OpenConstruction Academy
Logi sisse / Registreeru
ET

Teooria enne ülesannet 6 · 12 min

The payment schedule and the statutory clock in NSW

Maksekinnitus ja seaduslik kell

Pärast seda loengut oskad

  1. Count business days as the NSW Security of Payment Act defines them.
  2. Find the last day for a payment schedule and the last day to apply for adjudication.
  3. Price the shortfall a payment schedule leaves, on the same basis as the claim.
1 / 3

A claim under the Act

The Building and Construction Industry Security of Payment Act 1999 (NSW) sits over the contract. A payment claim under it states that it is made under the Act and the amount claimed. A head contractor serves it with a supporting statement that its subcontractors have been paid. Once it is served, the Principal has a fixed number of business days to answer with a payment schedule.

Näide. The contract can shorten the Act's periods but cannot lengthen them.
2 / 3

Business days

The Act counts business days: not Saturday, not Sunday, not a public holiday, and not any day from 27 to 31 December. The day of service is not counted. The Principal must provide a payment schedule within ten business days after the claim is served, or earlier if the contract says so. If the schedule pays less than claimed, you have ten business days after receiving it to apply for adjudication.

Näide. A claim served just before Christmas runs into weekends, Christmas, Boxing Day, the five excluded December days and New Year's Day. Count on a calendar, one day at a time.
Saturday, Sundaynot counted
Public holidays in NSWnot counted
27 to 31 Decembernot counted
Day the claim is servednot counted
3 / 3

The shortfall in money

A schedule that withholds value lowers the amount payable by more than the value withheld changes, because GST and retention follow the value. Withheld value comes off the value excluding GST; retention falls by its percentage of it; GST falls by one tenth of it. Compare the amount payable as claimed with the amount payable as scheduled.

Näide. The schedule withholds $18,400.00 of value. With 5 % retention: $18,400.00 − $920.00 + $1,840.00 = $19,320.00 less to be paid.
Payable as claimed
$301,240
Payable as scheduled
$281,920

Run the clock

Another job, June 2027. The claim is served on Tuesday 8 June. King's Birthday, a NSW public holiday, falls on Monday 14 June. The schedule arrives on the last day allowed.

Mõõtkavata
Ülesanne
  • Claim served Tuesday 8 June 2027. Monday 14 June is a public holiday.
  • Schedule: preliminaries ($380,000) at 50% instead of 56%; a variation of $3,140.00 disallowed.
  • Retention 5% of the value. GST one tenth on the full value.
Samm 1 / 4

Last day for the schedule

Count ten business days after 8 June. On which date in June does the schedule fall due?

Counting from Wednesday 9 June and skipping two weekends and the holiday, the tenth business day is Wednesday 23 June.

Samm 2 / 4

Last day to apply

Ten more business days after the schedule is received. Which date in July is the last day to apply for adjudication?

Counting from Thursday 24 June and skipping the weekends, the tenth business day is Wednesday 7 July.

Samm 3 / 4

Calendar days

How many calendar days from service on 8 June to that last day?

From 8 June to 7 July is 29 calendar days. Diarise it the day the claim is served.

$25,9401−$1,2972+$2,5943?4
  • 1 Value withheld
  • 2 Retention not held
  • 3 GST not charged
  • 4 Shortfall
$25,9401−$1,2972+$2,5943$27,2374
  • 1 Value withheld
  • 2 Retention not held
  • 3 GST not charged
  • 4 Shortfall
Samm 4 / 4

Shortfall

What does the schedule withhold from the amount payable, after retention and with GST?

Withheld value $25,940.00. Less 5% retention, plus one tenth GST: $27,237.00 less to be paid.

Lühidalt. Count business days one by one on a calendar. Price the shortfall on the same basis as the claim.

Kontrolli ennast

Küsimus 1 / 3

Which of these is a business day under the NSW Act?

  • 27 to 31 December are excluded, whatever the weekday.

  • A public holiday is not a business day.

  • A weekday that is not a public holiday and not in late December.

  • Weekends never count.

Küsimus 2 / 3

The Principal provides no payment schedule within the time allowed. What follows?

  • The Act works the other way: silence has a cost for the Principal.

  • No schedule in time means the claimed amount is owed.

  • Under the Act it is the schedule, or its absence, that counts.

  • The Act works month by month.

Küsimus 3 / 3

A claim is served on Wednesday 12 April 2028. Good Friday is 14 April, Easter Monday 17 April, Anzac Day Tuesday 25 April. How many calendar days from service to the last day for the payment schedule?

Counting from Thursday 13 April and skipping Good Friday, Easter Monday, Anzac Day and the weekends, the tenth business day is Monday 1 May 2028: 19 calendar days after service.