Run a forward pass and read the planned length as the largest early finish.
Run a backward pass and find an activity's total float.
Tell the critical path from the longest bar on the chart.
1 / 3
Forward pass: the earliest dates
Start every activity without a predecessor at day 0, the data date. Early finish is early start plus duration. An activity with several predecessors waits for the last of them, so its early start is the latest early finish among them. Carry this through the network: the largest early finish is the planned length.
Exempel. Never add the two predecessors together. They run side by side; the activity waits only for the one that ends last.
Predecessor 1, early finish31
Predecessor 2, early finish36
Early start: the later of the two36
Duration4
Early finish40
2 / 3
Backward pass and total float
Now walk back from the finish. The last activity's late finish is the planned length. An activity's late finish is the earliest late start among its successors; late start is late finish minus duration. Total float is late start minus early start: the working days an activity can slip before Substantial Completion moves. Zero float means critical.
Exempel. Float is counted on the schedule's calendar. On a five-day calendar it is working days, never the calendar days between two dates.
Late start of the successor36
Duration of the activity8
Late start of the activity28
Early start of the activity17
Total float, working days11
3 / 3
The longest bar is not the longest path
A long activity catches the eye on a bar chart, but criticality belongs to paths, not to bars. A chain of short activities can be longer than one long activity running beside it. Total float is shared along a path: if one activity spends it, the others on the same path lose it.
Exempel. The curtain wall is the longest bar on the chart. Its path ends two days before the fit-out chain, so it has 2 days of float and the fit-out is critical.
Fit-out chain, four short activities
33 (7 + 9 + 8 + 9)
Curtain wall, one long bar
31
Three paths into one inspection
Another job. Three paths meet at the final inspection E. All links are finish-to-start; A, D and G start at day 0.
Inte skalenlig
Uppgiften
Path 1: A framing 9, B rough-in 8, C drywall 11 working days.
Path 2: D storefront 6, F paving 5.
Path 3: G elevator 17, the longest bar.
E final inspection 5, after C, F and G.
Steg 1 av 4
Forward pass on path 1
What is the early finish of C?
Tips: In series each activity starts where the last one ended.
9 + 8 + 11 = 28.
C, early finish28
F, early finish11
G, early finish17
E, duration5
Planned length?
C, early finish28
F, early finish11
G, early finish17
E, duration5
Planned length33
Steg 2 av 4
Planned length
E waits for C, F and G. What is the planned length?
Tips: The latest of the three early finishes, plus E.
C ends at 28, F at 11, G at 17. E starts at 28 and ends at 33.
A, B, C: critical
28
G and its float
?
A, B, C: critical
28
G and its float
28 (17 + 11)
Steg 3 av 4
Float of the elevator
What is the total float of G?
Tips: G must finish by E's late start. Late start minus early start.
E must start by 28, so G must start by 28 − 17 = 11. Its early start is 0: total float 11 working days. The longest bar is not critical.
Steg 4 av 4
A slip on the critical path
Rough-in B takes 3 days longer. What is the new planned length?
Tips: B has no float.
B is critical, so the finish moves day for day: 36. The same 3 days on G would have moved nothing.
Kort sagt. Forward pass for early dates and the length, backward pass for late dates, float as the difference.
Testa dig själv
Fråga 1 av 3
Path 1: four activities of 9, 9, 9 and 9 working days, then a final inspection of 5. Path 2: roofing 9, siding 8, gutters 6, sealants 5, then the same inspection. What is the total float of the roofing?
Path 1 reaches the inspection at day 36, path 2 at day 28. The roofing can slip 8 working days.
Fråga 2 av 3
Two activities on the same path each show six days of total float. How far can they slip together before the finish moves?
Right. Total float belongs to the path. What one activity spends, the next one no longer has.
The float is counted once for the path, not once per activity on it.
Float is not split by rule. Either activity can use all of it, and then the other has none.
Fråga 3 av 3
An activity has two predecessors that finish at day 17 and day 31. When can it start?
It needs both predecessors finished. The later one decides.
Right. The early start is the latest early finish among the predecessors.
The predecessors run side by side. Their days are not added.