OpenConstruction Academy
Log ind / Tilmeld
DA

Teori før opgave 4 · 10 min

Price adjustment on delayed work

Attest 2: prisregulering af forsinket arbejde

Efter dette foredrag kan du

  1. Split a month's work into work done on programme and work done late.
  2. Apply the rule for contractor-caused delay: the lower of the programme month's and the actual month's indices.
  3. Compute F for a month that contains both.
1 / 3

The programme sets the month

The work programme (iş programı) says in which month each part of the work should be done. Price adjustment normally uses the indices of the month the work is actually done. If the contractor is late through its own fault, it must not profit from prices that rose while it was late.

Eksempel. A delay the administration caused is a different case: then the work is adjusted in the month it was actually done.
2 / 3

The lower of the two

For work delayed by the contractor, the Principles compare the indices of the month in which the programme placed the work with those of the month in which it was actually done, and apply the lower. When prices rise, that is the programme month: the contractor is paid as if it had been on time. When prices fall, it is the actual month: lateness never earns more.

Eksempel. Programme month Pn 1.028, actual month Pn 1.061, prices rising: the late work takes 1.028.
Pn, programme month1.03
Pn, month done1.06
Pn for the late work1.03
3 / 3

One month, two parts

A hakediş month may contain both kinds of work. Split An: the work that was programmed for this month takes this month's Pn; the late work takes the lower Pn. F is the sum of the two parts. Keep the split visible on the hakediş: it is what the controller asks for.

Eksempel. F = An,on time × 0.90 × (Pn − 1) + An,late × 0.90 × (Pn,lower − 1).

A month with late work

In month 2 the contractor did work worth 500,000.00. Of it, 200,000.00 was programmed for month 1 and is late by the contractor's fault.

Ikke i målestok
Opgaven
  • Work programmed for month 2, done on time: ₺300,000.00.
  • Late work, programmed for month 1, done in month 2: ₺200,000.00.
  • Pn of month 1: 1.03. Pn of month 2: 1.06. Both relative to the tender month.
Trin 1 af 3

F on the on-time work

Month 2's Pn. What is F on the on-time work?

₺300,000.00 × 0.90 × (1.06 − 1) = ₺16,470.00.

Trin 2 af 3

F on the late work

The lower of the two Pn. What is F on the late work?

₺200,000.00 × 0.90 × (1.03 − 1) = ₺5,040.00.

₺16,470₺5,040
  • On time ₺16,470
  • Late ₺5,040
₺16,470₺5,040
  • On time ₺16,470
  • Late ₺5,040
Trin 3 af 3

F for month 2

Add the two parts. What is F?

₺16,470.00 + ₺5,040.00 = ₺21,510.00. Applying month 2's Pn to all of it would pay ₺5,940.00 too much.

Kort sagt. Split the month by the programme, apply the lower Pn to contractor-caused late work, add the parts.

Test dig selv

Spørgsmål 1 af 3

Late work by the contractor's fault: An = 100,000.00, programme month Pn 1.030, actual month Pn 1.060. What is F on it?

100,000.00 × 0.90 × 0.030 = ₺2,700.00.
Spørgsmål 2 af 3

Indices fell between the programme month and the month the late work was done. Which applies?

  • That would pay the contractor more for being late.

  • Right. The lower of the two always applies to contractor-caused delay.

  • Late work is still adjusted, at the lower index.

Spørgsmål 3 af 3

The administration handed over drawings late, so the work slipped. Which month's indices apply?

  • That rule is for delay caused by the contractor.

  • Right. The contractor is not at fault.

  • The tender month gives the base indices, not the current ones.