OpenConstruction Academy
Přihlásit se / Registrace
CS

Teorie před úlohou 3 · 11 min

Stored material, and over or under billing

Nenainstalovaný materiál a nadměrná/nedostatečná fakturace

Po této přednášce dokážete

  1. Say why material delivered but not installed distorts a cost-to-cost percent.
  2. Take uninstalled material out of the progress measure and add it back as revenue at cost.
  3. Compare earned revenue with gross billings to date and name the result: over billing (a contract liability) or under billing (a contract asset).
1 / 3

Delivered is not installed

Cost-to-cost assumes that every dollar of cost is a dollar of progress. Material bought and parked on site breaks that: the cost lands in the month of delivery, the percent jumps, and the margin on the material is recognized before anyone installs it. The guidance on input methods in ASC 606 deals with this case. When the material is not a separate deliverable, the owner controls it well before installation, its cost is significant to the job, and the contractor bought it rather than designed or made it, revenue equal to its cost is recognized and its cost is left out of the progress measure.

Příklad. Rooftop units delivered in March and set in May: their cost is in March's cost to date, but no rooftop work happened in March.
$400,000$100,000
  • Work in place $400,000
  • Stored on site, not installed $100,000
2 / 3

Material at cost: the formula

Take the material M out of both sides of the ratio: percent complete = (cost to date − M) / (estimate − M). Apply that percent to the contract value less M, then add M back at cost: earned revenue = (contract value − M) × percent + M. The material earns exactly its cost and no margin. When it is installed, it rejoins the measure and earns its share of margin as work.

Příklad. The plain formula would give $1,150,000 × 500,000 / 900,000 = $638,888.89: $13,888.89 of margin on material nobody has installed.
Cost to date less material$400,000
Estimate less material$800,000
Percent complete50%
Contract value less material, times the percent$525,000
Material, at cost$100,000
Earned revenue$625,000
3 / 3

Over billing and under billing

Compare earned revenue with what you have billed to date, gross: on the AIA G702 that is the total completed and stored to date, before retainage. Retainage is billed and earned; the owner only holds it back. Billed more than earned is over billing, the old WIP name for it is billings in excess of costs and estimated earnings, and under ASC 606 it is a contract liability: the owner has paid ahead for work you still owe. Earned more than billed is under billing, a contract asset. Sureties look hard at large under billings, because revenue claimed but not yet billed may never be billed.

Příklad. $640,000 billed against $600,000 earned is $40,000 over billed. Take this contract's 10% retainage off the billing first and the same job looks $24,000 under billed: the wrong sign, from the wrong line.
Billed to date, gross
$640,000
Earned revenue
$600,000

Stored switchgear on a school job

Another job. The electrical switchgear is on site, bought from a supplier, owned by the school district on delivery, not yet set.

Není v měřítku
Zadání
  • Contract value $5,600,000.00; cost to date $3,180,000.00; estimate at completion $4,980,000.00.
  • Cost to date includes $180,000.00 of switchgear, delivered, not installed.
  • G702: total completed and stored to date $3,460,000.00; total earned less 10% retainage $3,114,000.00.
$3,000,000.00
  • Work in place $3,000,000.00
  • Switchgear, stored $180,000.00
$3,000,000.00
  • Work in place $3,000,000.00
  • Switchgear, stored $180,000.00
Krok 1 z 4

The plain formula first

Contract value × cost to date / estimate, with the switchgear inside. What revenue would that show?

$5,600,000.00 × $3,180,000.00 / $4,980,000.00 = $3,575,903.61. Keep it for comparison.

Krok 2 z 4

Percent complete without the switchgear

Take the switchgear out of cost to date and out of the estimate. What is the percent complete?

($3,180,000.00 − $180,000.00) / ($4,980,000.00 − $180,000.00) = 62.5%.

Plain formula$3,575,903.61
Material at cost?
Plain formula$3,575,903.61
Material at cost$3,567,500.00
Krok 3 z 4

Earned revenue, material at cost

Apply the percent to the contract value less the switchgear, then add the switchgear back at cost. What is the earned revenue?

($5,600,000.00 − $180,000.00) × 62.5% + $180,000.00 = $3,567,500.00. The plain formula, $3,575,903.61, pulled $8,403.61 of margin forward on equipment nobody has set.

Billed to date, gross
$3,460,000.00
Earned revenue
$3,567,500.00
Billed to date, gross
$3,460,000.00
Earned revenue
$3,567,500.00
Krok 4 z 4

Over or under billing

Gross billed to date less earned revenue. What is the billing position? Under billing is negative.

$3,460,000.00 − $3,567,500.00 = −$107,500.00. Negative: the job is under billed, a contract asset. Against the net $3,114,000.00 the gap would look far bigger than it is.

Stručně. Stored material leaves the percent and comes back at cost. The billing position is gross billings less earned revenue: positive is over billed, negative is under billed.

Zkontrolujte se

Otázka 1 z 3

Which delivery comes out of the cost-to-cost measure until it is installed?

  • It was installed on arrival. Its cost is progress.

  • Making them is part of the contractor's work, so their cost measures progress.

  • Bought, not made, controlled by the owner and not yet installed: revenue at cost, out of the measure.

  • These are general conditions cost, used as the work goes on.

Otázka 2 z 3

Earned revenue is $2,150,000. The G702 shows total completed and stored to date $2,240,000, retainage $112,000, total earned less retainage $2,128,000. What is the billing position?

  • $2,240,000 − $2,150,000. Gross billing against earned revenue.

  • That compares the figure after retainage. Retainage is billed; use the gross.

  • That is the retainage, not the billing position.

  • The size is right, the sign is not: the job has billed more than it has earned.

Otázka 3 z 3

Contract value $2,000,000, estimate at completion $1,650,000, cost to date $810,000, of which $150,000 is purchased material stored on site. What is the earned revenue with the material at cost?

Percent ($810,000 − $150,000) / ($1,650,000 − $150,000) = 44%. Earned revenue ($2,000,000 − $150,000) × 44% + $150,000 = $964,000.00.