Úvod do kurzu · 3 min

Zemní práce: objemy výkopů a násypů, hmotnice a oceňování (Kanada)

Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Smyšlený projekt

You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.

Začít úlohu 1

Work
Cut, fill, borrow (soil brought in) and haul for two streets
Contract
Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
Story
Tender in October 2026 to a change in June 2027
Práce v ERP
Úlohy: 5, asi 3 h 15 min

Kdo komu co předává

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Přichází k vám

  • The Town's engineerIssues sections, checks quantities
    • Cross-sections of Heron DriveÚloha 1
    • Mass ordinates of Marlow AvenueÚloha 3
    • Order: silt out, Granular B inÚloha 5
  • Site superintendentRuns the machines and trucks
    • Excavator, trucks and cycle timesÚloha 4
VyEstimator, earthworks contractor

Odchází od vás

    • Cut and fill quantitiesÚloha 1
    • Borrow and waste quantitiesÚloha 2
    • Overhaul and surplusÚloha 3
    • Rate for haul to wasteÚloha 4
    • Change for unsuitable siltÚloha 5
    The TownOwner, pays by the unit

Vaše cesta zakázkou

Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.

  1. Quantities

    Úloha 1 · 35 min

    Výkop a násyp metodou průměrných profilových ploch

    Výstup
    Cut and fill volumes, items 02.01 and 02.02
    Dokument
    Ten cross-sections of Heron Drive
    V ERP
    Bill of Quantities
  2. Quantities

    Úloha 2 · 35 min

    Nakypření, zhutnění a počty fůr

    Výstup
    Borrow to bring in, and truck loads to take away
    Dokument
    Soil factors and the engineer's note on wet clay
    V ERP
    Bill of Quantities
  3. Quantities

    Úloha 3 · 40 min

    Hmotočára, volná a příplatková dopravní vzdálenost

    Výstup
    Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
    Dokument
    Mass ordinates of Marlow Avenue
    V ERP
    Bill of Quantities
  4. Rate

    Úloha 4 · 45 min

    Produktivita strojů na jednotkovou cenu

    Výstup
    The unit rate for haul to waste
    Dokument
    Machine costs, fuel and cycle times
    V ERP
    Bill of Quantities
  5. Change

    Úloha 5 · 40 min

    Nevhodný materiál: ocenění změny

    Výstup
    The priced change for unsuitable silt
    Dokument
    Test pit sections and agreed rates
    V ERP
    Variations

How a cross-section becomes a price

Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.

Cut and fill
Úloha 1Measured volumesThe areas at each end of a slice times its length give cut and fill, each in its own unit and item.
Borrow and wasteCut and fill
Úloha 2Borrow and wasteCut and fill compared in one state of the soil. What is short is imported, what is unusable leaves by truck.
Overhaul and surplusBorrow and wasteCut and fill
Úloha 3HaulDistance beyond the free haul is paid as overhaul. What is left at the end is surplus.
Haul to waste, pricedOverhaul and surplusBorrow and wasteCut and fill
Úloha 4A rate built upMachine output, hourly cost and the dump's gate fee give a price per bank m³ (soil as it lies in the ground).
Change for siltThe priced bill
Úloha 5A changeUnsuitable silt out, granular fill in, at agreed rates and without HST (sales tax).

Modře je to, co úloha přidává; šedě to, co se přenáší z dřívějška.

Stručně. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.