OpenConstruction Academy
Logg inn / Registrer deg
NO

Teori før oppgave 4 · 8 min

A rate per net tonne

Pris armeringspakken

Etter denne leksjonen kan du

  1. Build a rate from supply, waste, cutting and bending, and fixing.
  2. Put the waste on the supply price only, and say why.
  3. Add overhead and profit once, as a markup row, and check the average rate.
1 / 4

Three parts in every rate

A tonne of reinforcement in the bill is bought, cut and bent, and fixed. The supplier quotes the steel delivered to site. Cutting and bending and fixing are labour, usually priced per tonne by bar size. The rate is the sum of the three, per net tonne.

Eksempel. Supply AED 2,700.00 a tonne with 5 % waste, cut and bend AED 380.00, fix AED 470.00: a rate of AED 3,685.00 per net tonne of T40.
AED 2,835
  • Supply, with waste AED 2,835
  • Cut and bend AED 380
  • Fix AED 470
2 / 4

Waste loads the supply only

The bill pays per net tonne, but you buy more than that because offcuts are bought and never built in. So each net tonne carries the cost of its offcuts in the supply price. The offcuts are not fixed, and the labour rates are already per net tonne, so waste does not go on cutting or fixing.

Eksempel. Putting the 5 % on the whole rate adds AED 42.50 a tonne for steel nobody cuts or fixes.
Waste on supply only
AED 3,685 (AED 2,835 + AED 850)
Waste on the whole rate
AED 3,728
3 / 4

Small bars cost more per tonne

A tonne of thin bar is many more metres than a tonne of thick bar. Suppliers add a size extra for small diameters, and fixers charge more per tonne because there are more pieces to place and tie. Read the quotation for size extras before you copy one price into every line.

Eksempel. A size extra is added to the supply price before the waste goes on, because it is part of what you buy.
Base price per tonneAED 2,700.00
Size extra for small barsAED 110.00
Supply price before wasteAED 2,810.00
4 / 4

One markup row, then a sense check

Overhead and profit are a percentage of the direct cost, added once as a row under the bill, not hidden in each rate. When the grand total is in, divide it by the net tonnes: an average rate far from what the market pays per tonne means something is missing or counted twice.

Eksempel. The average includes the markup, so compare it with all-in prices per tonne, not with your net rates.
AED 13,2701+AED 1,3272AED 14,5973
  • 1 Direct cost
  • 2 Overhead and profit
  • 3 Grand total

Price a small package

Two bar sizes, made-up prices. Same method as your task.

Ikke i målestokk
Oppgaven
  • Supply AED 2,700.00 per tonne delivered; bars of T8 and below carry a size extra of AED 110.00. Waste 5% on supply.
  • T40: cut and bend AED 380.00, fix AED 470.00 per net tonne. T8: cut and bend AED 680.00, fix AED 780.00.
  • Net tonnes: T40 3, T8 0.5. Overhead and profit 10% of the direct cost.
?AED 380AED 470
  • Supply with waste ?
  • Cut and bend AED 380
  • Fix AED 470
AED 2,835
  • Supply with waste AED 2,835
  • Cut and bend AED 380
  • Fix AED 470
Trinn 1 av 4

Rate for T40

Supply with its waste, plus cut and bend, plus fix. What is the rate per net tonne?

AED 2,700.00 × 1.05 = AED 2,835.00. Plus AED 380.00 and AED 470.00: AED 3,685.00.

?AED 680AED 780
  • Supply with waste ?
  • Cut and bend AED 680
  • Fix AED 780
AED 2,950AED 680AED 780
  • Supply with waste AED 2,950
  • Cut and bend AED 680
  • Fix AED 780
Trinn 2 av 4

Rate for T8

The size extra joins the supply price before the waste. What is the rate per net tonne?

(AED 2,700.00 + AED 110.00) × 1.05 = AED 2,950.50. Plus AED 680.00 and AED 780.00: AED 4,410.50.

?1?2?3
  • 1 Direct cost
  • 2 Overhead and profit
  • 3 Grand total
AED 13,2601+AED 1,3262AED 14,5863
  • 1 Direct cost
  • 2 Overhead and profit
  • 3 Grand total
Trinn 3 av 4

Package price

Net tonnes times rates, then one markup row. What is the grand total?

Direct cost AED 13,260.25. Overhead and profit 10% on it. Grand total AED 14,586.28.

Grand totalAED 14,586.28
Net tonnes3.5
Average per tonne?
Grand totalAED 14,586.28
Net tonnes3.5
Average per tonneAED 4,167.51
Trinn 4 av 4

Average per net tonne

Grand total divided by the net tonnes. What is the average?

AED 14,586.28 ÷ 3.5 t = AED 4,167.51 per tonne, markup included.

Kort sagt. Supply with its waste, plus labour per net tonne, is the rate. The markup goes on once, under the bill.

Test deg selv

Spørsmål 1 av 3

Mesh costs AED 3,000.00 a tonne delivered, with 2 % waste. Cut to size AED 160.00 and fix AED 440.00 per net tonne. What is the rate per net tonne?

3,000.00 × 1.02 = 3,060.00. Plus 160.00 and 440.00: AED 3,660.00.
Spørsmål 2 av 3

A colleague adds 10 % overhead and profit into each unit rate and also keeps the markup row. What happens?

  • One place only: the markup row, where the employer and you can both see it.

  • It cannot see a percentage inside a rate. It adds what it is given.

  • The grand total changes too, by about a tenth of the direct cost.

Spørsmål 3 av 3

Why do T10 bars carry a higher rate per tonne than T25?

  • More pieces to buy, cut, place and tie per tonne, so the size extra and the labour are higher.

  • Both are the same grade. The difference is how many metres make a tonne.

  • The waste percentage is the same for loose bars here.