OpenConstruction Academy
Нэвтрэх / Бүртгүүлэх
MN

3-р даалгаврын өмнөх онол · 11 мин

Price adjustment (fiyat farkı): the base month, Pn and F

Гэрчилгээ 1 ба дөрөвдүгээр сарын үнийн залруулга

Энэ лекцийн дараа та дараахыг хийж чадна

  1. State the price adjustment formula of the 2013 Principles: F = An × B × (Pn − 1), with B = 0.90.
  2. Choose the base indices: the month in which the tender date falls.
  3. Compute Pn from weights and index ratios, round it to three decimals, then compute F.
1 / 3

Why there is a price adjustment

Prices move during a long job. Turkish public works contracts carry a price adjustment under the Principles on Price Adjustment in Works Contracts (Yapım İşlerinde Uygulanacak Fiyat Farkına İlişkin Esaslar, 2013). For works longer than 365 days it is compulsory. The administration pays, or deducts, a share of the change in published indices between the base month and the month the work is done.

Жишээ. F is positive when the indices rise and negative when they fall. The contractor bears 10 % of the movement through B = 0.90.
2 / 3

Pn: a weighted ratio of indices

Pn = a × In/Io + b1 × Çn/Ço + b2 × Dn/Do + … + c × Mn/Mo. Each weight is the share of a cost type in the work (labour index, cement and mineral products, base metals, fuel, machinery), fixed in the contract; the weights add up to 1. Io, Ço and the other base indices belong to the month in which the tender date falls; In, Çn and the others to the month the work is done. In this course Pn is rounded to three decimals, as the contract says.

Жишээ. If every index rose by 2.8 %, Pn would be 1.028 whatever the weights.
3 / 3

F on the work of the month

F = An × B × (Pn − 1). An is the value of the work done in the month at contract prices, without the price adjustment and without KDV. B = 0.90. A common slip is to use the contract month or the site handover month as the base: the base is the tender month, because bidders priced at the tender date.

Жишээ. An 600,000.00 at Pn 1.028: F = 600,000.00 × 0.90 × 0.028.
An, work of the month₺600,000.00
B0.9
Pn − 10.03
F₺15,120.00

Price adjustment for one month

A contract with four weights. Tender in January; the work of March is valued.

Масштабгүй
Бодлого
  • Weights: a 0.35 labour, b1 0.3 mineral products, b2 0.2 base metals, c 0.15 machinery.
  • January (tender month): İ 120.4, Ç 98.5, D 110.2, M 101.3. March: İ 124.1, Ç 101.9, D 112.8, M 103.
  • Work done in March at contract prices: ₺600,000.00.
Алхам 1 / 3

Labour term

a × In/Io. What is the labour term, to four decimals?

0.35 × 124.1 ÷ 120.4 = 0.36.

Алхам 2 / 3

Pn

Add the four terms and round to three decimals. What is Pn?

0.36 + 0.3 × 101.9/98.5 + 0.2 × 112.8/110.2 + 0.15 × 103/101.3 = 1.03 after rounding.

Work of the month
₺600,000
Price adjustment
?
Work of the month
₺600,000
Price adjustment
₺15,120
Алхам 3 / 3

F

F = An × 0.90 × (Pn − 1). What is the price adjustment?

₺600,000.00 × 0.90 × (1.03 − 1) = ₺15,120.00.

Товчхондоо. Base indices from the tender month, current ones from the month of the work, weights from the contract, Pn to three decimals, then F = An × 0.90 × (Pn − 1).

Өөрийгөө шалгах

Асуулт 1 / 3

An = 250,000.00 and Pn = 1.040. What is F?

250,000.00 × 0.90 × 0.040 = ₺9,000.00.
Асуулт 2 / 3

The tender was on 17 June, the contract signed on 22 July, the site handed over on 4 August. Which month gives the base indices?

  • Right. Bidders priced at the tender date.

  • A common slip; the Principles take the tender month.

  • Work could not start before handover, but prices were fixed at the tender.

Асуулт 3 / 3

What does B = 0.90 mean?

  • B applies only to the price movement.

  • Right.

  • B multiplies F, not Pn.