A sliding threshold, not a single percentage
Under the Construction Act, s. 2 (1), a contract is substantially performed when the work is ready for use or being used for its purpose and what is left can be completed or corrected for no more than 3 per cent of the first $1,000,000 of the contract price, 2 per cent of the next $1,000,000 and 1 per cent of the balance. Use the price as adjusted by change orders. Applying 3 per cent to the whole price overstates the threshold on any contract above a million.