OpenConstruction Academy
Logg inn / Registrer deg
NO

Teori før oppgave 4 · 9 min

Duct is priced by the pound

Ventilasjonskanaler: vekt etter platetykkelse

Etter denne leksjonen kan du

  1. Work the sheet area of a rectangular duct from its size and length.
  2. Weigh each segment with the gauge its size calls for.
  3. Add a fittings allowance, then price and plan labor by the pound.
1 / 4

Why weight

Rectangular duct is cut and folded from galvanized sheet. The shop buys sheet by weight and its labor tracks the sheet it handles, so sheet metal is priced per pound, not per foot of duct. A foot of large duct may weigh several times a foot of small duct.

2 / 4

Sheet area from the size

Duct sizes are given in inches and lengths in feet. The sheet around one foot of duct is its perimeter, 2 × (width + height), turned into feet. Times the length, that is the sheet area in square feet.

Eksempel. A 20 × 10 in duct has a 60 in perimeter, which is 5 ft. Over 25 ft that is 125 sf of sheet.
Perimeter, inches60
Perimeter, feet5
Length, feet25
Sheet area, sf125
3 / 4

Gauge by size

Bigger ducts need thicker sheet to stay stiff. The gauge number goes down as the sheet gets thicker, so 24 gauge is heavier than 26. SMACNA's HVAC Duct Construction Standards set the gauge from the duct size, the pressure class and the reinforcement; this course simplifies that to the longest side, and on a real job the project specification governs. Each segment is weighed with its own gauge.

Eksempel. Galvanized sheet weights from the gauge tables. Area times the weight of its gauge gives pounds.
26 gauge, lb per sf0.906
24 gauge, lb per sf1.156
Heavier gauges, for the largest ductsmore per sf
4 / 4

Fittings weigh too

Elbows, transitions and taps are made from the same sheet and take more shop time per pound than straight duct. When they are not taken off one by one, an allowance is added as a percentage of the straight weight. Price and labor then follow the total pounds: hours per pound and dollars per pound.

Weigh two segments

A different trunk from your task, and a 25 % fittings allowance instead of yours. Type your answer first.

Ikke i målestokk
Oppgaven
  • Segment P: 28 × 14 in, 40 ft, 24 gauge at 1.156 lb per sf.
  • Segment Q: 10 × 8 in, 24 ft, 26 gauge at 0.906 lb per sf.
  • Fittings 25% of the straight weight. Labor 0.07 hr per lb.
Perimeter, feet7
Length, feet40
Area, sf?
Perimeter, feet7
Length, feet40
Area, sf280
Trinn 1 av 4

Sheet area of P

Perimeter in feet times length. How many sf?

2 × (28 + 14) = 84 in, which is 7 ft. Times 40 ft: 280 sf.

Straight duct, lb
?
Straight duct, lb
388.91 (323.68 + 65.23)
Trinn 2 av 4

Straight weight, both segments

Weigh P with 24 gauge and Q with 26 gauge, then add. How many lb?

P: 280 sf × 1.156 = 323.68 lb. Q: 72 sf × 0.906 = 65.23 lb. Straight duct: 388.91 lb.

388.91?
  • Straight (lb) 388.91
  • Fittings (lb) ?
388.9197.23
  • Straight (lb) 388.91
  • Fittings (lb) 97.23
Trinn 3 av 4

With fittings

Add the fittings allowance to the straight weight. How many lb in total?

388.91 × 1.25 = 486.14 lb. The allowance is on pounds, not on area.

Total, lb486.14
Hours per lb0.07
Labor hours?
Total, lb486.14
Hours per lb0.07
Labor hours34.03
Trinn 4 av 4

Labor hours

Hours per pound times all the pounds. How many hours?

486.14 lb × 0.07 hr = 34.03 hr.

Kort sagt. Area from perimeter and length, weight from the gauge, fittings on the pounds, then hours and dollars per pound.

Test deg selv

Spørsmål 1 av 3

A duct is 15 × 9 in and 20 ft long. What is its sheet area?

  • Inches and feet were mixed: 48 in × 20 ft. Turn the perimeter into feet first.

  • 2 × (15 + 9) = 48 in = 4 ft. 4 × 20 = 80 sf.

  • That counts two sides only. A duct has four: 2 × (W + H).

Spørsmål 2 av 3

Two segments of one trunk need different gauges. How do you weigh them?

  • The trunk gets lighter as it gets smaller. Weigh segment by segment.

  • That overprices the small segments, and the bid rises for sheet you will not buy.

  • Area is not weight. Multiply by the pounds per sf of the gauge.

Spørsmål 3 av 3

Straight duct weighs 800 lb. Fittings are 20 % of the straight weight. Labor is 0.09 hr per lb. How many labor hours?

800 × 1.20 = 960 lb. 960 × 0.09 = 86.4 hr.