OpenConstruction Academy
সাইন ইন / নিবন্ধন
BN

কাজ 2-এর আগে তত্ত্ব · 9 মি

Bank, loose and compacted

সোয়েল, শ্রিংকেজ এবং ট্রাক লোড

এই লেকচারের পর আপনি পারবেন

  1. Name the three states of soil and convert between them with swell and shrinkage factors.
  2. Compare cut and fill in one state to find the borrow, and bill it in bank m³.
  3. Count truck loads from the loose volume, rounded up.
1 / 5

One soil, three volumes

Ground in place is bank volume. Dug out, it breaks up and takes more room: that is loose volume, and the increase is the swell. Placed in an embankment and compacted, it takes less room than it did in the ground: that is compacted volume, found with a shrinkage factor. The same earth has three sizes depending on where it is.

উদাহরণ. Illustrative factors: 100 m³ of bank becomes 132 m³ loose and 90 m³ compacted. Your task gives its own factors; use those.
In the ground: bank
100
In the truck: loose, swell 32%
132
In the fill: compacted, factor 0.90
90
2 / 5

Compare in one state

Cut is measured in bank m³. Fill is measured in compacted m³. Subtracting one from the other mixes two sizes of the same earth. Convert the usable cut to compacted m³ first, then see what the fill still lacks.

উদাহরণ. 100 m³ of cut does not fill 100 m³ of embankment. At a factor of 0.90 it fills 90 m³.
3 / 5

Borrow is billed at the pit

What the fill lacks must be imported from a borrow pit. The bill measures borrow in bank m³, as dug at the pit, so divide the missing compacted volume by the shrinkage factor. More bank volume is needed than the hole it fills.

উদাহরণ. If the fill lacks 90 m³ compacted at a factor of 0.90, the borrow is 100 m³ bank.
4 / 5

Unsuitable cut goes to waste

Not every cut can go into the fill. Wet clay, organic soil or rubble that the engineer rejects is hauled away, and it counts neither as fill nor as borrow. Take it out of the cut before you convert.

উদাহরণ. The engineer decides what is unsuitable. Your job is to take that decision into the quantities.
5 / 5

Trucks carry loose volume

A truck body holds loose soil. To count loads, turn the bank volume into loose with the swell, then divide by the body size. A part load at the end still needs a truck, so round up.

উদাহরণ. Shrinkage has nothing to do with a truck: it describes compaction in the fill.

Balance a smaller job

Different factors and volumes from your task. Predict each figure first.

মাপমতো নয়
সমস্যা
  • Cut 900 m³ bank, of which 200 m³ is unsuitable and goes to waste.
  • The embankment needs 800 m³ compacted.
  • Swell 0.32: 1 m³ bank becomes 1.32 m³ loose. Compaction: 0.9 m³ compacted per bank m³. Truck body 13 m³ loose.
Usable cut, bank
700
Usable cut, compacted
?
Usable cut, bank
700
Usable cut, compacted
630
ধাপ 1 / 4

Usable cut, compacted

Take the unsuitable cut out, then compact the rest. How many m³ compacted does it give?

(900 − 200) × 0.9 = 630 m³ compacted.

Fill needed
?
Fill needed
800 (630 + 170)
ধাপ 2 / 4

What the fill lacks

Fill needed less usable cut, both compacted. What is short?

800 − 630 = 170 m³ compacted.

Gap, compacted
170
Borrow, bank
?
Gap, compacted
170
Borrow, bank
189
ধাপ 3 / 4

Borrow, in bank m³

The bill measures borrow at the pit. How many m³ bank, to the whole m³?

170 ÷ 0.9 = 188.9, so 189 m³ bank. More bank volume than the gap it fills.

Waste, bank m³200
Waste, loose m³?
Truck loads?
Waste, bank m³200
Waste, loose m³264
Truck loads21
ধাপ 4 / 4

Truck loads to waste

The unsuitable cut leaves by truck. How many loads?

200 × 1.32 = 264 m³ loose. ÷ 13 = 20.3, so 21 loads: the part load still needs a truck.

সংক্ষেপে. Take out what is unsuitable, compare cut and fill in compacted m³, bill borrow in bank m³, and count trucks in loose m³, rounded up.

নিজেকে যাচাই করুন

প্রশ্ন 1 / 3

210 m³ bank of unsuitable clay goes to waste. Swell is 32%. A truck body holds 15 m³ loose. How many loads?

210 × 1.32 = 277.2 m³ loose. ÷ 15 = 18.5, so 19 loads.
প্রশ্ন 2 / 3

The fill lacks 180 m³ compacted. In which volume is borrow billed?

  • The bill measures borrow at the pit, in bank m³. Bank is more than compacted.

  • Dug at the pit, it shrinks when compacted, so more is needed than the gap.

  • Loose volume counts trucks, not borrow.

প্রশ্ন 3 / 3

Which factor do you use to count truck loads?

  • A truck carries dug, loose soil.

  • Compaction happens in the fill, after the truck has tipped.

  • The body is sized in loose m³, so the volume must be loose too.