Сургалтын танилцуулга · 3 мин
Шороон ажил: ухаш ба асгаасын эзлэхүүн, масс тээвэрлэлт ба үнэ тогтоолт (Канад)
Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Зохиомол төсөл
You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.
- Work
- Cut, fill, borrow (soil brought in) and haul for two streets
- Contract
- Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
- Story
- Tender in October 2026 to a change in June 2027
- ERP дээрх ажил
- Даалгавар: 5, ойролцоогоор 3 цаг 15 мин
Хэн хэнд юу дамжуулдаг
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Танд ирдэг
- The Town's engineerIssues sections, checks quantities
- Cross-sections of Heron DriveДаалгавар 1
- Mass ordinates of Marlow AvenueДаалгавар 3
- Order: silt out, Granular B inДаалгавар 5
- Site superintendentRuns the machines and trucks
- Excavator, trucks and cycle timesДаалгавар 4
Танаас гардаг
- Cut and fill quantitiesДаалгавар 1
- Borrow and waste quantitiesДаалгавар 2
- Overhaul and surplusДаалгавар 3
- Rate for haul to wasteДаалгавар 4
- Change for unsuitable siltДаалгавар 5
Төслөөр явах таны зам
Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.
Quantities
Даалгавар 1 · 35 мин
Төгсгөлийн дундаж талбайн аргаар ухаш ба асгаасыг тооцох
- Үр дүн
- Cut and fill volumes, items 02.01 and 02.02
- Баримт бичиг
- Ten cross-sections of Heron Drive
- ERP дээр
- Bill of Quantities
Quantities
Даалгавар 2 · 35 мин
Сийрэгжилт, нягтрал ба самосвалын ачаалал
- Үр дүн
- Borrow to bring in, and truck loads to take away
- Баримт бичиг
- Soil factors and the engineer's note on wet clay
- ERP дээр
- Bill of Quantities
Quantities
Даалгавар 3 · 40 мин
Масс зөөвөр, үнэгүй зөөвөр болон нэмэлт зөөвөр
- Үр дүн
- Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
- Баримт бичиг
- Mass ordinates of Marlow Avenue
- ERP дээр
- Bill of Quantities
Rate
Даалгавар 4 · 45 мин
Тоног төхөөрөмжийн бүтээмжээс нэгж үнийг тооцох
- Үр дүн
- The unit rate for haul to waste
- Баримт бичиг
- Machine costs, fuel and cycle times
- ERP дээр
- Bill of Quantities
Change
Даалгавар 5 · 40 мин
Шаардлага хангахгүй материал: үнийн өөрчлөлт
- Үр дүн
- The priced change for unsuitable silt
- Баримт бичиг
- Test pit sections and agreed rates
- ERP дээр
- Variations
How a cross-section becomes a price
Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.
Цэнхэр нь даалгаврын нэмж буй хэсэг; саарал нь өмнөх алхмаас ирсэн хэсэг.
Товчхондоо. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.