OpenConstruction Academy
Logga in / Registrera
SV

Teori före uppgift 5 · 11 min

Quantity deviation over 15 %: adjusting the 综合单价

Mängdavvikelse över 15 %

Efter den här lektionen kan du

  1. State the rule: above 15 % more, the excess is repriced lower; above 15 % less, the remaining quantity is repriced higher.
  2. Split an increased quantity at 115 % of the bill quantity.
  3. Compute the change amount without VAT.
1 / 3

Why rates change with quantity

A 综合单价 was priced for the bill quantity. If the real quantity is much larger, part of the fixed cost has been recovered already and the rate is too generous for the excess; if it is much smaller, fixed costs are spread over less work. GB/T 50500 (2013 edition, clause 9.6.2) therefore allows the rate to be adjusted when the deviation exceeds 15 %: lowered for the part above 115 %, raised for the remaining quantity when it falls below 85 %. The contract sets how; this course's contract uses 95 % and 105 % of the original rate.

Exempel. Within ±15 % the original rate stands, whatever the quantity.
2 / 3

More than 115 %

Only the excess above 115 % of the bill quantity takes the lower rate. The first 115 % is paid at the original rate.

Exempel. Bill 400 m³ at 520.00, actual 500 m³: 460 m³ at 520.00, 40 m³ at 494.00.
Up to 115 %
¥239,200
Excess at 95 %
¥19,760
3 / 3

Less than 85 %

When the quantity falls by more than 15 %, the whole remaining quantity takes the higher rate. The change amount is the adjusted amount minus the bill amount, item by item, reported without VAT; VAT is added at settlement.

Exempel. Bill 300 m² at 85.00, actual 240 m² (−20 %): 240 × 85.00 × 1.05.

Two deviations

After the final measurement two items deviate by more than 15 %.

Inte skalenlig
Uppgiften
  • Item A: bill 400 m³ at ¥520.00; measured 500 m³.
  • Item B: bill 300 m² at ¥85.00; measured 240 m².
  • Contract: above 115 %, excess at 95 %; below 85 %, remaining quantity at 105 %.
Steg 1 av 3

Item A, adjusted amount

115 % of the bill at the original rate, the excess at 95 %. What is A worth?

400 × 1.15 × ¥520.00 + (500 − 460) × ¥520.00 × 0.95 = ¥258,960.00.

Steg 2 av 3

Item B, adjusted amount

−20 %: the remaining quantity at 105 %. What is B worth?

240 × ¥85.00 × 1.05 = ¥21,420.00.

+¥50,9601−¥4,0802?3
  • 1 Item A
  • 2 Item B
  • 3 Change
+¥50,9601−¥4,0802¥46,8803
  • 1 Item A
  • 2 Item B
  • 3 Change
Steg 3 av 3

Change amount

Adjusted amounts less bill amounts. What is the change, without VAT?

(¥258,960.00 − ¥208,000.00) + (¥21,420.00 − ¥25,500.00) = ¥46,880.00.

Kort sagt. Test each item against ±15 %. Above, reprice only the excess; below, reprice all that remains. Report without VAT.

Testa dig själv

Fråga 1 av 3

Bill 200 m³ at 300.00 yuan; measured 260 m³. Above 115 %, the excess takes 95 % of the rate. What is the item worth?

230 × 300.00 + 30 × 285.00 = ¥77,550.00.
Fråga 2 av 3

A quantity rises by 12 %. What rate applies?

  • Right. Within 15 % nothing changes.

  • The adjustment starts only above 15 %.

  • Within 15 % there is no adjustment.

Fråga 3 av 3

A quantity falls by 25 %. Which part takes the higher rate?

  • That work was not done; nothing is paid for it.

  • Right.

  • The rule reprices the remaining quantity.