Introducere în curs · 3 min
Lucrări de terasamente: volume de debleu și rambleu, diagrama de mase și deviz (Canada)
Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Proiect fictiv
You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.
- Work
- Cut, fill, borrow (soil brought in) and haul for two streets
- Contract
- Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
- Story
- Tender in October 2026 to a change in June 2027
- Lucru în ERP
- 5 sarcini, circa 3 h 15 min
Cine ce predă cui
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Ajunge la tine
- The Town's engineerIssues sections, checks quantities
- Cross-sections of Heron DriveSarcina 1
- Mass ordinates of Marlow AvenueSarcina 3
- Order: silt out, Granular B inSarcina 5
- Site superintendentRuns the machines and trucks
- Excavator, trucks and cycle timesSarcina 4
Pleacă de la tine
- Cut and fill quantitiesSarcina 1
- Borrow and waste quantitiesSarcina 2
- Overhaul and surplusSarcina 3
- Rate for haul to wasteSarcina 4
- Change for unsuitable siltSarcina 5
Traseul tău prin proiect
Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.
Quantities
Sarcina 1 · 35 min
Debleu și rambleu prin metoda suprafețelor medii extreme
- Produci
- Cut and fill volumes, items 02.01 and 02.02
- Document
- Ten cross-sections of Heron Drive
- În ERP
- Bill of Quantities
Quantities
Sarcina 2 · 35 min
Înfoiere, compactare și curse de camion
- Produci
- Borrow to bring in, and truck loads to take away
- Document
- Soil factors and the engineer's note on wet clay
- În ERP
- Bill of Quantities
Quantities
Sarcina 3 · 40 min
Diagrama maselor, transportul gratuit și supratransportul
- Produci
- Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
- Document
- Mass ordinates of Marlow Avenue
- În ERP
- Bill of Quantities
Rate
Sarcina 4 · 45 min
De la productivitatea utilajului la prețul unitar
- Produci
- The unit rate for haul to waste
- Document
- Machine costs, fuel and cycle times
- În ERP
- Bill of Quantities
Change
Sarcina 5 · 40 min
Material necorespunzător: o modificare de preț
- Produci
- The priced change for unsuitable silt
- Document
- Test pit sections and agreed rates
- În ERP
- Variations
How a cross-section becomes a price
Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.
Albastru este ce adaugă sarcina; gri este ce vine de dinainte.
Pe scurt. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.