OpenConstruction Academy
سائن ان / رجسٹر کریں
UR

ٹاسک 4 سے پہلے نظریہ · 10 منٹ

From machine cycles to a rate per m³

مشینری کی پیداوار سے یونٹ ریٹ تک

اس لیکچر کے بعد آپ کر سکیں گے

  1. Work the hourly output of an excavator and of a truck fleet.
  2. Take the slower of the two as the output of the spread, in bank m³ per hour.
  3. Divide the hourly cost of the spread by its output and add the gate fee per bank m³.
1 / 4

What the excavator can dig

Each bucket holds its struck capacity times a fill factor: buckets are rarely full to the brim. The number of buckets in an hour is the productive seconds divided by the cycle time. Crews do not dig every minute of the hour; waiting, moving and breaks take part of it, so use the productive minutes the job gives you.

مثال. The bucket measures loose soil. The bill pays bank m³. Keep track of which one each figure is in.
Bucket × fill factorLoose m³ per cycle
Productive seconds ÷ cycleCycles per hour
OutputLoose m³ per hour
2 / 4

What the trucks can carry

A truck's round trip is loading, the loaded haul, dumping and manoeuvring, the empty return, and spotting at the excavator. Haul times come from distance over speed, loaded and empty separately. Loads per hour times body size times the number of trucks gives the fleet's output in loose m³.

مثال. Speed loaded and speed empty differ. Average them and the cycle is wrong; work each leg on its own.
3 / 4

The slower one sets the pace

An excavator that can fill more trucks than are waiting stands idle. Trucks that come back faster than they can be loaded queue. The spread produces the smaller of the two outputs. Turn it into bank m³ per hour by dividing by one plus the swell.

مثال. Here the trucks are the limit at 108 m³ loose an hour. Adding a truck would raise the output; a bigger excavator would not.
Excavator, loose m³ per hour
153
Truck fleet, loose m³ per hour
108
4 / 4

Cost per bank m³

The hourly cost of the spread is every machine and every person in it: excavator and operator, each truck and its driver, and the fuel all of them burn. Divide by the spread's bank output. If the tip charges per loose m³, each bank m³ arrives as one plus the swell loose, so multiply the fee by that before adding it.

مثال. Wages and fuel are direct costs of the spread. Leave them out and the rate covers only the machines' hire.

Rate a smaller spread

A different excavator, fleet and haul from your task, with the truck round trip given. Predict each figure first.

پیمانے کے مطابق نہیں
مسئلہ
  • Excavator: bucket 2 m³, fill factor 0.85, cycle 27 s. 45 productive minutes an hour for every machine.
  • 5 trucks, body 12 m³ loose, round trip 25 min with loading. Swell 0.2.
  • Excavator $130.00 an hour and operator $58.00; each truck $70.00 and driver $50.00. Fuel: excavator 25 L/h, truck 21 L/h, at $1.50 a litre.
  • The tip charges $5.00 per loose m³.
Cycles per hour?
Loose m³ per cycle1.7
Loose m³ per hour?
Cycles per hour100
Loose m³ per cycle1.7
Loose m³ per hour170
مرحلہ 1 از 4

Excavator output

Buckets per productive hour times the loose volume per bucket. Loose m³ per hour?

45 minutes is 2,700 s. ÷ 27 = 100 cycles. × 2 × 0.85 = 170 m³ loose an hour.

Excavator
170
Truck fleet
?
Excavator
170
Truck fleet
108
مرحلہ 2 از 4

Fleet output

Trips per productive hour per truck, times the body, times the trucks. Loose m³ per hour?

45 ÷ 25 = 1.8 trips. × 12 × 5 = 108 m³ loose an hour.

Trucks, loose
108
Spread, bank
?
Trucks, loose
108
Spread, bank
90
مرحلہ 3 از 4

Output of the spread

Take the slower one and turn it into bank m³. Bank m³ per hour?

The trucks are slower: 108 ÷ 1.20 = 90 m³ bank an hour.

??
  • Spread cost per bank m³ ?
  • Tip fee per bank m³ ?
$10.92$6.00
  • Spread cost per bank m³ $10.92
  • Tip fee per bank m³ $6.00
مرحلہ 4 از 4

Rate per bank m³

Hourly cost of the whole spread over its output, plus the tip fee per bank m³. Give cents.

Spread $983.00 an hour ÷ 90 = $10.92. Tip fee $5.00 × 1.20 = $6.00 per bank m³. Rate $16.92 per bank m³.

مختصراً. Output of each part, the slower one in bank m³, the whole spread's hourly cost over that, and the tip fee converted to bank m³.

خود کو جانچیں

سوال 1 از 3

A spread costs $900.00 an hour and produces 75 m³ bank an hour. The tip charges $4.00 per loose m³. Swell is 25%. What is the rate per bank m³?

$900.00 ÷ 75 = $12.00. Tip $4.00 × 1.25 = $5.00. Rate $17.00 per bank m³.
سوال 2 از 3

The excavator could load 160 m³ loose an hour; the trucks carry 125 m³ loose an hour. What is the spread's output?

  • The excavator would stand waiting for trucks.

  • The slower part sets the pace, and the bill pays bank m³.

  • Soil cannot move faster than the slowest link in the chain.

سوال 3 از 3

Why use productive minutes, not the full hour?

  • Planning on every minute overstates the output and understates the rate.

  • The contract pays per bank m³. Productive minutes make the output realistic.

  • Profit is a separate mark-up, not hidden in the output.