OpenConstruction Academy
Log ind / Tilmeld
DA

Teori før opgave 4 · 10 min

Schedule rates, the cost index and the estimate total

Prislistens poster med omkostningsindeks, analyserede poster uden

Efter dette foredrag kan du

  1. Raise a schedule item's base rate by the station cost index and round it to the paisa.
  2. Leave items analysed from market rates without the index.
  3. Build section totals and the estimate total from rounded rates times quantities.
1 / 3

What the cost index does

A schedule of rates is priced for one place and one date: CPWD's Delhi schedule for Delhi, a state schedule for its base. A building elsewhere costs more or less, so the department publishes a cost index for each station, a percentage that brings schedule rates to local price levels. The detailed estimate takes each schedule item at its base rate, raises it by the index, and rounds the result to the paisa.

Eksempel. Base rate 185.40 per m³ at a 9 % index: 185.40 × 1.09 = 202.09 per m³.
Base rate, per m³₹185.40
Cost index 9 %₹16.69
Rate in the estimate₹202.09
2 / 3

Analysed items take no index

Items that are not in the schedule are analysed from current market rates at the site, as in the brickwork and RCC sheets. Their basic rates are already today's local prices, so adding the cost index would raise them twice. State schedules say so plainly: rates of non-schedule items are worked out from market rates without the cost index. That is why the index cannot be one markup on the whole estimate.

Eksempel. An estimate of two sections: schedule items with the index, analysed items without it.
3 / 3

Round each rate, then multiply

Each rate is rounded to the paisa before it is multiplied by its quantity, because the rate is what the contract will hold. The line amount is rate times quantity; section totals add the lines; the estimate total adds the sections. The whole estimate here is before GST; how GST enters is set by the department's own instructions.

Eksempel. Raising a section total by the index instead of each rate gives a total that no line of the estimate can reproduce.

Price a short estimate

Two schedule items at a station with a 9 % cost index, and one item analysed from market rates.

Ikke i målestok
Opgaven
  • Schedule item A, earthwork: base ₹185.40 per m³, quantity 120 m³.
  • Schedule item B, plain concrete: base ₹4,860.00 per m³, quantity 6.5 m³.
  • Analysed item C, stone masonry: ₹5,872.54 per m³ from market rates, quantity 4 m³. Cost index 9%.
Trin 1 af 4

Rate of item A

Base rate plus the index, rounded to the paisa. What is A's rate?

₹185.40 × 1.09 = ₹202.09 per m³.

Trin 2 af 4

Rate of item B

Same rule. What is B's rate?

₹4,860.00 × 1.09 = ₹5,297.40 per m³.

Item A
₹24,251
Item B
₹34,433
Item A
₹24,251
Item B
₹34,433
Trin 3 af 4

Schedule section total

Rate times quantity for A and B, then add. What is the section total?

₹202.09 × 120 + ₹5,297.40 × 6.5 = ₹58,683.90.

₹58,684₹23,490
  • Schedule items ₹58,684
  • Analysed item ₹23,490
₹58,684₹23,490
  • Schedule items ₹58,684
  • Analysed item ₹23,490
Trin 4 af 4

Estimate total

Item C takes no index. What is the estimate total?

₹58,683.90 + ₹5,872.54 × 4 = ₹82,174.06. With the index on C as well, the estimate would be too high by ₹2,114.12.

Kort sagt. Index the schedule rates one by one, leave analysed rates as they are, then multiply and add.

Test dig selv

Spørgsmål 1 af 3

A schedule item has a base rate of 412.30 per m². The station cost index is 11 %. What is the rate in the estimate?

412.30 × 1.11 = ₹457.65 per m².
Spørgsmål 2 af 3

An item is analysed from current market rates at the site. Does it get the cost index?

  • The index adjusts schedule rates to the station; market rates are already local.

  • Right. Indexing it would raise it twice.

  • There is no half index.

Spørgsmål 3 af 3

Why round each indexed rate before multiplying by the quantity?

  • Right. Amounts follow from the rounded rate.

  • GST has nothing to do with it.

  • On large quantities half a paisa per unit becomes rupees.