OpenConstruction Academy
Kirjaudu / Rekisteröidy
FI

Teoria ennen tehtävää 6 · 8 min

Net the change, then add the terms once

Hinnoittele muutostyömääräys RFI 14:stä

Tämän luennon jälkeen osaat

  1. Price adds and deducts at the bid's own rates and net them.
  2. Credit deleted duct with its fittings.
  3. Apply the subcontract's change terms, not the bid's markups.
1 / 3

From RFI to change order

When the drawings leave a question, the contractor sends a request for information. The answer may come as a bulletin, a drawing revision issued after award, that adds or deletes work. Once the subcontract is signed, that change is priced as a change order, using the unit rates of the bid, so both sides can trace every figure back to what was agreed.

2 / 3

Net adds and deducts first

A bulletin often adds some work and removes other work. Price both the same way and take the deduct off before anything is marked up. Deleted duct comes out with its fittings, just as it went in with them. The burden, tools and tax then follow the net labor and the net material.

Esimerkki. 170 lb added, 90 lb deleted, with a 25% fittings allowance: 100 lb net to price.
Added straight duct, lb170
Deleted straight duct, lb-90
Net with fittings, lb100
3 / 3

Change terms are not bid markups

The subcontract usually states its own terms for changes: often a combined overhead and profit percentage on cost, and often no bond premium unless the bond is increased. Burden, tools and tax are still real costs of the changed work, so they stay in the cost and the percentage is worked on them as well.

Price a small change order

Different numbers and terms from your task. Round each step to the cent.

Ei mittakaavassa
Tehtävä
  • Electrical added: 20 hr at $38.00, material $940.00.
  • Duct: 170 lb added, 90 lb deleted, both straight; fittings 25%. Labor 0.07 hr per lb at $42.00; material $1.40 per lb.
  • Change terms: burden 28% and tools 2.5% on labor, tax 8.25% on material, then overhead and profit combined 10% on that cost. No bond.
Added, lb
212.5
Deleted, lb
112.5
Added, lb
212.5
Deleted, lb
112.5
Vaihe 1/4

Net duct pounds

Added minus deleted, then fittings. How many lb?

(170 − 90) × 1.25 = 100 lb.

??
  • Labor ?
  • Material ?
$1,054$1,080
  • Labor $1,054
  • Material $1,080
Vaihe 2/4

Direct cost

Electrical labor and material plus duct labor and material. What is the direct cost?

Labor $1,054.00, material $1,080.00. Direct cost $2,134.00.

$2,1341?2?3?4
  • 1 Direct cost
  • 2 Burden and tools
  • 3 Tax
  • 4 Cost
$2,1341+$3212+$89.103$2,5454
  • 1 Direct cost
  • 2 Burden and tools
  • 3 Tax
  • 4 Cost
Vaihe 3/4

Cost with burden, tools and tax

Add burden and tools on labor and tax on material. What is the cost?

Burden and tools $321.47, tax $89.10. Cost $2,544.57.

$2,5451?2?3
  • 1 Cost
  • 2 Overhead and profit
  • 3 Change order
$2,5451+$2542$2,7993
  • 1 Cost
  • 2 Overhead and profit
  • 3 Change order
Vaihe 4/4

Change order price

Overhead and profit combined on the cost, no bond. What is the price?

$2,544.57 × 1.10 = $2,799.03. No bond under these terms.

Lyhyesti. Net the work at bid rates, add burden, tools and tax as in the bid, then the change terms once.

Testaa itsesi

Kysymys 1/3

A bulletin deletes a duct segment you priced with a fittings allowance. How do you credit it?

  • Its fittings were priced too, so they come out with it.

  • A deduct is priced the same way as an add.

  • The change order is the net of adds and deducts.

Kysymys 2/3

A change costs $5,000 with burden, tools and tax. The terms allow 15 % overhead and profit combined and no bond. What is the price?

5,000 × 1.15 = $5,750.00.
Kysymys 3/3

Why are burden and tax inside the base for the change's overhead and profit?

  • The percentage is worked on cost, and they are cost.

  • Markups are worked on cost. Burden and tax are part of the cost.

  • That leaves part of the cost without its overhead and profit.