Zemní práce: objemy výkopů a násypů, hmotnice a oceňování (Kanada)
Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Smyšlený projekt
You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.
- Work
- Cut, fill, borrow (soil brought in) and haul for two streets
- Contract
- Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
- Story
- Tender in October 2026 to a change in June 2027
- Práce v ERP
- Úlohy: 5, asi 3 h 15 min
Kdo komu co předává
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Přichází k vám
- The Town's engineerIssues sections, checks quantities
- Cross-sections of Heron DriveÚloha 1
- Mass ordinates of Marlow AvenueÚloha 3
- Order: silt out, Granular B inÚloha 5
- Site superintendentRuns the machines and trucks
- Excavator, trucks and cycle timesÚloha 4
Odchází od vás
- Cut and fill quantitiesÚloha 1
- Borrow and waste quantitiesÚloha 2
- Overhaul and surplusÚloha 3
- Rate for haul to wasteÚloha 4
- Change for unsuitable siltÚloha 5
Vaše cesta zakázkou
Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.
Quantities
Úloha 1 · 35 min
Výkop a násyp metodou průměrných profilových ploch
- Výstup
- Cut and fill volumes, items 02.01 and 02.02
- Dokument
- Ten cross-sections of Heron Drive
- V ERP
- Bill of Quantities
Quantities
Úloha 2 · 35 min
Nakypření, zhutnění a počty fůr
- Výstup
- Borrow to bring in, and truck loads to take away
- Dokument
- Soil factors and the engineer's note on wet clay
- V ERP
- Bill of Quantities
Quantities
Úloha 3 · 40 min
Hmotočára, volná a příplatková dopravní vzdálenost
- Výstup
- Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
- Dokument
- Mass ordinates of Marlow Avenue
- V ERP
- Bill of Quantities
Rate
Úloha 4 · 45 min
Produktivita strojů na jednotkovou cenu
- Výstup
- The unit rate for haul to waste
- Dokument
- Machine costs, fuel and cycle times
- V ERP
- Bill of Quantities
Change
Úloha 5 · 40 min
Nevhodný materiál: ocenění změny
- Výstup
- The priced change for unsuitable silt
- Dokument
- Test pit sections and agreed rates
- V ERP
- Variations
How a cross-section becomes a price
Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.
Modře je to, co úloha přidává; šedě to, co se přenáší z dřívějška.
Stručně. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.