Count devices by type, including rooms drawn as 'same as' another.
Add the vertical conduit the plan does not draw: the rise from the panel and a drop to each box.
Work wire from conduit length, conductors and make-up, and add waste once.
1 / 4
Count by type, and count the rooms not drawn
Each device type is its own bill line with its own price: a GFCI receptacle costs and takes longer than a plain duplex, so it is never counted with them. Drawings save work by showing one room and marking the others 'same as' or 'typical'. Those rooms have no symbols on the sheet, and they still get built.
مثال. One consult room shows 3 duplex symbols and is marked typical for 4 rooms. With the office's 5, the wing needs 17, not 8.
Duplex in the consult room drawn3
Consult rooms in total, typical ones included4
Duplex in the office5
Duplex for the wing17
2 / 4
The plan shows the run, not the height
A branch circuit is drawn as a line from box to box. In the building the conduit runs in the ceiling space, so two vertical pieces are missing from the plan: the rise from the top of the panelboard up to the run, and a drop from the run down to each box. A drop ends at the box, not at the floor.
مثال. Run at 11 ft, panel top at 7 ft, boxes at 1.5 ft. The rise is 4 ft and each drop 9.5 ft. With 4 boxes the vertical conduit is 42 ft, and none of it is on the plan.
38
Rise, panel top to the run (ft) 4
Drops, run to each box (ft) 38
3 / 4
Wire follows the conduit, once per conductor
Every conductor in the conduit runs its whole length, so wire is conduit length times the number of conductors: hot, neutral and ground make three. At each box the electrician leaves a short tail of each conductor to make the connection. That make-up is added per conductor, per box.
مثال. 80 ft of conduit with 3 conductors is 240 ft of wire. Make-up of 1 ft for each of 3 conductors at each of 4 boxes comes on top, before any waste.
240
Conduit length × conductors (ft) 240
Make-up at the boxes (ft) 12
4 / 4
Waste goes on once, at the end
Conduit is cut, wire is pulled long and offcuts are thrown away. The allowance is a percentage of the measured length, vertical pieces and make-up included. Apply it once to the full measured figure. Adding it to each piece and again to the total pays for the same offcuts twice.
Measure circuit B-3
A different circuit from your task, same method. Type your answer first. A wrong guess costs nothing.
پیمانے کے مطابق نہیں
مسئلہ
Circuit B-3 feeds 5 boxes. Along the walls: panel to box 1 20 ft, then 17, 11, 15 and 13 ft.
Run in the ceiling at 11 ft. Panel top at 7 ft. Boxes at 1.5 ft.
3 conductors, 1 ft make-up per conductor at each box, waste 10% once.
??
Rise (ft) ?
Drops (ft) ?
47.5
Rise (ft) 4
Drops (ft) 47.5
مرحلہ 1 از 3
Vertical conduit
Rise from the panel plus a drop to every box. How many feet?
اشارہ: One rise. Then one drop per box, from the run down to the box.
Rise 11 − 7 = 4 ft. Each drop 11 − 1.5 = 9.5 ft, times 5 boxes. Vertical: 51.5 ft.
?51.5?
Horizontal (ft) ?
Vertical (ft) 51.5
Waste (ft) ?
7651.5
Horizontal (ft) 76
Vertical (ft) 51.5
Waste (ft) 12.75
مرحلہ 2 از 3
Conduit to order
Horizontal run plus vertical, then the waste. How many feet?
اشارہ: Add the five horizontal pieces, add the vertical, then multiply by 1.10.
Horizontal 76 ft plus vertical 51.5 ft = 127.5 ft measured. With 10% waste: 140.25 ft.
Measured wire (ft)?
Waste10%
Wire to order (ft)?
Measured wire (ft)397.5
Waste10%
Wire to order (ft)437.25
مرحلہ 3 از 3
Wire to order
Measured conduit times conductors, plus make-up, then waste once. How many feet?
اشارہ: Start from the measured conduit, before its waste, so the waste is not counted twice.
127.5 ft × 3 conductors, plus 3 × 5 boxes × 1 ft make-up = 397.5 ft. With 10% waste: 437.25 ft.
مختصراً. The plan gives the horizontal run. You add the rise and the drops, multiply by conductors for wire, add make-up at the boxes, and put waste on once.
خود کو جانچیں
سوال 1 از 3
Receptacle boxes are 1.5 ft above the floor and the conduit runs at 9 ft. How long is one drop?
That runs the drop to the floor. It stops at the box.
9 − 1.5 = 7.5 ft, from the run down to the box.
That is a leg down and a leg back up. Each box is fed by one drop from the overhead run.
سوال 2 از 3
A colleague adds 10 % to each piece of conduit, then 10 % again to the total. What is wrong?
The bid gets dearer for offcuts that will not exist.
One allowance on the full measured length, vertical pieces included.
Conduit is cut too. Both carry the allowance, each once.
سوال 3 از 3
A run of 60 ft of conduit carries 3 conductors to 5 boxes. Make-up is 1 ft per conductor per box. Waste 10 %. How many feet of wire do you order?
60 × 3 = 180 ft, plus make-up 3 × 5 × 1 = 15 ft, is 195 ft. With 10 % waste: 214.5 ft.