Put preliminaries, overheads and profit, risk and inflation in NRM 1 order.
State the base of each row, and keep two risk rows on the same base.
Compound quarterly inflation rates into one percentage.
1 / 5
The order of the rows
NRM 1 builds the cost limit in a fixed order. Building works first. Then the main contractor's preliminaries and the main contractor's overheads and profit: together with the works they make the works cost estimate. Then risk allowances. Then inflation. Each row is visible on its own, so the client can see what each one adds.
Жишээ. Illustrative: 12% preliminaries, 5% overheads and profit, 6% risk and 3% inflation take £4,000,000 of building works to about 5.14 million.
1 Building works
2 Preliminaries
3 Overheads and profit
4 Risk
5 Inflation
6 Cost limit
2 / 5
Each row has a base
Preliminaries are a percentage of the building works. Overheads and profit are a percentage of works plus preliminaries. Risk allowances are percentages of the works cost estimate. Inflation is a percentage of everything above it. A percentage means nothing until its base is stated.
Жишээ. In the ERP you choose the base of each row in «Markups»: «Sum of positions», «Running total incl. rows above» or «Same base as the row above».
PreliminariesBuilding works
Overheads and profitWorks + preliminaries
Design development riskWorks cost estimate
Construction risk, same baseWorks cost estimate
Tender price inflationEverything above it
3 / 5
Two risks, one base
Design development risk covers the design still changing. Construction risk covers what can go wrong on site. Both are a share of the same works cost estimate. If the second one is taken of the running total, it also takes a share of the first risk, and the allowance grows for no reason.
Жишээ. On a works cost estimate of £5,000,000 the difference is 3,000 pounds. Small here, and wrong every time.
3% and 2%, both of the works cost estimate
£250,000 (£150,000 + £100,000)
2% taken of the running total instead
£253,000 (£150,000 + £103,000)
4 / 5
Inflation compounds
The estimate is at the base date. The client pays at the tender date. Inflation covers each quarter between them, and quarters compound: multiply one plus each quarter's rate, then take one away. Adding the rates gives a little less, because it ignores growth on growth.
Жишээ. Three quarters at 2%, 1.3% and 1%: 1.02 × 1.013 × 1.01 − 1 = 4.36%, not 4.3%. Count every quarter after the base date up to and including the tender quarter.
Rates added4.3%
Rates compounded4.36%
5 / 5
What the full method adds
In full NRM 1 the design team fees and other project costs sit between the works cost estimate and the risk allowances, and a second inflation row runs from the tender date to the middle of construction. In this course the client holds fees and other costs in its budget, and the cost limit stops at the tender date.
Жишээ. When you compare with another cost plan, check which of these rows it carries before you compare totals.
Build a cost limit row by row
Different percentages and a different building from your task. Guess first, then open each step.
Масштабгүй
Бодлого
Building works, elements 1 to 8: £5,000,000.
Preliminaries 14% of the works. Overheads and profit 6% of works plus preliminaries.
Design development risk 3% and construction risk 2%, each of the works cost estimate.
Inflation from base date to tender date, three quarters: 1.7%, 1.2%, 1%.
1 Building works
2 Preliminaries
3 Overheads and profit
4 Works cost estimate
1 Building works
2 Preliminaries
3 Overheads and profit
4 Works cost estimate
Алхам 1 / 4
Works cost estimate
Works, plus preliminaries, plus overheads and profit on both. What is the works cost estimate?
Зөвлөмж: Overheads and profit are taken of works plus preliminaries, not of the works alone.
Preliminaries 14% of £5,000,000 = £700,000. Overheads and profit 6% of £5,000,000 + £700,000 = £342,000. Works cost estimate £6,042,000.
1 Works cost estimate
2 Risk
1 Works cost estimate
2 Risk
Алхам 2 / 4
Risk allowances
Both risks are taken of the works cost estimate. How much do they add together?
Зөвлөмж: Same base for both rows.
3% of £6,042,000 plus 2% of £6,042,000 = £302,100.
Quarter 11.7%
Quarter 21.2%
Quarter 31%
Compounded?
Quarter 11.7%
Quarter 21.2%
Quarter 31%
Compounded3.95%
Алхам 3 / 4
Inflation as one percentage
Compound the three quarters. What percentage, to two decimals?
Зөвлөмж: Multiply 1 plus each rate, then take 1 away.
1.017 × 1.012 × 1.010 = 1.0395, so inflation is 3.95%. Added, the rates would give 3.9%.
1 Works cost estimate
2 Risk
3 Inflation
4 Cost limit
1 Works cost estimate
2 Risk
3 Inflation
4 Cost limit
Алхам 4 / 4
The cost limit
Inflation applies to everything above it. What is the cost limit? Give pence.
Зөвлөмж: Works cost estimate plus risk, then times one plus inflation.
(£6,042,000 + £302,100) × (1 + 3.95%) = £6,594,691.95. This is the most the client should expect to pay at the tender date for building works, fees and VAT excluded.
Товчхондоо. Preliminaries on the works, overheads and profit on works plus preliminaries, both risks on the works cost estimate, compounded inflation on everything above.
Өөрийгөө шалгах
Асуулт 1 / 3
Inflation is forecast at 2.0% and then 1.2% for the two quarters to the tender date. What is the compounded percentage, to two decimals?
1.020 × 1.012 = 1.0322. Inflation 3.22%.
Асуулт 2 / 3
You add construction risk as a second row under design development risk. Which base does it take?
Then construction risk takes a share of design development risk. Both are shares of the works cost estimate.
Both risks measure uncertainty in the same works, so they share one base.
Preliminaries, overheads and profit carry risk too. The works cost estimate includes them.
Асуулт 3 / 3
What does tender price inflation apply to?
Preliminaries, overheads, profit and risk will also be priced at tender-date prices.
Every row above is at base-date prices, so every row rises.
The estimate does. The cost limit is stated at the tender date, so inflation is added once, here.