Name the three states of soil and convert between them with swell and shrinkage factors.
Compare cut and fill in one state to find the borrow, and bill it in bank m³.
Count truck loads from the loose volume, rounded up.
1 / 5
One soil, three volumes
Ground in place is bank volume. Dug out, it breaks up and takes more room: that is loose volume, and the increase is the swell. Placed in an embankment and compacted, it takes less room than it did in the ground: that is compacted volume, found with a shrinkage factor. The same earth has three sizes depending on where it is.
Eksempel. Illustrative factors: 100 m³ of bank becomes 132 m³ loose and 90 m³ compacted. Your task gives its own factors; use those.
In the ground: bank
100
In the truck: loose, swell 32%
132
In the fill: compacted, factor 0.90
90
2 / 5
Compare in one state
Cut is measured in bank m³. Fill is measured in compacted m³. Subtracting one from the other mixes two sizes of the same earth. Convert the usable cut to compacted m³ first, then see what the fill still lacks.
Eksempel. 100 m³ of cut does not fill 100 m³ of embankment. At a factor of 0.90 it fills 90 m³.
3 / 5
Borrow is billed at the pit
What the fill lacks must be imported from a borrow pit. The bill measures borrow in bank m³, as dug at the pit, so divide the missing compacted volume by the shrinkage factor. More bank volume is needed than the hole it fills.
Eksempel. If the fill lacks 90 m³ compacted at a factor of 0.90, the borrow is 100 m³ bank.
4 / 5
Unsuitable cut goes to waste
Not every cut can go into the fill. Wet clay, organic soil or rubble that the engineer rejects is hauled away, and it counts neither as fill nor as borrow. Take it out of the cut before you convert.
Eksempel. The engineer decides what is unsuitable. Your job is to take that decision into the quantities.
5 / 5
Trucks carry loose volume
A truck body holds loose soil. To count loads, turn the bank volume into loose with the swell, then divide by the body size. A part load at the end still needs a truck, so round up.
Eksempel. Shrinkage has nothing to do with a truck: it describes compaction in the fill.
Balance a smaller job
Different factors and volumes from your task. Predict each figure first.
Ikke i målestokk
Oppgaven
Cut 900 m³ bank, of which 200 m³ is unsuitable and goes to waste.
The embankment needs 800 m³ compacted.
Swell 0.32: 1 m³ bank becomes 1.32 m³ loose. Compaction: 0.9 m³ compacted per bank m³. Truck body 13 m³ loose.
Usable cut, bank
700
Usable cut, compacted
?
Usable cut, bank
700
Usable cut, compacted
630
Trinn 1 av 4
Usable cut, compacted
Take the unsuitable cut out, then compact the rest. How many m³ compacted does it give?
Hint: Bank to compacted: multiply by the shrinkage factor.
(900 − 200) × 0.9 = 630 m³ compacted.
Fill needed
?
Fill needed
800 (630 + 170)
Trinn 2 av 4
What the fill lacks
Fill needed less usable cut, both compacted. What is short?
Hint: Both figures are now compacted m³, so subtract directly.
800 − 630 = 170 m³ compacted.
Gap, compacted
170
Borrow, bank
?
Gap, compacted
170
Borrow, bank
189
Trinn 3 av 4
Borrow, in bank m³
The bill measures borrow at the pit. How many m³ bank, to the whole m³?
Hint: Compacted back to bank: divide by the shrinkage factor.
170 ÷ 0.9 = 188.9, so 189 m³ bank. More bank volume than the gap it fills.
Waste, bank m³200
Waste, loose m³?
Truck loads?
Waste, bank m³200
Waste, loose m³264
Truck loads21
Trinn 4 av 4
Truck loads to waste
The unsuitable cut leaves by truck. How many loads?
Hint: Bank to loose with the swell, divide by the body, round up.
200 × 1.32 = 264 m³ loose. ÷ 13 = 20.3, so 21 loads: the part load still needs a truck.
Kort sagt. Take out what is unsuitable, compare cut and fill in compacted m³, bill borrow in bank m³, and count trucks in loose m³, rounded up.
Test deg selv
Spørsmål 1 av 3
210 m³ bank of unsuitable clay goes to waste. Swell is 32%. A truck body holds 15 m³ loose. How many loads?