OpenConstruction Academy
سائن ان / رجسٹر کریں
UR

ٹاسک 5 سے پہلے نظریہ · 9 منٹ

The fully detailed Claim within 84 days

مکمل تفصیلی کلیم: 84 دن

اس لیکچر کے بعد آپ کر سکیں گے

  1. List what a fully detailed Claim contains under Sub-Clause 20.2.4.
  2. Count the 84 days from awareness and the days that remain.
  3. Know what happens if the statement of contractual basis is late.
1 / 3

What the detailed Claim contains

Within 84 days after the Contractor became aware, or should have become aware, of the event, it must submit a fully detailed Claim (Sub-Clause 20.2.4). It contains a description of the event, a statement of the contractual or legal basis, the contemporary records relied on, and detailed supporting particulars of the time and money claimed. The 1999 Red Book allowed half as long.

مثال. The notice says a claim is coming. The detailed Claim proves it.
2 / 3

The basis must arrive in time

If the statement of the contractual or legal basis is not submitted within the 84 days, the Notice of Claim is deemed to have lapsed and it is no longer a valid notice, unless the Engineer fails to say so within 14 days. Quantum can be updated later for an event with continuing effect, but the basis cannot wait.

مثال. Submit the basis and the records early; refine the money later if the effect continues.
3 / 3

Counting 84 days

Count from the day of awareness, as for the notice. Add the days month by month. Days left = 84 − days elapsed.

مثال. Aware 18/10, today 01/01: 13 + 30 + 31 + 1 = 75 days elapsed, so 9 days left.
Rest of October13
November30
December31
January1
Days elapsed75

Is there still time?

Awareness was 18/10/2027. It is now 01/01/2028 and the detailed Claim is ready.

پیمانے کے مطابق نہیں
مسئلہ
  • Days left in October after the 18th: 13. November 30, December 31. Today is 1 January.
مرحلہ 1 از 2

Days elapsed

From 18 October to 1 January. How many days?

13 + 30 + 31 + 1 = 75 days.

مرحلہ 2 از 2

Days left

84 minus the days elapsed. How many days remain?

84 − 75 = 9 days. Submit now.

مختصراً. 84 days from awareness. The basis and the records must be in by then; a continuing effect can be updated later.

خود کو جانچیں

سوال 1 از 3

Aware on 05/03. Today is 25/04 (March has 31 days). How many of the 84 days remain?

26 + 25 = 51 days elapsed; 84 − 51 = 33 days left.
سوال 2 از 3

What happens if the contractual basis is not stated within 84 days?

  • The basis cannot wait; only quantum can be updated.

  • Right. Sub-Clause 20.2.4.

  • There is no such rule.

سوال 3 از 3

Which edition of the Red Book gives 84 days for the detailed claim?

  • The 1999 edition allowed half as long.

  • Right.

  • They differ.