OpenConstruction Academy
Σύνδεση / Εγγραφή
EL

Θεωρία πριν από την εργασία 3 · 10 λ.

A change off the critical path: float first

Αλλαγή του ιδιοκτήτη εκτός κρίσιμης διαδρομής

Μετά από αυτή τη διάλεξη μπορείτε να

  1. Say what a Change Order states about Contract Time under A201-2017.
  2. Find how much of a change's added days float absorbs, and how much reaches the finish.
  3. Read an activity's float through its tightest successor, and carry the float that is left to the next event.
1 / 3

A change order prices time as well as money

Under A201-2017 Section 7.2.1 a Change Order states three things: the change in the Work, the adjustment to the Contract Sum, and the adjustment to the Contract Time, if any. The money is agreed from the estimate. The time is a schedule question: what the change does to Substantial Completion, not how many days it adds to one activity.

Παράδειγμα. A subcontractor who adds days to his own activity is right about his activity. Whether the owner owes time depends on the path that activity sits on.
2 / 3

Float absorbs the change first

Put the change into the activity and run the critical path again. If the activity had total float, the added days use it up first. Only the days beyond the float reach Substantial Completion. A change that fits inside the float costs the project float, not time, and the Contract Time adjustment is zero.

Παράδειγμα. A change adds 8 days to an activity with 3 days of total float: 5 working days reach the finish.
81-3253
  • 1 Days the change adds
  • 2 Total float on the path
  • 3 Delay to Substantial Completion
3 / 3

The tightest successor sets the float

An activity that feeds two paths has a different margin through each. Its total float is the smaller one, because the tighter path turns critical first. After a change, read the float from the recalculated schedule and do not subtract the change again by hand: the schedule already holds it.

Παράδειγμα. The activity's total float is 4, not 11. A change of 5 days uses all of it and moves the finish by one day.
Margin through the retail finishes
11
Margin through the paving
4

Two changes on one canopy

Another job. Activity S, an entrance canopy, starts at day 0 and lasts 11 working days. It feeds two successors.

Όχι υπό κλίμακα
Το πρόβλημα
  • S: early start 0, duration 11, early finish 11.
  • Successor T: late start 28. Successor U: late start 17.
  • CO-A adds 4 days to S. Months later CO-B adds 4 more.
  • Substantial Completion: Thursday, April 1, 2027.
S, early finish11
T, late start28
U, late start17
Total float of S?
S, early finish11
T, late start28
U, late start17
Total float of S6
Βήμα 1 από 4

Float before the changes

What is the total float of S?

Through U: 17 − 11 = 6. Through T the margin is larger. The tighter one counts: 6.

Βήμα 2 από 4

CO-A

CO-A adds 4 days. How much float does S have left after the critical path is run again?

6 − 4 = 2. The finish does not move, so CO-A adjusts the Contract Time by zero. Write the float used on its backup.

41-22?3
  • 1 Days CO-B adds
  • 2 Float left after CO-A
  • 3 Delay to the finish
41-2223
  • 1 Days CO-B adds
  • 2 Float left after CO-A
  • 3 Delay to the finish
Βήμα 3 από 4

CO-B

CO-B adds 4 more days to S. By how many working days does Substantial Completion move?

Only 2 days of float are left. 4 − 2 = 2 working days reach the finish. Measured against the original float, CO-B would wrongly look free.

Βήμα 4 από 4

In calendar days

The finish moves from Thursday, April 1, 2027 by 2 working days. How many calendar days does CO-B add to the Contract Time?

Friday is working day 1, Monday, April 5 is day 2. From Thursday to Monday is 4 calendar days.

Με λίγα λόγια. Float absorbs a change first. Each change uses the float the last one left. Only the excess moves the Contract Time.

Ελέγξτε τον εαυτό σας

Ερώτηση 1 από 3

An activity has 7 working days of total float. A change order adds 9 days to it. By how many working days does Substantial Completion move?

9 − 7 = 2 working days reach the finish.
Ερώτηση 2 από 3

A change adds four days to an activity with six days of total float. What does the Change Order state for the Contract Time?

  • Right. The finish does not move. The change costs float, and the backup should say how much.

  • Those days fall inside the float. Time follows the finish, not the activity.

  • Converting is right only for days that move the finish. These move nothing.

Ερώτηση 3 από 3

An activity feeds two paths, with eleven and four days of margin through them. What is its total float?

  • Right. The tighter path turns critical first.

  • That margin holds only through the looser path. The other path runs out first.

  • Margins through different paths are alternatives, not additions.