Turn a labor unit and a crew rate into labor dollars, and add material to get the unit rate.
Handle units given per 100 ft without slipping a factor of a hundred.
Keep a separate total of labor hours, lump sums included.
1 / 4
A labor unit is time, not money
Electrical estimators price installation in hours: so many hours per device, or per 100 ft of conduit. Most firms start from a published manual of labor units, such as the one NECA issues, and adjust for the job. Hours are turned into dollars only at the end, by the crew rate. A unit rate in the bill is labor dollars plus material for one unit.
উদাহরণ. A 2x2 fixture at 0.46 hr and $38.00 an hour is $17.48 of labor. With $84.00 of material the unit rate is $101.48. The labor units in this course are invented, not NECA's.
Labor unit, hours per each0.46
Crew rate per hour$38.00
Labor per each$17.48
Material per each$84.00
Unit rate$101.48
2 / 4
Per 100 ft means divide by 100
Conduit and wire are installed by length, so their labor units are given per 100 ft. The bill measures in feet. Divide the hours by 100 before you multiply by the crew rate, or a rate per foot becomes a rate per 100 ft and the line is a hundred times too high.
উদাহরণ. 1 in EMT at 9 hr per 100 ft is 0.09 hr per foot. At $38.00 that is $3.42 of labor, and with $3.40 of material, $6.82 per foot.
Hours per 100 ft9
Hours per ft0.09
Labor per ft$3.42
Rate per ft, material included$6.82
3 / 4
Keep the hours as their own total
The hours are what the field crew is budgeted, what the schedule is built on, and what labor burden is worked on in the bid. So the estimate keeps a labor hours total next to the dollar total. A lump sum for the rest of the scope has hours in it too. Leave them out and the crew is short and the burden is too low.
4 / 4
Unit rates stay on the base wage
Payroll taxes, workers' compensation, small tools, sales tax and markups are added once, later, as their own lines. If a unit rate already carries burden, the bid adds it a second time and nobody can see where.
Rate three lines and add the hours
Different items and numbers from your task. Type your answer first.
মাপমতো নয়
সমস্যা
Crew rate $38.00 an hour, base wage.
Dimmer switches: 24, at 0.36 hr each, material $27.50 each.
1 in EMT: 250 ft, at 9 hr per 100 ft, material $3.40 per ft.
The rest of the scope as one lump: 600 hr and $45,000 of material.
$13.68$27.50
Labor $13.68
Material $27.50
$13.68$27.50
Labor $13.68
Material $27.50
ধাপ 1 / 4
Rate for a dimmer switch
Hours times crew rate, plus material. What is the unit rate?
ইঙ্গিত: Labor first, then add the material.
0.36 × $38.00 = $13.68 of labor, plus $27.50 material: $41.18.
$3.42$3.40
Labor per ft $3.42
Material per ft $3.40
$3.42$3.40
Labor per ft $3.42
Material per ft $3.40
ধাপ 2 / 4
Rate per foot of EMT
The unit is per 100 ft. What is the rate per foot?
ইঙ্গিত: Divide the hours by 100 first.
9 ÷ 100 × $38.00 = $3.42 of labor, plus $3.40: $6.82 per foot.
$22,800$45,000
Labor $22,800
Material $45,000
$22,800$45,000
Labor $22,800
Material $45,000
ধাপ 3 / 4
Rate for the lump
The lump is quantity 1. Its hours at the crew rate plus its material. What is its rate?
ইঙ্গিত: The lump has labor in it, not only material.
600 hr × $38.00 = $22,800, plus $45,000: $67,800.
Hours by line
631.14 (8.64 + 22.5 + 600)
Hours by line
631.14 (8.64 + 22.5 + 600)
ধাপ 4 / 4
Labor hours, all lines
Switches, conduit and the lump. How many labor hours in total?
ইঙ্গিত: Hours per unit times quantity for each line, and the lump's hours as they are.
24 × 0.36 = 8.64 hr, 250 ft × 0.09 = 22.5 hr, and the lump 600 hr. Total 631.14 hr.
সংক্ষেপে. Hours per unit times crew rate, plus material, gives each rate. The hours are added up on their own, the lump's included.
নিজেকে যাচাই করুন
প্রশ্ন 1 / 3
Wire is listed at 1.50 hr per 100 ft. The crew rate is $40.00. What is the labor per foot?
That is the labor for 100 ft. The bill is in feet.
1.50 ÷ 100 × 40.00 = $0.60 per foot.
Hours are not dollars: multiply by the crew rate.
প্রশ্ন 2 / 3
A floor box takes 0.75 hr at a crew rate of $42.00 and $65.00 of material. What is its unit rate?
0.75 × 42.00 = 31.50, plus 65.00: $96.50.
প্রশ্ন 3 / 3
Why keep a labor hours total when the bill already shows dollars?
Dollars mix labor and material. Hours tell you how many people for how long.
This is a lump-sum subcontract. Hours are for your own planning and pricing.
Every line with labor adds hours, the lumps as well.