Price your own hours at a cost rate, even when you are the boss.
Take GST out of a GST-inclusive quote by dividing by 1.10.
Price labour-only trades on laid area and put waste in the rate only where it is not already in the quantity.
1 / 4
Your own hours are a cost
A small builder often forgets to price the work he does himself. Your hour costs your wage, super, insurance and leave. Strip-out, framing, lining and fit-out by your own hands go in at that cost rate, like any other trade. Otherwise you work the job for nothing and find out at the end.
2 / 4
Take GST out of quotes
A builder registered for GST claims back the GST on what it buys, so its cost is the price without GST. GST is one tenth of the price before GST. To take it out of an inclusive price, divide by 1.10. Taking 10% off the inclusive price removes too much.
Exempel. $8,800 including GST is $8,000 of cost and $800 of GST. Less 10% gives $7,920, which leaves part of the GST in your cost.
Quote including GST$8,800
Divided by 1.10: your cost$8,000
Less 10%: wrong$7,920
3 / 4
Labour-only trades are paid on laid area
A tiler quoting labour only is paid per square metre laid. Use the net areas, floor and walls. The order quantity with waste is what you buy in tiles, not what the tiler lays.
4 / 4
Waste goes in once: in the quantity or in the rate
Where a quantity already carries waste, such as tiles and board to order, the rate is the supplier's price. Where the quantity is net, such as timber, skirting and cornice, add the waste to the rate. One place, never both.
Cost four lines
A different job from your task, same rules. Type your answer first.
Inte skalenlig
Uppgiften
Your cost rate $58.00 an hour, 40 hours of fit-out.
Electrician $6,600 including GST. Tiler $55.00 per m² laid, labour only.
Laid areas: floor 4.60 m², walls 9.90 m². Skirting 22.0 m net at $7.20 per metre, waste 10% in the rate.
Hours40
Cost rate$58.00
Your labour?
Hours40
Cost rate$58.00
Your labour$2,320.00
Steg 1 av 4
Your labour
Hours times your cost rate. How much?
Tips: Your time is priced like anyone else's.
40 × $58.00 = $2,320.00.
??
Cost ?
GST, claimed back ?
$6,000
Cost $6,000
GST, claimed back $600
Steg 2 av 4
Electrician without GST
Take GST out of the quote. What is your cost?
Tips: Divide by 1.10.
$6,600 ÷ 1.10 = $6,000.00. The GST is claimed back.
$253$544
Floor $253
Walls $544
$253$544
Floor $253
Walls $544
Steg 3 av 4
Tiler
Rate times the laid area, floor and walls. How much?
Tips: Net areas, not the order areas.
(4.60 m² + 9.90 m²) × $55.00 = $797.50.
Rate with waste?
Net length22.0 m
Skirting?
Rate with waste$7.92
Net length22.0 m
Skirting$174.24
Steg 4 av 4
Skirting
Put 10% waste in the rate, then times the net length. How much?
Tips: The length is net, so the waste goes in the rate.
Rate $7.20 × 1.10 = $7.92. Times 22.0 m: $174.24.
Kort sagt. Price your own time, strip GST from quotes, pay labour on laid area, and carry waste once.
Testa dig själv
Fråga 1 av 3
A concreter quotes $14,300 including GST. You are registered for GST. What is your cost?
14,300 ÷ 1.10 = $13,000.00.
Fråga 2 av 3
Board is already ordered with 10% waste in the quantity. What rate do you enter?
The waste is in the number of sheets. Adding it to the rate counts it twice.
Then the waste is paid twice: in the quantity and in the rate.
Fråga 3 av 3
You do the strip-out yourself. Why price your hours?
Unpriced hours are worked for nothing.
Your own hours cost the business too.
The margin is for overheads and profit, not for the work itself.