OpenConstruction Academy
Кирүү / Катталуу
KY

3-тапшырма алдындагы теория · 11 мүн

Reinforced concrete: what the concrete rate pays and what it does not

RCC M25: бетон наркына эмне кирет

Бул лекциядан кийин сиз төмөнкүнү үйрөнөсүз

  1. Price an RCC analysis for 1 m³ including plant, then add water charges and CPOH.
  2. Keep reinforcement out of the concrete rate when the bill pays it as its own item by weight.
  3. Take the reinforcement quantity from the bar bending schedule and put a value on double payment.
1 / 3

Concrete by volume, steel by weight

IS 1200, the Indian method of measurement, measures concrete in m³ and reinforcement separately by weight. The CPWD schedule follows the same split: the RCC item pays the concrete, formwork aside, and a reinforcement item pays steel per kg, cut, bent, placed and bound. The reason is practical. The amount of steel per m³ varies from a lightly reinforced slab to a heavily reinforced column, so one rate per m³ with steel inside would be right for no member.

Мисал. If the RCC analysis sheet lists TMT bars and the bill also has a reinforcement item, the steel is paid twice. Strike it from the concrete sheet.
2 / 3

The bar bending schedule gives the steel quantity

The designer's bar bending schedule (BBS) lists every bar: mark, diameter, number, cut length and weight. The weight of a bar follows from its nominal mass per metre, which for round steel is close to d²/162 kg per metre with d in mm. The reinforcement item is the total weight in kg from the BBS, not the steel coefficient of the concrete sheet.

Мисал. A 12 mm bar weighs about 144 ÷ 162 = 0.89 kg per metre.
8 mm bars, kg412.6
10 mm bars, kg538.25
12 mm bars, kg701.4
Reinforcement item, kg1,652.25
3 / 3

Plant is part of W

A concrete mixer and a needle vibrator are consumed by the work just as cement is. Their day-rates times the coefficients go into W, and the 1 % water charges and 15 % CPOH are taken on them too. The sheet for RCC is often written for 1 m³, so there is nothing to divide at the end.

Мисал. Leaving the steel in a concrete rate of a 30 m³ line at 110 kg/m³ pays for about 3.3 t of steel that the reinforcement line pays again.

Analyse 1 m³ of RCC M20

An RCC M20 sheet for 1 m³. It also lists 110 kg of TMT bars, which the bill pays elsewhere. Price the concrete rate correctly and value the mistake.

Масштабсыз
Маселе
  • Cement, sand and aggregate ₹5,075.00; mixer and vibrator ₹192.00; mason, beldar and bhisti ₹1,930.50.
  • The sheet also lists TMT bars: 110 kg at ₹66.00 per kg.
  • BBS: 8 mm 412.6 kg, 10 mm 538.25 kg, 12 mm 701.4 kg. Concrete line quantity 8 m³.
4 кадамдын 1-си

W without steel

Add materials, plant and labour, leaving out the bars. What is W for 1 m³?

₹5,075.00 + ₹192.00 + ₹1,930.50 = ₹7,197.50.

₹7,1981+₹71.982?3?4
  • 1 W
  • 2 Water 1 %
  • 3 CPOH 15 %
  • 4 Rate
₹7,1981+₹71.982+₹1,0903₹8,3604
  • 1 W
  • 2 Water 1 %
  • 3 CPOH 15 %
  • 4 Rate
4 кадамдын 2-си

Complete rate per m³

Add 1 % water, then 15 % CPOH. What is the rate per m³?

₹7,197.50 × 1.01 × 1.15 = ₹8,359.90 per m³.

4 кадамдын 3-си

Reinforcement quantity

Add up the BBS. How many kg go on the reinforcement line?

412.6 + 538.25 + 701.4 = 1,652.25 kg.

4 кадамдын 4-си

Value of double payment

If the bars stayed in the concrete rate, how much would the 8 m³ line overpay?

110 × ₹66.00 = ₹7,260.00 per m³, × 1.1615 = ₹8,432.49, × 8 = ₹67,459.92 paid twice.

Кыскача. Concrete in m³ without steel, steel in kg from the BBS. Each sheet line should be paid once in the whole bill.

Өзүңүздү текшериңиз

3 суроонун 1-си

A BBS lists 8 mm bars 240.50 kg, 12 mm bars 615.75 kg and 16 mm bars 380.00 kg. What quantity goes on the reinforcement line, in kg?

240.50 + 615.75 + 380.00 = 1,236.25 kg.
3 суроонун 2-си

Where does the cost of the needle vibrator go?

  • It is consumed by this item, per m³; it belongs in W.

  • Right. Plant used by the item is part of its cost.

  • The vibrator compacts concrete; it has nothing to do with steel.

3 суроонун 3-си

Why is reinforcement paid by weight from the BBS and not as a fixed amount per m³ of concrete?

  • Price is not the reason; variation is.

  • Right. That is why IS 1200 and the schedule keep it separate.

  • It sets how to measure, and steel is measured separately.