OpenConstruction Academy
Log ind / Tilmeld
DA

Teori før opgave 1 · 9 min

Net first, waste last, round up at the end

Opmåling fra tegningen: fliser, plader, fodlister, hulkehlslister

Introduktion til kurset

Efter dette foredrag kan du

  1. Measure wall tiling as perimeter times height, less the openings inside it.
  2. Add waste once, then round board up to whole sheets.
  3. Tell where skirting stops and where cornice runs on.
1 / 4

What you lay is not what you order

Tiles and board are cut at every edge and some break. The laid area is the net area of the surface; the order is that area plus a waste allowance. Work the net area first and put the waste on once, at the end. Waste added twice buys tiles you will throw away.

2 / 4

Walls: perimeter times height, less the openings

Unroll the walls: the perimeter of the room times the tiled height gives the gross area. Take off each door and window that sits inside the tiled height, because no tile goes there. Then add the waste.

Eksempel. A laundry 2.00 × 1.80 m tiled to 2.4 m: perimeter 7.6 m, gross 18.24 m². A door 0.77 × 2.04 and a window 0.60 × 0.60 come off: 16.31 m² net. With 10% waste the order is 17.94 m².
7.6 m2.4 m
  • Tiled wall, unrolled
  • Door and window: no tiles, taken off
3 / 4

Board comes in whole sheets

Plasterboard is sold by the sheet. Add the net wall area and the ceiling, add the waste, divide by the area of one sheet, and round up. Round only at the end: rounding each wall up first buys sheets you do not need.

Eksempel. 15.46 sheets means you buy 16. A sheet cannot be bought in part.
Walls and ceiling, net45.55 m²
With 10% waste50.11 m²
One sheet, 1200 × 2700 mm3.24 m²
Sheets, before rounding15.46
4 / 4

Skirting stops, cornice runs on

Skirting sits on the floor, so it stops at every door and opening. A window is above it and does not interrupt it. Cornice sits at the ceiling and runs the full perimeter, over doors and openings alike. Both are measured net in metres, with any waste carried in the rate.

Line a study

A different room from your task, same rules. Type your answer first. A wrong guess costs nothing.

Ikke i målestok
Opgaven
  • Study 4.0 m × 3.4 m, ceiling 2.4 m. Walls and ceiling lined.
  • One door 0.87 m × 2.04 m, one window 1.5 m × 1.2 m.
  • Board sheets 1200 × 2700 mm, 3.24 m² each, bought whole. Waste 10% on board.
14.8 m2.4 m? m²
  • Lined wall, unrolled
  • Door and window, taken off
14.8 m2.4 m31.95 m²
  • Lined wall, unrolled
  • Door and window, taken off
Trin 1 af 4

Net wall area

Perimeter times height, less the door and the window. How many m²?

Perimeter 14.8 m × 2.4 m = 35.52 m². Less door 1.77 m² and window 1.80 m²: 31.95 m².

31.95??
  • Walls, net 31.95
  • Ceiling ?
  • Waste ?
31.9513.6
  • Walls, net 31.95
  • Ceiling 13.6
  • Waste 4.56
Trin 2 af 4

Board to order

Net walls plus the ceiling, plus 10% waste. How many m²?

Ceiling 4.0 m × 3.4 m = 13.60 m². (31.95 m² + 13.60 m²) × 1.10 = 50.11 m².

Board to order50.11 m²
One sheet3.24 m²
Whole sheets?
Board to order50.11 m²
One sheet3.24 m²
Whole sheets16
Trin 3 af 4

Sheets

Divide by one sheet and round up. How many sheets?

50.11 m² ÷ 3.24 m² = 15.46. You buy 16 sheets.

Perimeter14.8 m
Door opening-0.87 m
Skirting?
Perimeter14.8 m
Door opening-0.87 m
Skirting13.93 m
Trin 4 af 4

Skirting

The perimeter less the door width. How many metres?

14.8 m − 0.87 m = 13.93 m. The cornice would be the full 14.8 m.

Kort sagt. Net area first, waste once, then whole sheets. Skirting stops at doors; cornice does not.

Test dig selv

Spørgsmål 1 af 3

A floor is 3.00 × 2.00 m. You order tiles with 10% waste, then add another 10% 'for breakage'. What is wrong?

  • The 10% allowance is for cuts and breakage together.

  • 6.00 m² net plus one 10% allowance.

  • Floor tiles are cut at every edge too.

Spørgsmål 2 af 3

A room has a door, a window and a cased opening. Where does the cornice stop?

  • That is skirting. Cornice is at the ceiling, above them.

  • Doors, openings and windows are all below the ceiling line.

  • The window is below the ceiling. Nothing interrupts the cornice.

Spørgsmål 3 af 3

A shower room floor is 1.90 × 1.50 m. Order 10% extra. How many m² of floor tiles do you order?

1.90 × 1.50 = 2.85 m², times 1.10 = 3.14 m².