OpenConstruction Academy
Кіру / Тіркелу
KK

1-тапсырма алдындағы теория · 11 мин

Measuring a suspended slab to the bill preambles

Талап үшін 1-деңгей плитасын қайта өлшеу

Курсқа кіріспе

Бұл дәрістен кейін сіз мынаны үйренесіз

  1. Say which unit each slab item is measured in: concrete, soffit formwork, edge formwork, reinforcement.
  2. Tell a recess from a void and apply the deduction threshold to every opening.
  3. Measure edge formwork round the slab and round every deducted void.
1 / 3

One slab, four units

A suspended slab is billed as four items, each in its own unit. Concrete is the net volume placed, in cubic metres. Soffit formwork is the surface it supports, in square metres. Edge formwork is a length, in metres, with its height stated, because a 150 mm edge and a 300 mm edge are not the same work. Reinforcement is the mass from the bar schedule, in tonnes. Laps, chairs, spacers and tie wire are in the rate, so they are never added to the mass.

Мысал. Concrete and soffit share one net area. Measure it once, then multiply by the thickness for the concrete.
Concretem³, net volume placed
Soffit formworkm², surface supported
Edge formworkm, height stated
Reinforcementt, from the bar schedule
2 / 3

A recess is not a void

A recess cut from the outline leaves no slab at all, so it is simply outside the measurement: take it off the overall rectangle. A void is a hole inside the slab, such as a lift shaft or a stair. The preambles set a threshold: a void at or under it is not deducted and its sides are not formed. A void over it comes out of the concrete and the soffit.

Мысал. Slab outline 12.00 m × 8.00 m, a corner recess 3.00 m × 2.00 m, one stair void 2.00 m × 1.50 m: 96 − 6 − 3 leaves 87 m². Plan, not to scale.
12.0 m8.0 m87.00 m²
  • Slab, measured
  • Stair void and corner recess, no concrete
3 / 3

Edges: the outline, plus every deducted void

Edge formwork runs round the outside of the slab and round the sides of every void that was deducted. A rectangular recess at a corner does not change the perimeter: the two sides it adds replace the two it removes. Openings under the threshold add nothing, because the preambles do not measure them.

Мысал. Same slab: perimeter 40.00 m with or without the recess, plus 7.00 m round the stair void.
Perimeter, plain rectangle
40.0 m
Perimeter with the corner recess
40.0 m
With the stair void sides
47.0 m (40.0 m + 7.0 m)

Measure another slab

A different job: a Level 2 slab on a medical suites building. Work through the four bill items.

Масштабсыз
Есеп шарты
  • Outline 38.5 m × 18.5 m, with a corner recess 6.0 m × 4.5 m. Slab 0.24 m thick.
  • One stair void 4.2 m × 2.6 m. Two riser voids 0.9 m × 0.7 m. Ten penetrations 0.40 m × 0.40 m.
  • Threshold: no deduction for a void of 0.50 m² or less.
  • Bar schedule, kg: bottom 6,120, top 5,340, trimmers 1,280, starters and ligatures 2,950.
38.5 m18.5 m? m²
  • Slab, measured
  • Recess and voids, deducted
38.5 m18.5 m673.07 m²
  • Slab, measured
  • Recess and voids, deducted
4 қадамның 1-і

Net area

Take off the recess and every void over the threshold. What is the net area for concrete and soffit?

38.5 m × 18.5 m = 712.25 m². The recess is 27.00 m². The stair void and the two riser voids are 12.18 m². Net area 673.07 m². The penetrations stay in.

Net area, m²673.07
Thickness, m0.24
Concrete, m³?
Net area, m²673.07
Thickness, m0.24
Concrete, m³161.54
4 қадамның 2-і

Concrete

Multiply the net area by the thickness. How many m³ of concrete?

673.07 m² × 0.24 m = 161.54 m³.

Slab perimeter
114.0 m
Edge formwork
?
Slab perimeter
114.0 m
Edge formwork
134.0 m (114.0 m + 20.0 m)
4 қадамның 3-і

Edge formwork

Perimeter of the slab plus the sides of the deducted voids. How many metres?

Perimeter 114.0 m, the same as without the recess. Stair void and two riser voids add 20.0 m. Edge formwork 134.0 m.

6,1205,3402,950
  • Bottom, kg 6,120
  • Top, kg 5,340
  • Trimmers, kg 1,280
  • Starters, ligatures, kg 2,950
6,1205,3402,950
  • Bottom, kg 6,120
  • Top, kg 5,340
  • Trimmers, kg 1,280
  • Starters, ligatures, kg 2,950
4 қадамның 4-і

Reinforcement

Add the four groups of the bar schedule. How many tonnes?

6,120 + 5,340 + 1,280 + 2,950 kg, divided by 1,000, is 15.69 t.

Қысқаша. One net area serves concrete and soffit. Edges follow the outline and every deducted void. Mass comes from the bar schedule as it stands.

Өзіңізді тексеріңіз

3 сұрақтың 1-і

A slab has fourteen penetrations of 0.40 m × 0.40 m. The threshold is 0.50 m². What do you do with them?

  • Concrete and soffit share one net area. Under the threshold, neither loses anything.

  • Each is 0.16 m², under the threshold, so the preambles leave them in.

  • That is how a void over the threshold is treated.

  • The threshold applies to each void, not to the group.

3 сұрақтың 2-і

A rectangular recess 5.00 m × 3.00 m is cut from one corner of a rectangular slab. What happens to the edge formwork?

  • The two sides you lose are replaced by the two sides of the recess.

  • That counts the recess sides on top of the full rectangle.

  • A corner recess swaps two edges for two edges of the same total length.

  • No slab is there at all. A recess is outside the measurement.

3 сұрақтың 3-і

Slab 24.00 m × 16.00 m, 200 mm thick. One stair void 4.50 m × 2.40 m and eight penetrations 0.20 m × 0.40 m. Threshold 0.50 m². How many m³ of concrete?

384.00 − 10.80 = 373.20 m². × 0.20 = 74.64 m³.