.
Area divided by the loop's volume, its peak. How far does each m³ travel, in metres?
Подсказка: The volume of the loop is its largest ordinate.
50,050 ÷ 660 = 75.83 m.
Loop A?
Loop BUnder free haul
Overhaul, m³·station?
Loop A170.5
Loop BUnder free haul
Overhaul, m³·station170.5
Стъпка 3 от 4
Overhaul
Volume times the haul beyond free haul, divided by a station. Loop B is under free haul. What is the overhaul, in m³·station?
Подсказка: Loop A only: loop B earns nothing and takes nothing away.
660 × (75.83 m − 50) ÷ 100 = 170.5 m³·station. Loop B adds nothing: its average haul is under the free haul.
1 0+035
2 0+070
3 0+105
4 0+140
5 0+175
6 0+210
7 0+245
8 Surplus
1 0+035
2 0+070
3 0+105
4 0+140
5 0+175
6 0+210
7 0+245
8 Surplus
Стъпка 4 от 4
Surplus
Where does the curve end, and what is the surplus, in m³?
Подсказка: The whole of the last ordinate, not the last change.
The curve ends at 200 m³ above zero: that much cut leaves the road as surplus.
Накратко. Mark the loops at the zero crossings, take each loop's area over its volume for the average haul, pay only the haul beyond free haul, and read the surplus from the last ordinate.
Проверете се
Въпрос 1 от 3
A loop holds 500 m³ and its area is 80,000 m³·m. Free haul is 120 m and a station is 100 m. What is its overhaul, in m³·station?
Average haul 80,000 ÷ 500 = 160 m. Beyond free haul: 40 m. 500 × 40 ÷ 100 = 200 m³·station.
Въпрос 2 от 3
A short loop moves its earth 70 m on average. Free haul is 120 m. What does it do to the overhaul of the job?
Each loop is worked alone, and never below zero.
A loop under the free haul is simply paid in the excavation rate. It is not a credit.
Loops are separate jobs, each with its own volume and distance.
Въпрос 3 от 3
The mass haul curve ends at −170 m³. What does that mean?
Above zero would be surplus. Below zero means fill is short.