OpenConstruction Academy
Logi sisse / Registreeru
ET

Teooria enne ülesannet 3 · 9 min

Security under JBCC: the payment reduction and its release

Maksevähendus ja selle vabastamine

Pärast seda loengut oskad

  1. Name the security options in JBCC PBA clause 11 and what a payment reduction is.
  2. Apply the certified shares of clause 25.12: 95 % before practical completion, 97.5 % after, 100 % in the final certificate.
  3. Compute what practical completion releases.
1 / 3

What the employer holds as security

If the contractor fails, the employer needs money to finish the works. Clause 11 of the JBCC PBA provides it in one of the forms chosen in the contract data: a guarantee from a bank or insurer, a payment reduction (a share of each certificate held back), or both. Without any guarantee the employer may withhold up to 10 % of the contract sum, dropping to 2.5 % after practical completion (clause 11.4.1). In this course the contractor chose a fixed 5 % guarantee together with a payment reduction of 5 %.

Näide. In other contracts this is called retention. The ERP calls the field Retention %; the JBCC wording is payment reduction.
2 / 3

The certified share changes at practical completion

Clause 25.12 sets how much of the value of the work is certified: 95 % before practical completion, 97.5 % after it, and 100 % in the final certificate. So the reduction is 5 % until practical completion, then 2.5 %. The base is the value certified, which moves with remeasurement and instructions, not the original contract sum.

Näide. On a value of R 1,840,000.00: 5 % held is R 92,000.00; after practical completion 2.5 % is held.
R 1,748,000
  • Certified, 95 % R 1,748,000
  • Released at practical completion R 46,000
  • Released at final certificate R 46,000
3 / 3

Release in two steps

Practical completion releases half of the reduction, 2.5 % of the value at that date. The other 2.5 % stays until the final certificate, after the defects have been put right. The amount released is therefore the difference between what was held and what is still held, both on the value at practical completion.

Näide. If the value at practical completion differs from the contract sum, use the value. That is what the certificates have been based on.

Release at practical completion

A project's forecast value at practical completion is known. The contract has a 5 % payment reduction.

Mõõtkavata
Ülesanne
  • Contract sum R 1,905,000.00; forecast value at practical completion R 1,840,000.00, both excluding VAT.
  • Payment reduction 5 % [11.1.2]; certified share 95 % before and 97.5 % after practical completion [25.12].
Samm 1 / 3

Held just before practical completion

5 % of the value. How much is held?

R 1,840,000.00 × 5 % = R 92,000.00.

Samm 2 / 3

Held after practical completion

Only 2.5 % stays. How much is still held?

R 1,840,000.00 × 2.5 % = R 46,000.00.

Held before PC
R 92,000
Held after PC
R 46,000
Held before PC
R 92,000
Held after PC
R 46,000
Samm 3 / 3

Released at practical completion

What does practical completion release?

R 92,000.00 − R 46,000.00 = R 46,000.00. The remaining R 46,000.00 is released with the final certificate.

Lühidalt. 5 % held until practical completion, 2.5 % after it, nothing at the final certificate, always on the value certified.

Kontrolli ennast

Küsimus 1 / 3

The value at practical completion is R 3,200,000.00 and the payment reduction is 5 %. How much does practical completion release?

3,200,000.00 × 2.5 % = R 80,000.00.
Küsimus 2 / 3

What is the payment reduction a percentage of?

  • The certificates are based on the value of work, which changes.

  • Right.

  • Cost does not appear on a JBCC certificate.

Küsimus 3 / 3

When is the last 2.5 % paid?

  • Practical completion releases only half.

  • Right. Clause 25.12.

  • Security is held, not kept.