Work the volume between two cross-sections by the average end area method.
Give each segment its own length, and keep cut and fill apart.
Check a segment with the prismoidal formula and say why it differs.
1 / 5
A road is measured in slices
The engineer cuts the road across at stations along its centreline. Each cross-section shows the ground and the new road, and gives two areas: the cut, where ground is taken away, and the fill, where ground is built up. Station 0+040 means 40 m from the start. Between two sections lies a slice of earth, and the bill is the sum of the slices.
Жишээ. Three sections 25 m apart make two slices. Each slice is measured from the two sections at its ends.
0+000, cut area
5.00 m²
0+025, cut area
9.00 m²
0+050, cut area
12.00 m²
2 / 5
Average end area
The volume of a slice is its length times the mean of its two end areas. It is the method most unit-price contracts name, because anyone can check it from the engineer's sections with a calculator.
Жишээ. 25 m × (9.0 + 12.0) ÷ 2 = 262.5 m³. Adding the two areas without halving them doubles the volume; using only the first area ignores how the ground changes.
End area at the start9.00 m²
End area at the end12.00 m²
Length of the slice25.0 m
Volume, m³262.5
3 / 5
Each segment takes its own length
Sections are usually evenly spaced, but not always. Where a culvert, a driveway or a change of slope makes the engineer skip or add a section, the slice is longer or shorter. Take every length from the two station numbers, never from the usual spacing.
Жишээ. From 0+100 to 0+140 the slice is 40 m long, even if every other slice is 25 m.
4 / 5
Cut and fill are separate items
Where a section has both cut and fill, measure both, each into its own total. Excavation is paid per bank m³ of ground dug; embankment per compacted m³ of fill placed. Netting one against the other hides work that is done and paid twice: once to dig, once to build up.
Жишээ. Round each total once, at the end, to the whole m³. Rounding every slice adds small errors that do not cancel.
5 / 5
The prismoidal check
When the shape of the ground changes between two sections, the average end area is slightly wrong. The prismoidal formula uses a third section measured at the middle: length ÷ 6 × (first area + 4 × middle area + last area). The middle area weighs four times as much as either end.
Жишээ. With a middle area of 10.0 m², the slice holds 254.17 m³, not 262.5 m³. The check tells you how far the quick method can be trusted on this ground.
Average end area
262.5
Prismoidal, middle area 10.0 m²
254.17
Four slices of a different street
A shorter street with different numbers from your task. Type your guess before you open each step.
Fill areas: nil up to 0+050, then 0+075 3.00 m², 0+110 14.00 m².
A section halfway between 0+025 and 0+050 has a cut area of 13.50 m².
Mean end area8.50 m²
Length25.0 m
Cut volume, m³?
Mean end area8.50 m²
Length25.0 m
Cut volume, m³212.5
Алхам 1 / 4
The first slice
Cut from 0+000 to 0+025. What volume, in m³?
Зөвлөмж: Length times the mean of the two end areas.
25 m × (6.00 m² + 11.00 m²) ÷ 2 = 212.5 m³.
212.5???
0+000 to 0+025 212.5
0+025 to 0+050 ?
0+050 to 0+075 ?
0+075 to 0+110 ?
212.5325237.5
0+000 to 0+025 212.5
0+025 to 0+050 325
0+050 to 0+075 237.5
0+075 to 0+110 70
Алхам 2 / 4
All the cut
Add every slice of cut. The last slice is 35 m long. Round once, to the whole m³.
Зөвлөмж: 0+075 to 0+110 is 35 m, and the cut area at 0+110 is nil.
212.5 + 325 + 237.5 + 70 = 845 m³ of cut, in bank m³.
Cut, bank m³
845
Fill, compacted m³
?
Cut, bank m³
845
Fill, compacted m³
335
Алхам 3 / 4
All the fill
Fill is measured on its own. What is the fill total, to the whole m³?
Зөвлөмж: Fill starts at 0+075: the slice before it has nil at one end.
0+050 to 0+075: 25 × (0 + 3.00 m²) ÷ 2 = 37.5. 0+075 to 0+110: 35 × (3.00 m² + 14.00 m²) ÷ 2 = 297.5. Together 335 m³ compacted, rounded once at the end.
Average end area
325
Prismoidal
?
Average end area
325
Prismoidal
333.33
Алхам 4 / 4
The prismoidal check
Slice 0+025 to 0+050 with the middle area. What volume does the prismoidal formula give?
Зөвлөмж: 25 ÷ 6 × (first + 4 × middle + last).
25 ÷ 6 × (11.00 m² + 4 × 13.50 m² + 15.00 m²) = 333.33 m³, against 325 m³ by average end area. The ground bulges a little between the sections.
Товчхондоо. Each slice: its own length times the mean of its end areas. Cut and fill in separate totals, each rounded once. The prismoidal formula checks a slice where the shape changes.
Өөрийгөө шалгах
Асуулт 1 / 3
A slice runs from 0+100 to 0+140. Its cut areas are 11.0 m² and 15.0 m². What is its volume, in m³?
40 m × (11.0 + 15.0) ÷ 2 = 520 m³.
Асуулт 2 / 3
A section has 4.0 m² of cut and 3.0 m² of fill. How do you carry it into the bill?
Both the digging and the building up happen and are paid. Netting hides one of them.
Cut and fill are separate items with separate units: bank m³ and compacted m³.
Fill is not dug. It goes to its own item.
Асуулт 3 / 3
The prismoidal volume of a slice is lower than its average end area volume. What does that tell you?
The middle section shows the true shape. The quick method assumes a straight change.
Both methods use the same sections. They differ in what they assume between them.
It is still earth to move. The check refines the volume; it does not remove it.