OpenConstruction Academy
সাইন ইন / নিবন্ধন
BN

কাজ 5-এর আগে তত্ত্ব · 10 মি

The second certificate: cumulative value, no double payment, VAT

সার্টিফিকেট 2: ইটের দাম দুবার দেবেন না

এই লেকচারের পর আপনি পারবেন

  1. Value a certificate cumulatively and deduct the amount previously certified.
  2. Spot materials claimed twice once they are built into the work.
  3. Add VAT at 15 % to the net amount due.
1 / 3

Every certificate starts from the beginning

Because a JBCC certificate is cumulative, each one revalues the whole job to date: work executed to date, plus materials still on site that pass the tests, times the certified share, less everything certified before. A mistake in one month is therefore corrected in the next, and a value counted twice in one month is paid twice unless someone sees it.

উদাহরণ. Certificate 2 net = 95 % × gross to date − certificate 1 net.
2 / 3

Materials move into the work

Last month's bricks on pallets were paid as materials on site. This month they are in the walls and paid inside the measured work. If the draft still lists them as materials, the employer pays for them twice. Check each material line against the site: anything built in leaves the materials list.

উদাহরণ. The overclaim is the double-counted value times the certified share, because only 95 % of it would have been paid.
Tiles claimed againR 23,600.00
Certified share0.95
Overclaim, excluding VATR 22,420.00
3 / 3

VAT on the certificate

A contractor registered for VAT charges 15 % on each amount certified (VAT Act 89 of 1991, section 7(1)(a)). The certificate states the net amount, then the tax. The employer pays the total within 14 calendar days of the date for issue, and the contractor pays its subcontractors within 7 calendar days of the employer's due date (clauses 25.10 and 25.13).

উদাহরণ. VAT is added after the reduction and after deducting previous certificates, on this month's net.

Check the contractor's second draft

Last month certified R 414,295.00 net, including tiles on site. This month the tiles are laid, but the draft lists them again.

মাপমতো নয়
সমস্যা
  • Certificate 1, net excluding VAT: R 414,295.00.
  • Work executed to date: R 698,000.00. No materials qualify this month.
  • The contractor's draft adds the tiles again: R 23,600.00.
ধাপ 1 / 4

Certified to date

95 % of the gross to date. What is it?

R 698,000.00 × 0.95 = R 663,100.00.

ধাপ 2 / 4

Net this certificate

Less certificate 1. What is the net amount, excluding VAT?

R 663,100.00 − R 414,295.00 = R 248,805.00.

ধাপ 3 / 4

Overclaim in the draft

What does the draft claim too much, excluding VAT?

R 23,600.00 × 0.95 = R 22,420.00.

R 663,1001−R 414,2952+R 37,3213?4
  • 1 Certified to date
  • 2 Certificate 1
  • 3 VAT 15 %
  • 4 Due
R 663,1001−R 414,2952+R 37,3213R 286,1264
  • 1 Certified to date
  • 2 Certificate 1
  • 3 VAT 15 %
  • 4 Due
ধাপ 4 / 4

Amount due with VAT

Add 15 % VAT to the net. What is due?

R 248,805.00 × 1.15 = R 286,125.75.

সংক্ষেপে. Revalue to date, remove what is built in from materials, deduct previous certificates, then add VAT.

নিজেকে যাচাই করুন

প্রশ্ন 1 / 3

Gross to date R 900,000.00, payment reduction 5 %, previously certified R 600,000.00. What is due with 15 % VAT?

900,000.00 × 0.95 = 855,000.00; less 600,000.00 = 255,000.00; with VAT R 293,250.00.
প্রশ্ন 2 / 3

Bricks paid as materials on site last month are now in the walls. Where do they appear on this certificate?

  • That pays them twice.

  • Right. They left the materials list when they were built in.

  • The certificate is cumulative: their value is in the work to date.

প্রশ্ন 3 / 3

Within how many days must the employer pay a certified amount under the JBCC PBA?

  • 7 days is the contractor's deadline to pay subcontractors (25.13).

  • Right. Clause 25.10.

  • Not under the PBA.