Put labor burden and small tools on base labor only.
Put sales tax on the material you buy, not on labor, not on quotes that already carry it.
Add overhead, profit and bond in order, each on the right running total.
1 / 4
Burden and tools follow wages
A worker costs more than the wage. Payroll taxes, workers' compensation, liability insurance and benefits are labor burden, stated as a percentage of base labor. Small tools and consumables usually follow labor too. Neither touches material or a sub-subcontractor's quote.
Exemplu. On $100,000 of base labor, 28% burden is $28,000 and 3% tools $3,000. Both are costs, so they go into the base for overhead and profit.
$100,000$28,000
Base labor $100,000
Burden $28,000
Small tools $3,000
2 / 4
Sales tax follows material
In Texas, a contractor on a lump-sum contract is treated as the consumer of the materials it installs: it pays sales tax to the supplier when it buys them, and that tax is a cost in the bid. Labor is not taxed. Equipment you install is taxed as material. A sub-subcontractor's quote already carries the tax on its own purchases, so taxing it again counts it twice. The combined rate is the state rate plus the local rate where the job is.
Exemplu. Tax 8.25% of $140,000 is $11,550.00. The $40,000 of quotes add nothing to it.
Material you buy: taxed$140,000
Sub-subcontract quotes: not taxed again$40,000
Sales tax, on material only$11,550.00
3 / 4
Markups go on in order
Overhead pays for the office and is worked on the direct cost: labor, material, quotes, burden, tools and tax. Profit is worked on cost plus overhead. The performance and payment bond premium is charged on the whole contract amount, so it comes last, on everything above it. Each percentage means something only with its base stated.
4 / 4
Lines first, markups second
Burden, tools and tax are costs, so they sit in the bill as lines and enter the direct cost. Overhead, profit and bond are markups on the result. Swap them and the markups miss part of the cost, or a cost is marked up twice.
Build a small bid
Different terms and numbers from your task. Round each step to the cent.
Nu este la scară
Problema
Base labor $100,000. Material you buy $140,000. Sub-subcontract quotes $40,000, tax already in.
Burden 28% and small tools 3%, both on base labor. Sales tax 8.25% on material.
Overhead 10% on direct cost, profit 5% on cost plus overhead, bond 1.5% on everything above.
$28,000
Burden $28,000
Tools $3,000
$28,000
Burden $28,000
Tools $3,000
Pasul 1 din 4
Burden and tools
Both on base labor. How much do they add together?
Indiciu: Material and quotes play no part here.
28% of $100,000 is $28,000.00, 3% is $3,000.00. Together $31,000.00.
Material$140,000
Tax rate8.25%
Sales tax?
Material$140,000
Tax rate8.25%
Sales tax$11,550.00
Pasul 2 din 4
Sales tax
On the material you buy only. How much?
Indiciu: Not on labor, not on the quotes.
8.25% of $140,000 = $11,550.00.
1 Labor
2 Material
3 Quotes
4 Burden, tools, tax
5 Direct cost
1 Labor
2 Material
3 Quotes
4 Burden, tools, tax
5 Direct cost
Pasul 3 din 4
Direct cost
Labor, material, quotes, burden and tools, and tax. What is the direct cost?