OpenConstruction Academy
Logg inn / Registrer deg
NO

Teori før oppgave 2 · 11 min

Plaster to IS 1200 Part XII: both faces, three size bands, reveals

Puss på samme vegg: tre terskler, ikke én

Etter denne leksjonen kan du

  1. Measure wall plaster in m² on each face it covers.
  2. Sort each opening into its band: not over 0.5 m², over 0.5 and not over 3 m², over 3 m².
  3. Add the jambs and soffit of an opening over 3 m², and only of that one.
1 / 3

Plaster is an area, face by face

IS 1200 (Part XII) measures wall plaster in m², on the dimensions of the wall before plastering: between the walls or partitions, from the floor or skirting to the ceiling. A wall plastered on both faces gives two areas. Brickwork took one face, because it needed the thickness; plaster needs every face that gets plaster.

Eksempel. A wall of 5.60 m by 3.00 m plastered both sides is 33.60 m² gross, not 16.80 m².
One face, 5.60 × 3.0016.80 m²
Second face, same plaster16.80 m²
Both faces, gross33.60 m²
2 / 3

Three size bands, not one threshold

Plaster deducts openings by size. Not over 0.5 m²: no deduction, and nothing added for the reveals. Over 0.5 m² and not over 3 m², with the same plaster on both faces: deduct one face only, add nothing for reveals. Over 3 m²: deduct both faces and measure the jambs, soffit and sill. The middle band is a trade-off: the second face stays in to pay for the reveals that are not measured. Brickwork's 0.1 m² has no place here.

Eksempel. A window of 1.40 × 1.10 m is 1.54 m²: one face comes off. A ventilator of 0.70 × 0.60 m is 0.42 m²: nothing comes off.
Not over 0.5 m²Nothing deducted, no reveals
Over 0.5, not over 3 m²One face deducted, no reveals
Over 3 m²Both faces deducted, reveals added
3 / 3

Reveals of a large opening

For an opening over 3 m² the reveals are measured. Run the girth up one jamb, across the soffit and down the other jamb; add the sill only if it is plastered too (a door or an archway has none). Multiply the girth by the width of the reveal, which is the thickness of the wall.

Eksempel. An archway 1.90 m wide and 2.75 m high in a 230 mm wall: girth 7.40 m, reveals 1.70 m².
Two jambs, 2 × 2.755.5 m
Soffit1.9 m
Girth7.4 m
Reveal width, wall thickness0.23 m
Reveals to add1.70 m²

Plaster a laboratory wall

A 200 mm wall plastered with the same mix on both faces. Four openings, one in each situation you will meet.

Ikke i målestokk
Oppgaven
  • Wall LW3: 8.4 m between walls, 3 m floor to ceiling, 0.2 m thick, plastered both faces.
  • Window 1.60 × 1.50 m (2.40 m²), door 0.90 × 2.10 m (1.89 m²), ventilator 0.60 × 0.60 m (0.36 m²).
  • Service opening 2 m wide × 2.4 m high, no sill.
Trinn 1 av 4

Both faces, gross

Two faces of 8.4 m × 3 m. What is the gross plaster area?

2 × 8.4 m × 3 m = 50.40 m².

Window, one face2.40 m²
Door, one face1.89 m²
Service opening, both faces9.60 m²
Ventilatornot over 0.5 m², stays in
Deducted?
Window, one face2.40 m²
Door, one face1.89 m²
Service opening, both faces9.60 m²
Ventilatornot over 0.5 m², stays in
Deducted13.89 m²
Trinn 2 av 4

Deductions by band

Window and door: one face each. Service opening: both faces. Ventilator: nothing. What is deducted?

2.40 m² + 1.89 m² + 2 × 4.80 = 13.89 m². The ventilator is under 0.5 m² and stays in.

Trinn 3 av 4

Reveals of the service opening

Girth of two jambs and the soffit, times the wall thickness. What area do you add?

(2 × 2.4 m + 2 m) × 0.2 m = 6.80 × 0.2 m = 1.36 m². The window and door get no reveals: they are in the middle band.

50.40 m²1−13.89 m²2+1.36 m²3?4
  • 1 Both faces, gross
  • 2 Openings, by band
  • 3 Reveals over 3 m²
  • 4 Plaster line
50.40 m²1−13.89 m²2+1.36 m²337.87 m²4
  • 1 Both faces, gross
  • 2 Openings, by band
  • 3 Reveals over 3 m²
  • 4 Plaster line
Trinn 4 av 4

Plaster for the bill

Gross less deductions plus reveals. What area goes on the plaster line?

50.40 m² − 13.89 m² + 1.36 m² = 37.87 m².

Kort sagt. Both faces gross; sort every opening into its band; add reveals only where both faces came off. Measure brickwork and plaster on one sheet and keep their thresholds apart.

Test deg selv

Spørsmål 1 av 3

A window of 1.00 × 1.20 m sits in a wall plastered the same on both faces. What do you do for it?

  • Right. 1.20 m² is in the middle band.

  • That treatment starts above 3 m². This window is 1.20 m².

  • Nothing comes off only for openings not over 0.5 m².

Spørsmål 2 av 3

A ventilator of 0.70 × 0.60 m is deducted from the brickwork. Is it deducted from the plaster too?

  • Each trade has its own rule. Brick uses 0.1 m²; plaster starts deducting above 0.5 m².

  • Right. And no reveals are added for it either.

  • One face comes off for openings over 0.5 m². This one is 0.42 m².

Spørsmål 3 av 3

An archway 2.10 m wide and 2.60 m high in a 300 mm wall has no sill. What area of reveals do you add to the plaster, in m²?

Girth 2 × 2.60 + 2.10 = 7.30 m. 7.30 × 0.30 = 2.19 m².