OpenConstruction Academy
Logg inn / Registrer deg
NO

Teori før oppgave 1 · 9 min

Measuring a road in slices

Skjæring og fylling med middelarealmetoden

Introduksjon til kurset

Etter denne leksjonen kan du

  1. Work the volume between two cross-sections by the average end area method.
  2. Give each segment its own length, and keep cut and fill apart.
  3. Check a segment with the prismoidal formula and say why it differs.
1 / 5

A road is measured in slices

The engineer cuts the road across at stations along its centreline. Each cross-section shows the ground and the new road, and gives two areas: the cut, where ground is taken away, and the fill, where ground is built up. Station 0+040 means 40 m from the start. Between two sections lies a slice of earth, and the bill is the sum of the slices.

Eksempel. Three sections 25 m apart make two slices. Each slice is measured from the two sections at its ends.
0+000, cut area
5.00 m²
0+025, cut area
9.00 m²
0+050, cut area
12.00 m²
2 / 5

Average end area

The volume of a slice is its length times the mean of its two end areas. It is the method most unit-price contracts name, because anyone can check it from the engineer's sections with a calculator.

Eksempel. 25 m × (9.0 + 12.0) ÷ 2 = 262.5 m³. Adding the two areas without halving them doubles the volume; using only the first area ignores how the ground changes.
End area at the start9.00 m²
End area at the end12.00 m²
Length of the slice25.0 m
Volume, m³262.5
3 / 5

Each segment takes its own length

Sections are usually evenly spaced, but not always. Where a culvert, a driveway or a change of slope makes the engineer skip or add a section, the slice is longer or shorter. Take every length from the two station numbers, never from the usual spacing.

Eksempel. From 0+100 to 0+140 the slice is 40 m long, even if every other slice is 25 m.
4 / 5

Cut and fill are separate items

Where a section has both cut and fill, measure both, each into its own total. Excavation is paid per bank m³ of ground dug; embankment per compacted m³ of fill placed. Netting one against the other hides work that is done and paid twice: once to dig, once to build up.

Eksempel. Round each total once, at the end, to the whole m³. Rounding every slice adds small errors that do not cancel.
5 / 5

The prismoidal check

When the shape of the ground changes between two sections, the average end area is slightly wrong. The prismoidal formula uses a third section measured at the middle: length ÷ 6 × (first area + 4 × middle area + last area). The middle area weighs four times as much as either end.

Eksempel. With a middle area of 10.0 m², the slice holds 254.17 m³, not 262.5 m³. The check tells you how far the quick method can be trusted on this ground.
Average end area
262.5
Prismoidal, middle area 10.0 m²
254.17

Four slices of a different street

A shorter street with different numbers from your task. Type your guess before you open each step.

Ikke i målestokk
Oppgaven
  • Cut areas: 0+000 6.00 m², 0+025 11.00 m², 0+050 15.00 m², 0+075 4.00 m², 0+110 nil.
  • Fill areas: nil up to 0+050, then 0+075 3.00 m², 0+110 14.00 m².
  • A section halfway between 0+025 and 0+050 has a cut area of 13.50 m².
Mean end area8.50 m²
Length25.0 m
Cut volume, m³?
Mean end area8.50 m²
Length25.0 m
Cut volume, m³212.5
Trinn 1 av 4

The first slice

Cut from 0+000 to 0+025. What volume, in m³?

25 m × (6.00 m² + 11.00 m²) ÷ 2 = 212.5 m³.

212.5???
  • 0+000 to 0+025 212.5
  • 0+025 to 0+050 ?
  • 0+050 to 0+075 ?
  • 0+075 to 0+110 ?
212.5325237.5
  • 0+000 to 0+025 212.5
  • 0+025 to 0+050 325
  • 0+050 to 0+075 237.5
  • 0+075 to 0+110 70
Trinn 2 av 4

All the cut

Add every slice of cut. The last slice is 35 m long. Round once, to the whole m³.

212.5 + 325 + 237.5 + 70 = 845 m³ of cut, in bank m³.

Cut, bank m³
845
Fill, compacted m³
?
Cut, bank m³
845
Fill, compacted m³
335
Trinn 3 av 4

All the fill

Fill is measured on its own. What is the fill total, to the whole m³?

0+050 to 0+075: 25 × (0 + 3.00 m²) ÷ 2 = 37.5. 0+075 to 0+110: 35 × (3.00 m² + 14.00 m²) ÷ 2 = 297.5. Together 335 m³ compacted, rounded once at the end.

Average end area
325
Prismoidal
?
Average end area
325
Prismoidal
333.33
Trinn 4 av 4

The prismoidal check

Slice 0+025 to 0+050 with the middle area. What volume does the prismoidal formula give?

25 ÷ 6 × (11.00 m² + 4 × 13.50 m² + 15.00 m²) = 333.33 m³, against 325 m³ by average end area. The ground bulges a little between the sections.

Kort sagt. Each slice: its own length times the mean of its end areas. Cut and fill in separate totals, each rounded once. The prismoidal formula checks a slice where the shape changes.

Test deg selv

Spørsmål 1 av 3

A slice runs from 0+100 to 0+140. Its cut areas are 11.0 m² and 15.0 m². What is its volume, in m³?

40 m × (11.0 + 15.0) ÷ 2 = 520 m³.
Spørsmål 2 av 3

A section has 4.0 m² of cut and 3.0 m² of fill. How do you carry it into the bill?

  • Both the digging and the building up happen and are paid. Netting hides one of them.

  • Cut and fill are separate items with separate units: bank m³ and compacted m³.

  • Fill is not dug. It goes to its own item.

Spørsmål 3 av 3

The prismoidal volume of a slice is lower than its average end area volume. What does that tell you?

  • The middle section shows the true shape. The quick method assumes a straight change.

  • Both methods use the same sections. They differ in what they assume between them.

  • It is still earth to move. The check refines the volume; it does not remove it.