Earthworks: mga volume ng cut at fill, mass haul at pagpepresyo (Canada)

Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Kathang-isip na proyekto

You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.

Simulan ang gawain 1

Work
Cut, fill, borrow (soil brought in) and haul for two streets
Contract
Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
Story
Tender in October 2026 to a change in June 2027
Trabaho sa ERP
5 gawain, mga 3 oras 15 min

Sino ang nagbibigay ng ano kanino

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dumarating sa iyo

  • The Town's engineerIssues sections, checks quantities
    • Cross-sections of Heron DriveGawain 1
    • Mass ordinates of Marlow AvenueGawain 3
    • Order: silt out, Granular B inGawain 5
  • Site superintendentRuns the machines and trucks
    • Excavator, trucks and cycle timesGawain 4
IkawEstimator, earthworks contractor

Lumalabas sa iyo

    • Cut and fill quantitiesGawain 1
    • Borrow and waste quantitiesGawain 2
    • Overhaul and surplusGawain 3
    • Rate for haul to wasteGawain 4
    • Change for unsuitable siltGawain 5
    The TownOwner, pays by the unit

Ang ruta mo sa proyekto

Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.

  1. Quantities

    Gawain 1 · 35 min

    Cut at fill ayon sa average end area

    Ang gagawin mo
    Cut and fill volumes, items 02.01 and 02.02
    Dokumento
    Ten cross-sections of Heron Drive
    Sa ERP
    Bill of Quantities
  2. Quantities

    Gawain 2 · 35 min

    Paglobo, pag-urong at mga biyahe ng trak

    Ang gagawin mo
    Borrow to bring in, and truck loads to take away
    Dokumento
    Soil factors and the engineer's note on wet clay
    Sa ERP
    Bill of Quantities
  3. Quantities

    Gawain 3 · 40 min

    Mass haul, free haul at overhaul

    Ang gagawin mo
    Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
    Dokumento
    Mass ordinates of Marlow Avenue
    Sa ERP
    Bill of Quantities
  4. Rate

    Gawain 4 · 45 min

    Mula sa productivity ng kagamitan hanggang unit rate

    Ang gagawin mo
    The unit rate for haul to waste
    Dokumento
    Machine costs, fuel and cycle times
    Sa ERP
    Bill of Quantities
  5. Change

    Gawain 5 · 40 min

    Hindi angkop na materyal: pagbabagong dapat presyuhan

    Ang gagawin mo
    The priced change for unsuitable silt
    Dokumento
    Test pit sections and agreed rates
    Sa ERP
    Variations

How a cross-section becomes a price

Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.

Cut and fill
Gawain 1Measured volumesThe areas at each end of a slice times its length give cut and fill, each in its own unit and item.
Borrow and wasteCut and fill
Gawain 2Borrow and wasteCut and fill compared in one state of the soil. What is short is imported, what is unusable leaves by truck.
Overhaul and surplusBorrow and wasteCut and fill
Gawain 3HaulDistance beyond the free haul is paid as overhaul. What is left at the end is surplus.
Haul to waste, pricedOverhaul and surplusBorrow and wasteCut and fill
Gawain 4A rate built upMachine output, hourly cost and the dump's gate fee give a price per bank m³ (soil as it lies in the ground).
Change for siltThe priced bill
Gawain 5A changeUnsuitable silt out, granular fill in, at agreed rates and without HST (sales tax).

Asul ang idinadagdag ng gawain; abo ang dala mula sa naunang hakbang.

Sa madaling salita. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.