OpenConstruction Academy
Вход / Регистрация
BG

Теория преди задача 2 · 9 мин

Bars across a slab, laps and mesh sheets

Плоча S3: пръти, снаждания и мрежа

След тази лекция ще можете да

  1. Count bars in a slab from the distribution length and the spacing.
  2. Add a lap once per joint where one bar cannot span the slab.
  3. Lay mesh sheets out in each direction, laps included.
1 / 4

Count spaces, then add one

Bars are spread across the slab from the first bar to the last. The distribution length is the slab dimension less the edge distance at both sides. Divide it by the spacing to get the spaces, round up so that no gap is wider than the spacing drawn, and add one bar for the start of the row.

Пример. 8,920 ÷ 200 = 44.6, so 45 spaces and 46 bars. Round the spaces up, never down: with 44 spaces every gap would be wider than the 200 mm drawn. This is the rule your task states.
Slab width (mm)9,000
Less 2 × edge distance (mm)80
Distribution length (mm)8,920
Spaces at 200 mm, rounded up45
Bars46
2 / 4

Each bar loses its cover at both ends

A straight bar runs from edge to edge, less the cover at each end, so that no steel reaches the face of the concrete. Cover is at both ends of every bar, not once per slab.

Пример. With 25 mm cover a 6,000 mm slab takes a bar of 5,950 mm.
Slab dimension (mm)6,000
Less cover at both ends (mm)50
Bar length (mm)5,950
3 / 4

A lap is steel in the slab twice

When a line of bars is longer than one bar can be, two bars overlap so that one passes its force to the other. The overlap, the lap, is a length of steel that sits in the slab twice. A line of two bars has one lap, in the middle; the ends of the line do not lap. The drawing gives the lap as a number of bar diameters.

Пример. Take the cover off both ends first, then add one lap per joint.
Line inside the cover (mm)8,950
One lap, 40d for T8 (mm)320
Steel in one line (mm)9,270
4 / 4

Mesh: lay the sheets out, do not divide the area

Mesh comes in sheets, and each sheet overlaps the next. Work each direction on its own: the first sheet covers its full length, every added sheet covers its length less the lap. Round each direction up to whole sheets, then multiply.

Пример. 13,700 ÷ 4,500 = 3.04, so 4 sheets along. A short division of the area by the sheet area ignores the laps and the offcuts, and comes out too low.
Net length, less one lap (mm)13,700
Each sheet adds, sheet less lap (mm)4,500
Sheets along, rounded up4

Measure one slab

A different slab from your task, same rules. Predict each figure before you open it.

Не е в мащаб
Задачата
  • Slab 9,000 × 6,000 mm. Cover 25 mm. First and last bar 50 mm from the edge.
  • Mark A: T16 at 200 mm centres, running across the 6,000 mm span, spread along the 9,000 mm.
  • Mark B: T10 at 350 mm centres, running along the 9,000 mm in two bars with one lap of 40d.
  • Mesh zone 14,000 × 4,000 mm net of cover. Sheets 4,800 × 2,400 mm, laps 300 mm both ways.
Spaces, rounded up?
Bars?
Spaces, rounded up45
Bars46
Стъпка 1 от 4

Bars of mark A

Distribution length along the 9,000 mm, spaces at 200 mm rounded up, plus one. How many bars?

9,000 − 2 × 50 = 8,900 mm. 8,900 ÷ 200 = 44.5, rounded up to 45 spaces: 46 bars.

Bars46
Bar length (mm)?
Total?
Bars46
Bar length (mm)5,950
Total273.7 m
Стъпка 2 от 4

Total length of mark A

Each bar is the span less cover at both ends. What is the total length?

6,000 − 2 × 25 = 5,950 mm. 46 × 5,950 mm = 273.7 m.

161.1
  • Line inside the cover 161.1
  • Laps 7.2
161.1
  • Line inside the cover 161.1
  • Laps 7.2
Стъпка 3 от 4

Total length of mark B

Lines across the 6,000 mm, each one 9,000 mm less cover, plus one lap. What is the total length?

5,900 ÷ 350 = 16.9, rounded up to 17 spaces: 18 lines. One line: 9,000 − 2 × 25 + 40 × 10 = 9,350 mm. Total 168.3 m.

Area ÷ sheet area
5
Laid out with laps
?
Area ÷ sheet area
5
Laid out with laps
8
Стъпка 4 от 4

Mesh sheets

Sheets along the 14,000 mm and across the 4,000 mm, each with the 300 mm lap. How many sheets?

Along: 13,700 ÷ 4,500 = 3.04, so 4. Across: 3,700 ÷ 2,100 = 1.76, so 2. 4 × 2 = 8 sheets. Dividing the area by one sheet would say 5.

Накратко. Spaces rounded up, plus one, cover off both ends, one lap per joint, and mesh laid out sheet by sheet in each direction.

Проверете се

Въпрос 1 от 3

A slab is 6,600 mm wide. Bars at 150 mm centres, first and last bar 40 mm from the edge. Round the spaces up, then add one. How many bars?

6,600 − 2 × 40 = 6,520 mm. 6,520 ÷ 150 = 43.5, rounded up to 44 spaces: 45 bars.
Въпрос 2 от 3

A line of T16 bars runs along a 10,000 mm slab with 25 mm cover. It is two bars with one lap of 40d. How much steel is in the line, in mm?

10,000 − 2 × 25 = 9,950 mm. Lap 40 × 16 = 640 mm. Line 10,590 mm.
Въпрос 3 от 3

A mesh zone is 9,000 mm long. Sheets are 4,800 mm with a 300 mm lap. How many sheets along it?

  • The right count, by the wrong road: 9,000 ÷ 4,800 ignores the lap. It will fail on another length.

  • (9,000 − 300) ÷ 4,500 = 1.93, rounded up: 2 sheets.

  • Two sheets with one lap already cover 9,300 mm.