OpenConstruction Academy
Prijava / Registracija
HR

Teorija prije zadatka 2 · 8 min

How long the extension is: § 6 (4) VOB/B

Nacrti stižu: koliko dana?

Nakon ovog predavanja moći ćete

  1. Name the three parts of an extension under § 6 (4).
  2. Count a period in working days.
  3. Say why only critical work moves completion.
1 / 3

Duration, restart, season

The extension is not just the days the cause lasted. Work rarely restarts the next morning: materials must be ordered, crews brought back. And if the delay pushes work into a worse season, the season costs time too. § 6 (4) names all three.

Primjer. Doors held up 8 days; the joiner needs 2 days to remobilise; no season change: 10 days.
Duration
€8
Restart
€2
Season
€0
2 / 3

The critical path decides

Only delay to work on the critical path moves completion. If another crew keeps working on activities with float, the site is still hindered where it matters. The claim says which activity was stopped and that it was critical.

Primjer. Facade work with 20 days of float held up for 5 days: no extension, though the notice was right.
Česta pogreška

Calendar days

The contract says how days are counted. Here it is working days, Monday to Friday, without public holidays. Counting the calendar from the first to the last day inflates the claim and makes the client doubt all of it.

Primjer. Monday to the Wednesday of the next week is 10 calendar days but 8 working days.

An extension in three parts

Different numbers from your task.

Nije u mjerilu
Zadatak
  • The cause lasted 8 working days.
  • Restart takes 2 days; the shift into winter costs 1 expected frost day.
Korak 1 od 1

Extension

How many working days are claimed?

8 + 2 + 1 = 11.

Ukratko. Count the duration in the contract's days, then add restart and season.

Provjerite se

Pitanje 1 od 3

Which is not part of § 6 (4)?

  • Right.

  • It is part.

  • It is part.

Pitanje 2 od 3

A hindered activity has 20 days of float and is held up for 6. Extension?

  • Right.

  • Float absorbs it.

  • No sharing rule.

Pitanje 3 od 3

Stop of 7 working days, restart 3, no season change. Extension?

7 + 3 = 10.

Izvori

Besplatni službeni tekstovi. Predavanje navodi brojeve odredbi i prepričava pravila vlastitim riječima.