OpenConstruction Academy
Kirjaudu / Rekisteröidy
FI

Teoria ennen tehtävää 2 · 10 min

From cost to complete rate: water charges, then profit and overheads

Kaksi urakoitsijatarjousta CPWD-yksikköhintaa vastaan

Tämän luennon jälkeen osaat

  1. Add 1 % water charges on W, then 15 % contractor's profit and overheads on the new total.
  2. Explain why two percentages in sequence are not the same as their sum.
  3. Compare a quote with the analysed rate for a whole bill line.
1 / 3

Two percentages, each on its own base

The CPWD analysis of rates closes every sheet the same way. First it adds 1 % water charges on W, the cost of materials and labour, for the water the work uses. Then it adds 15 % contractor's profit and overheads (CPOH) on W plus water charges. The second percentage is taken on the total after the first, so the water charge also carries profit and overheads.

Esimerkki. W of 20,000.00 becomes 20,200.00 with water, and 23,230.00 with CPOH.
W, materials and labour₹20,000.00
Water charges, 1 % of W₹200.00
CPOH, 15 % of W + water₹3,030.00
Total for the sheet quantity₹23,230.00
2 / 3

Why 1 % plus 15 % is not 16 %

Applied one after the other, the factors multiply: 1.01 × 1.15 = 1.1615, not 1.16. The difference, 0.15 % of W, is the profit and overheads on the water charges. On one rate it looks like small change; across a bill line of tens of cubic metres it is a real sum, and a quote that applies 16 % in one step is short by exactly that amount.

Esimerkki. On W = 20,000.00 the one-step 16 % gives 23,200.00, which is 30.00 short of the analysed 23,230.00.
3 / 3

Percentages apply to the whole of W

Water charges and CPOH are taken on everything in W: materials, carriage, labour, plant and sundries. Overheads and profit are a share of the contractor's turnover, not of the wage bill only. A quote that applies 15 % to labour alone leaves the materials without overheads and profit and is too low for a reason the analysis cannot defend.

Esimerkki. The rate per unit is the sheet total divided by the sheet quantity, rounded to the paisa. The bill line amount is that rate times the measured quantity.

Complete the stone masonry rate

W for 10 m³ of stone masonry is known. Add the two percentages, find the rate per m³ and price a bill line of 12 m³.

Ei mittakaavassa
Tehtävä
  • W for 10 m³: ₹50,560.00.
  • Water charges 1 % on W; CPOH 15 % on W plus water.
  • Bill line quantity: 12 m³.
Vaihe 1/4

Water charges

1 % of W. What are the water charges for the sheet?

₹50,560.00 × 1 % = ₹505.60.

₹50,5601+₹5062?3?4
  • 1 W
  • 2 Water 1 %
  • 3 CPOH 15 %
  • 4 Total
₹50,5601+₹5062+₹7,6603₹58,7254
  • 1 W
  • 2 Water 1 %
  • 3 CPOH 15 %
  • 4 Total
Vaihe 2/4

Sheet total with CPOH

Add 15 % on W plus water charges. What is the total for 10 m³?

(₹50,560.00 + ₹505.60) × 1.15 = ₹58,725.44.

Vaihe 3/4

Rate per m³

Divide by the sheet quantity and round to the paisa. What is the rate per m³?

₹58,725.44 ÷ 10 = ₹5,872.54 per m³.

Vaihe 4/4

Bill line amount

Rate times the measured quantity. What is the line amount for 12 m³?

₹5,872.54 × 12 = ₹70,470.48. A quote at 16 % in one step would come to ₹90.96 less on this line.

Lyhyesti. W, then 1 % water on W, then 15 % on the new total, then divide by the sheet quantity. Compare quotes on the line amount, where small rate errors become visible sums.

Testaa itsesi

Kysymys 1/3

W for 10 m³ of a work item is 18,400.00. With 1 % water charges and 15 % CPOH, what is the complete rate per m³?

18,400.00 × 1.01 × 1.15 = 21,371.60 for 10 m³, so ₹2,137.16 per m³.
Kysymys 2/3

A quote applies 15 % profit and overheads to the labour lines only. What is wrong?

  • Overheads and profit are a share of the whole cost, materials included.

  • Right. The analysis applies it to the full total.

  • The base is wrong, not the percentage.

Kysymys 3/3

Why is 1.01 × 1.15 the right factor and not 1.16?

  • Right. Sequential percentages multiply.

  • Rounding moves a rate by at most half a paisa; the gap here is 0.15 % of W.

  • The analysis is worked before GST.