OpenConstruction Academy
Inloggen / Registreren
NL

Theorie vóór opdracht 4 · 9 min

The running account bill: five lines, the share billed, the balance

Termijnstaat 1 in het ERP

Na deze les kunt u

  1. Say what a running account bill is and when CPWD contracts allow one.
  2. Build the bill as three sections at base rates, then the index line, then the tender line.
  3. Measure the bill against the tendered amount, the sum the contract is for.
1 / 3

Paid on account, month by month

Under the CPWD General Conditions of Contract 2023 the contractor is paid monthly by running account (RA) bills, on the measurements recorded in the measurement book and checked by the Engineer-in-Charge. Each RA bill is a payment on account: the final bill settles everything. Schedule 'F' of the contract sets a minimum: if the gross work done since the last payment is below it, no interim payment is made that month and the work goes on the next bill.

Voorbeeld. With a minimum of ₹15 lakh, work worth ₹11.5 lakh this month waits for the next bill.
Schedule 'F' minimum
₹15,00,000
Work done since last bill
₹11,50,000
2 / 3

The bill re-keys the abstract

The RA bill carries the same money as the priced abstract, in five lines: the three sections at base rates, then the cost index on their sum, then the tender percentage on the running total. In the ERP this is Contracts, the contract, the Progress Claims tab, New Progress Claim, and one line by hand for each. Put the index or the tender percentage inside the section lines and the two lines below add it again.

Voorbeeld. Sections of ₹10 lakh in all, index 107, tender 2 % above: CI ₹70,000.00, TP ₹21,400.00.
₹2,10,000₹6,40,000
  • S1 at base rates ₹2,10,000
  • S2 at base rates ₹6,40,000
  • S3 at base rates ₹1,50,000
  • CI, 7 % on S1 + S2 + S3 ₹70,000
  • TP, 2 % on the total above ₹21,400
3 / 3

Tendered amount, not estimated cost

The estimated cost put to tender is the department's figure. The tendered amount is that figure with the contractor's percentage applied: it is what the contract is for. The share billed is the gross of the bills to date over the tendered amount, and what is left to bill is the tendered amount less that gross. Both sides must carry the index and the tender percentage, or the comparison is off.

Voorbeeld. ₹15 lakh billed on a ₹2.5 crore contract is 6 %; ₹2.35 crore is left to bill.
Tendered amount
₹2,50,00,000
Billed to date
₹15,00,000

Raise RA Bill 1 for a library block

Another contract: index 107, tender 2.15 % above. The abstract's three sections are ready at base rates.

Niet op schaal
De opgave
  • S1 ₹2,86,400.00, S2 ₹10,34,750.00, S3 ₹98,300.00, all at base rates.
  • Estimated cost put to tender ₹2,46,80,000.00; tender 2.15 % above; cost index 107.
  • Schedule 'F' minimum interim payment: ₹15 lakh.
Stap 1 van 4

CI line

7 % on the sum of the three sections. What is the CI line?

(₹2,86,400.00 + ₹10,34,750.00 + ₹98,300.00) × 7 % = ₹99,361.50.

Stap 2 van 4

TP line

2.15 % on the three sections plus the CI line. What is the TP line?

(₹2,86,400.00 + ₹10,34,750.00 + ₹98,300.00 + ₹99,361.50) × 2.15 % = ₹32,654.45.

₹2,86,400₹10,34,750
  • S1 ₹2,86,400
  • S2 ₹10,34,750
  • S3 ₹98,300
  • CI ₹99,362
  • TP ₹32,654
₹2,86,400₹10,34,750
  • S1 ₹2,86,400
  • S2 ₹10,34,750
  • S3 ₹98,300
  • CI ₹99,362
  • TP ₹32,654
Stap 3 van 4

Gross of RA Bill 1

Add the five lines. What is the gross, and does it clear the Schedule 'F' minimum?

₹2,86,400.00 + ₹10,34,750.00 + ₹98,300.00 + ₹99,361.50 + ₹32,654.45 = ₹15,51,465.95. That is over ₹15 lakh, so the bill can be paid.

Tendered amount
₹2,52,10,620
RA Bill 1 gross
₹15,51,466
Tendered amount
₹2,52,10,620
RA Bill 1 gross
₹15,51,466
Stap 4 van 4

Share of the tendered amount billed

The tendered amount is the estimate plus 2.15 %. What percentage of it does RA Bill 1 bill?

Tendered amount ₹2,46,80,000.00 × 1.0215 = ₹25,210,620.00. ₹15,51,465.95 ÷ that × 100 = 6.15%.

Kort gezegd. Five lines in a fixed order, the gross checked against the Schedule 'F' minimum, and the share and balance worked on the tendered amount. The Engineer-in-Charge reads the same five lines in the measurement book.

Test uzelf

Vraag 1 van 3

To say how much of the contract has been billed, you divide the gross to date by which figure?

  • That is the department's figure before the contractor's percentage. The contract is for the tendered amount.

  • Right. It is the sum the contract is for, with the tender percentage in.

  • That leaves out the index and the tender percentage, which the gross carries. The two sides would not match.

Vraag 2 van 3

Schedule 'F' sets the minimum interim payment at ₹15 lakh. This month's measured work is worth ₹11.5 lakh gross. What happens?

  • There is no penalty. The work simply waits.

  • Right. The minimum applies to the gross work done since the last payment.

  • The work is not held to the end. It is paid with the next running bill that clears the minimum.

Vraag 3 van 3

A contract's tendered amount is ₹1.845 crore (₹18,450,000.00). RA Bill 1 has a gross of ₹1,236,480.50. How much contract work is still to bill?

18,450,000.00 − 1,236,480.50 = 17,213,519.50.