The interim payment certificate: work, materials, reduction
Løbende betalingsattest 1
Efter dette foredrag kan du
List the lines of a JBCC payment certificate (clause 25.3).
Decide which materials on site may be certified under clause 25.4 and why off-site goods need a guarantee (25.5).
Compute the net amount certified on a first certificate.
1 / 3
What a certificate adds up
A JBCC interim payment certificate is cumulative: it values everything to date and deducts what was certified before. Clause 25.3 lists its lines: work executed, materials and goods, adjustment for security, cost fluctuations where the contract data provides for them, the gross amount, amounts previously certified, recovery of any advance, and tax. The quantity surveyor values; the principal agent certifies; the employer pays within 14 calendar days of the date for issue (clause 25.10).
Eksempel. On a first certificate the amount previously certified is nil, so the net equals the certified share of the gross.
2 / 3
Materials on site: four tests
Materials not yet built in are certified only if they are not delivered prematurely, are adequately stored and protected, and are insured (clause 25.4). Goods off site, at a fabricator's yard for example, are certified only against a guarantee (clause 25.5). Each test answers a risk: early deliveries tie up the employer's money, unprotected materials may spoil, uninsured ones may be lost, and goods off site may never arrive.
Eksempel. Cement stacked uncovered fails the protection test even if it is on site and insured.
3 / 3
The reduction is taken on the gross
The certified share of 95 % applies to the value of work and materials together. The payment reduction is thus 5 % of the gross value, not of the work alone. Practical completion is far away on a first certificate, so 95 % is the share to use.
Eksempel. Work R 412,500.00 plus qualifying materials R 23,600.00 is a gross of R 436,100.00; 95 % of it is certified.
R 391,875
Work executed R 391,875
Materials on site R 22,420
Reduction, 5 % R 21,805
Certificate 1 for a small clinic
The first valuation. Work to date is measured; four lots of materials are claimed.
Ikke i målestok
Opgaven
Work executed to date R 412,500.00.
Floor tiles for next month, on site, covered, insured: R 23,600.00. Doors, delivered four months before they are needed: R 15,600.00.
Timber stacked in the open, uncovered: R 3,200.00. Kitchen units at the supplier's yard, no guarantee: R 18,000.00.
Trin 1 af 4
Materials that qualify
Apply the tests of clauses 25.4 and 25.5. What value of materials is certified?
Hint: Premature, unprotected and off-site without a guarantee all fail.
Only the tiles pass: R 23,600.00. The doors are premature, the timber unprotected, the kitchen units off site without a guarantee.
Trin 2 af 4
Gross value
Work plus qualifying materials. What is the gross value?
Hint: Two numbers.
R 412,500.00 + R 23,600.00 = R 436,100.00.
Trin 3 af 4
Payment reduction
5 % of the gross. What is held back?
Hint: On the gross, materials included.
R 436,100.00 × 5 % = R 21,805.00.
1 Work
2 Materials
3 Reduction
4 Net
1 Work
2 Materials
3 Reduction
4 Net
Trin 4 af 4
Net amount certified
Nothing was certified before. What is the net amount, excluding VAT?
Hint: Gross less reduction less previous certificates (nil).
R 436,100.00 − R 21,805.00 = R 414,295.00. VAT at 15 % is added on the tax invoice.
Kort sagt. Value work to date, add only materials that pass the clause 25.4 and 25.5 tests, take 95 %, then deduct what was certified before.
Test dig selv
Spørgsmål 1 af 3
Work executed R 250,000.00, qualifying materials R 12,000.00, payment reduction 5 %, first certificate. Net amount certified, excluding VAT?
262,000.00 × 0.95 = R 248,900.00.
Spørgsmål 2 af 3
Roof sheeting is on site, covered and insured, but the programme roofs the building in ten weeks. Is it certified now?
It fails the first test: it is premature.
Right. It can be certified when it is no longer premature.
There is no partial value for materials.
Spørgsmål 3 af 3
Window frames are finished at the fabricator's yard. What would allow them on the certificate?
Proof of existence is not security.
Right.
An invoice does not protect the employer if the goods never arrive.