OpenConstruction Academy
Logg inn / Registrer deg
NO

Teori før oppgave 2 · 9 min

A late Notice of Claim and the Engineer's 14 days

Varsler om krav og det forsinkede varselet

Etter denne leksjonen kan du

  1. Count how many days a notice is past the 28-day limit.
  2. Apply Sub-Clause 20.2.2: the Engineer has 14 days to say a notice is late, or it is deemed valid.
  3. Know what the Contractor can still do when the Engineer calls a notice late in time.
1 / 3

The late notice is not automatically dead

FIDIC 2017 gives the Engineer a duty as well. If a Notice of Claim arrives after the 28 days, the Engineer must give notice saying so within 14 days after receiving it (Sub-Clause 20.2.2). If the Engineer does not, the Notice of Claim is deemed to be valid. The time bar cuts both ways: the Contractor must notify on time, and the Engineer must object on time.

Eksempel. Count the Engineer's 14 days from receipt of the Notice of Claim, not from the event.
2 / 3

When the Engineer objects in time

If the Engineer does call the notice late within 14 days, the Contractor is not without remedy. If it disagrees, or thinks circumstances justify the late submission, it sets that out in its fully detailed Claim, and the Engineer considers it when agreeing or determining the claim (Sub-Clause 3.7). So a late notice is a weak position, not always a lost one.

Eksempel. Register every notice, with the date received, in the contract register: these dates decide claims.
3 / 3

Two counts

First count: days from awareness to receipt of the notice, minus 28, gives days late. Second count: days from receipt to the Engineer's response; more than 14 means the notice is deemed valid.

Eksempel. Aware 02/02/2027, notice received 13/03/2027 (February 2027 has 28 days): 26 + 13 = 39 days, so 11 days late.
Days to receipt39
Limit, 20.2.128
Days late11

Does the late notice stand?

Ground conditions differ from the site data. The Contractor became aware on 02/02/2027 and its notice reached the Engineer on 13/03/2027. The Engineer called it late on 25/03/2027.

Ikke i målestokk
Oppgaven
  • Awareness 2 February 2027; February 2027 has 28 days.
  • Notice received 13 March 2027. Engineer's notice that it is late: 25 March 2027.
Trinn 1 av 2

Days late

Days from awareness to receipt, less 28. How many days late?

(28 − 2) + 13 − 28 = 11 days late.

Trinn 2 av 2

Engineer's days

From receipt to the Engineer's notice. How many days?

25 − 13 = 12 days: within 14, so the objection stands and the Contractor must justify the delay in its detailed Claim.

Kort sagt. Count both clocks. A late notice the Engineer fails to challenge within 14 days is deemed valid; one challenged in time needs a justification.

Test deg selv

Spørsmål 1 av 3

A notice is received on 11/06. The Engineer says it is late on 30/06. How many days did the Engineer take?

30 − 11 = 19 days, more than 14: the notice is deemed valid.
Spørsmål 2 av 3

The Engineer never responds to a late Notice of Claim. What is its status?

  • The Engineer had to give notice within 14 days.

  • Right.

  • No such step exists.

Spørsmål 3 av 3

From when are the Engineer's 14 days counted?

  • The event starts the Contractor's clock.

  • Right.

  • The Engineer cannot respond to a notice not yet received.