OpenConstruction Academy
Кіру / Тіркелу
KK

2-тапсырма алдындағы теория · 11 мин

K2 and K7: surcharges on the right base

K7 және K2: үстемелер дұрыс негізде

Бұл дәрістен кейін сіз мынаны үйренесіз

  1. Build the overall surcharge (Gesamtzuschlag) of K2 from its four parts, each on its own base.
  2. Explain why the percentages multiply instead of adding up.
  3. Price an item on K7 from labour and other costs, as cost and as price.
1 / 3

What the four surcharges cover

K2 of ÖNORM B 2061 turns costs into prices with four surcharges. Geschäftsgemeinkosten (GGK) pay for the firm itself: head office, management, insurance. Bauzinsen or Finanzierungskosten pay for money tied up between spending and being paid. Wagnis covers the risk the firm carries, Gewinn is the profit. Each comes from the firm's own figures and must be explainable if the client asks.

Мысал. The surcharges are a property of the bid, the same for every item; this course applies one rate to labour and to other costs alike.
2 / 3

Each surcharge on the sum before it

GGK are taken on the base, the costs. Financing is taken on base plus GGK. Wagnis and Gewinn are taken on the sum so reached. So the factors multiply: (1 + GGK) × (1 + financing) × (1 + Wagnis + Gewinn) − 1 gives the overall surcharge, stated in percent to two decimals. Adding the percentages gives less, and the gap is money the firm would lose on every item.

Мысал. GGK 9 %, financing 1.5 %, Wagnis 2 % and Gewinn 4 %: 1.09 × 1.015 × 1.06 − 1 = 17.27 %, not 16.5 %.
Base1
After GGK 9 %1.09
After financing 1.5 %1.11
After Wagnis and Gewinn 6 %1.17
3 / 3

K7: the item price

K7 builds each item from time value × hourly rate for labour, plus other costs (Sonstiges: materials from K4 with breakage and waste, plant). As costs it uses B18 and the bare other costs. As a price it uses B21 = B18 × (1 + overall surcharge) and the other costs raised by the same surcharge. The price is what goes in the bid; the cost calculation is what lets you check it.

Мысал. If the overall surcharge were simply 16.5 %, every price would be about 0.66 % too low.

Price a wall on K7

A firm's K2 has four surcharges. Build the overall surcharge, the crew's hourly price and the K7 price of a wall item.

Масштабсыз
Есеп шарты
  • K2: GGK 9 % on the base; financing 1.5 % on base + GGK; Wagnis 2 % and Gewinn 4 % on the sum reached.
  • B18 €48.04 per hour. Wall item: 0.8 h/m², other costs €44.20 per m² (from K4, with breakage).
3 қадамның 1-і

Overall surcharge

Multiply the factors and subtract 1. What is the overall surcharge in percent, two decimals?

1.09 × 1.015 × 1.06 − 1 = 17.27%. Adding the four gives only 16.5 %.

3 қадамның 2-і

B21 Mittellohnpreis

B18 raised by the overall surcharge. What is B21?

€48.04 × (1 + 17.27%) = €56.34 per hour.

Cost
€82.63 (€38.43 + €44.20)
Price
€96.90 (€45.07 + €51.83)
Cost
€82.63 (€38.43 + €44.20)
Price
€96.90 (€45.07 + €51.83)
3 қадамның 3-і

K7 price per m²

Labour at B21 plus other costs raised by the surcharge. What is the item price?

0.8 × €56.34 = €45.07; €44.20 × (1 + 17.27%) = €51.83; price €96.90 per m².

Қысқаша. Surcharges stack, each on the sum before it. K7 then uses B21 for labour and the same surcharge on other costs.

Өзіңізді тексеріңіз

3 сұрақтың 1-і

GGK 8 %, financing 2 %, Wagnis and Gewinn together 5 %. What is the overall surcharge in percent, to two decimals?

1.08 × 1.02 × 1.05 − 1 = 15.67 %.
3 сұрақтың 2-і

Financing costs are a percentage of what?

  • In K2 they are taken on base plus GGK.

  • Right. Each surcharge rides on the sum before it.

  • The bid price is the result, not a base.

3 сұрақтың 3-і

Why is the K7 cost calculation kept beside the price?

  • The client pays the price.

  • Right.

  • K7 has both.