OpenConstruction Academy
Logga in / Registrera
SV

Teori före uppgift 5 · 11 min

Recoveries from an RA bill: security deposit, welfare cess, GST TDS

Avdrag: säkerhetsdeposition, välfärdsavgift, GST

Efter den här lektionen kan du

  1. Take the security deposit from the gross of each bill, and tell it apart from the performance guarantee.
  2. Divide GST out of a tax-inclusive gross to find the taxable value.
  3. Take the welfare cess and GST TDS on the value without GST, and reach the amount payable.
1 / 3

Security deposit: held from every bill

Clause 1A of the CPWD General Conditions of Contract 2023 deducts 2.5 % of the gross amount of each running and final bill, until the sum held reaches a security deposit of 2.5 % of the tendered amount. It is the department's security for the work and is returned later. The performance guarantee is a different thing: 5 % of the tendered value, given once after acceptance of the tender, not cut from bills. In the ERP the deposit is the contract's 'Retention %'.

Exempel. On a ₹2 crore contract the deposit to reach is ₹5 lakh. A first bill of ₹16 lakh gross gives ₹40,000.00 towards it.
Deposit to reach, 2.5 % of tendered
₹5,00,000
Held after a bill of ₹16 lakh
₹40,000
2 / 3

The gross includes GST: divide it out

CPWD tendered rates include the taxes in force on the last date of receipt of tender, so the bill's gross already contains GST. Works contract services are taxed at 18 %; within one State that is 9 % CGST plus 9 % SGST. The value of the taxable supply is the gross divided by 1.18. Taking 18 % off the gross removes too much, because the 18 % was charged on the smaller figure.

Exempel. ₹590,000.00 gross is ₹500,000.00 taxable plus ₹90,000.00 GST. Gross × 0.82 would give ₹483,800.00.
Gross, GST included₹5,90,000.00
Taxable value, gross ÷ 1.18₹5,00,000.00
GST in the gross₹90,000.00
Gross less 18 % (wrong)₹4,83,800.00
3 / 3

Statutory recoveries: on the value without GST

Under section 51 of the CGST Act, 2017, a government department paying for a taxable supply under a contract worth more than ₹2.5 lakh deducts tax at source: 2 % for an intra-State supply (1 % CGST plus 1 % SGST), on the value without the tax. The building and other construction workers' welfare cess, 1 % of the cost of construction, is also recovered from the bill; it now falls under the Code on Social Security, 2020. This course takes the cost of construction as the bill value without GST, a case convention. Income tax deducted at source is a further recovery in practice; the course leaves it out.

Exempel. Two bases on one bill: the deposit on ₹590,000.00, the cess and TDS on ₹500,000.00.
₹5,90,0001−₹14,7502−₹5,0003−₹10,0004₹5,60,2505
  • 1 Gross of the bill
  • 2 Security deposit, 2.5 % of gross
  • 3 Welfare cess, 1 % of taxable
  • 4 GST TDS, 2 % of taxable
  • 5 Paid to the contractor

Pay a passed RA bill

Another contract in one State. The Engineer-in-Charge has passed the bill; work out what the accounts officer releases.

Inte skalenlig
Uppgiften
  • Gross of the bill ₹8,26,000.00, rates inclusive of GST at 18 %.
  • Security deposit 2.5 % of the gross (Clause 1A).
  • Welfare cess 1 % and GST TDS 2 %, both on the value without GST.
??
  • Taxable value ?
  • GST ?
₹7,00,000₹1,26,000
  • Taxable value ₹7,00,000
  • GST ₹1,26,000
Steg 1 av 4

Value of the taxable supply

Divide the GST out of ₹8,26,000.00. What is the taxable value?

₹8,26,000.00 ÷ 1.18 = ₹7,00,000.00.

Steg 2 av 4

Security deposit

2.5 % of which figure? What does Clause 1A hold back from this bill?

2.5 % of ₹8,26,000.00 = ₹20,650.00.

Steg 3 av 4

Cess and GST TDS

1 % plus 2 % of the taxable value. What do the two statutory recoveries come to?

1 % of ₹7,00,000.00 plus 2 % of ₹7,00,000.00 = ₹21,000.00.

₹8,26,0001−₹20,6502−₹21,0003?4
  • 1 Gross
  • 2 Security deposit
  • 3 Cess and GST TDS
  • 4 Payable
₹8,26,0001−₹20,6502−₹21,0003₹7,84,3504
  • 1 Gross
  • 2 Security deposit
  • 3 Cess and GST TDS
  • 4 Payable
Steg 4 av 4

Amount payable

Take all three recoveries off the gross. What is paid to the contractor?

₹8,26,000.00 − ₹20,650.00 − ₹21,000.00 = ₹7,84,350.00.

Kort sagt. Find the taxable value first, then use the right base for each recovery: the gross for the deposit, the value without GST for the cess and the TDS. The payment is the gross less all three.

Testa dig själv

Fråga 1 av 3

The contract asks for a 5 % performance guarantee and a 2.5 % security deposit. Which one is cut from each running bill?

  • The performance guarantee is given once, after acceptance of the tender. It is not cut from bills.

  • Right. That is Clause 1A.

  • Only the security deposit comes off the bills. The guarantee is a separate instrument.

Fråga 2 av 3

On what figure does the department take GST TDS?

  • The tax on the invoice is excluded from the value for the deduction.

  • Right. Gross ÷ 1.18 here, then 2 %.

  • The deposit is a contract deduction. It does not change the value of the supply.

Fråga 3 av 3

A passed RA bill has a gross of ₹4.72 lakh (₹472,000.00), GST 18 % included. Security deposit 2.5 % of the gross; welfare cess 1 % and GST TDS 2 % of the value without GST. What is payable?

Taxable 472,000.00 ÷ 1.18 = 400,000.00. Deposit 11,800.00; cess 4,000.00; TDS 8,000.00. Payable 472,000.00 − 23,800.00 = 448,200.00.