Reforecast the estimate at completion and see when it passes the contract value.
Say why cost-to-cost on its own shows only part of a loss, and which part.
Size the provision for anticipated loss so that gross profit to date equals the whole loss.
1 / 3
When the estimate passes the contract value
A reforecast raises the cost to complete: a subcontractor defaults and the replacement costs more, work fails inspection and has to be redone, a price goes up. The estimate at completion rises with it. Contract value does not: unsigned change orders and claims stay out until the owner agrees. Once the estimate is above the contract value, the job will lose the difference.
Primjer. Against a contract value of $2,450,000, an estimate of $2,500,000 means the job loses $50,000.
1 Estimate before the reforecast
2 Replacement subcontractor
3 Rework
4 Estimate after the reforecast
2 / 3
Cost-to-cost shows only part of the loss
Earned revenue still follows progress. At 40% complete the job has earned 40% of the contract value and spent 40% of the estimate, so the gross profit to date is 40% of the loss. The rest would land in later months as the work is done. US GAAP does not wait: for construction-type contracts the provision for losses in ASC 605-35, which stayed in force when ASC 606 replaced the old revenue guidance, requires the entire anticipated loss in the period it becomes evident.
Primjer. Of a $50,000 loss, $20,000 is already in gross profit to date. The provision carries the other $30,000.
$20,000$30,000
Shown by cost-to-cost at 40% $20,000
Still to come: the provision $30,000
3 / 3
Booking the provision
Provision = gross profit to date on the new estimate − the whole anticipated loss. It is a cost, booked as an accrual at the close; in this ERP it sits on its own cost head, LOSS, so it never mixes with cost of the work. After it, gross profit to date equals the whole loss. In the months that follow, the remaining work shows its own share of the loss and the provision is used up against it; at completion it is zero. Stored material stays at cost while you do this: the percent excludes it, as before.
Primjer. If gross profit to date is still positive after the reforecast, the provision is larger than the loss: it must wipe out that profit first.
Gross profit to date, new estimate−$20,000
Whole anticipated loss−$50,000
Provision, accrued cost$30,000
A parking structure turns into a loss
Another job, with purchased precast stair units stored on site. The reforecast arrives two days before the close.
Nije u mjerilu
Zadatak
Contract value $6,250,000.00, no change orders pending. Cost to date $3,900,000.00, including $120,000.00 of stored precast stairs.
Estimate at completion before the reforecast $5,950,000.00.
Reforecast: waterproofing subcontractor replaced, cost to complete up $310,000.00; deck coating rework, up $95,000.00.
1 Estimate before
2 Waterproofing
3 Rework
4 Estimate after
1 Estimate before
2 Waterproofing
3 Rework
4 Estimate after
Korak 1 od 4
New estimate at completion
Add both increases to the estimate. What is the estimate at completion now?
Savjet: The cost to complete moves; cost to date does not.
Contract value less the new estimate. What does the job lose? Enter a loss as a negative number.
Savjet: Estimated gross profit, as in task 2. It is now below zero.
$6,250,000.00 − $6,355,000.00 = −$105,000.00.
Korak 3 od 4
What cost-to-cost shows
Rework earned revenue on the new estimate, stairs at cost, and take off cost to date. What is the gross profit to date before any provision?
Savjet: (Contract value − material) × (cost to date − material) / (estimate − material) + material, then less cost to date.
Earned revenue $3,836,343.22, less cost to date $3,900,000.00: −$63,656.78. Only part of the −$105,000.00 loss shows.
$63,656.78?
Shown by cost-to-cost $63,656.78
Provision ?
$63,656.78$41,343.22
Shown by cost-to-cost $63,656.78
Provision $41,343.22
Korak 4 od 4
The provision
How much accrued cost brings gross profit to date down to the whole loss?
Savjet: Gross profit to date less the whole loss.
−$63,656.78 − (−$105,000.00) = $41,343.22. Booked on the LOSS head, it takes gross profit to date to −$105,000.00.
Ukratko. Reforecast first. If the estimate passes the contract value, rework revenue on the new estimate, then book only the part of the loss that cost-to-cost has not already shown.
Provjerite se
Pitanje 1 od 3
A job's estimate at completion is now $40,000 above its contract value. The job is 25% complete. When is the $40,000 loss recognized?
That is what cost-to-cost does on its own. A loss contract needs the rest provided for now.
The entire anticipated loss goes in the period it becomes evident.
Waiting would show profit or a small loss for months on a job known to lose money.
An unagreed claim is not in the contract value, so it cannot hold the loss back.
Pitanje 2 od 3
Before the reforecast the job showed gross profit to date of $30,000. On the new estimate cost-to-cost shows −$12,000, and the whole anticipated loss is $45,000. What provision do you book?
That books the whole loss again. $12,000 of it is already in gross profit to date.
−$12,000 − $33,000 = −$45,000: gross profit to date now equals the whole loss.
That starts from the old gross profit. Rework revenue on the new estimate first.
That is the part cost-to-cost already shows. The provision is the part still to come.
Pitanje 3 od 3
Contract value $900,000, estimate at completion after the reforecast $960,000. The job is 30% complete on cost, with no stored material. What provision for anticipated loss do you book?
Whole loss $900,000 − $960,000 = −$60,000. Cost-to-cost shows 30% of it, −$18,000. Provision −$18,000 − (−$60,000) = $42,000.00.