Inleiding tot de cursus · 3 min

Grondverzet: afgraving- en ophogingsvolumes, massadiagram en prijsberekening (Canada)

Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Fictief project

You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.

Start opdracht 1

Work
Cut, fill, borrow (soil brought in) and haul for two streets
Contract
Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
Story
Tender in October 2026 to a change in June 2027
Werk in de ERP
5 opdrachten, ongeveer 3 u 15 min

Wie geeft wat aan wie

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Komt bij u

  • The Town's engineerIssues sections, checks quantities
    • Cross-sections of Heron DriveOpdracht 1
    • Mass ordinates of Marlow AvenueOpdracht 3
    • Order: silt out, Granular B inOpdracht 5
  • Site superintendentRuns the machines and trucks
    • Excavator, trucks and cycle timesOpdracht 4
UEstimator, earthworks contractor

Gaat van u uit

    • Cut and fill quantitiesOpdracht 1
    • Borrow and waste quantitiesOpdracht 2
    • Overhaul and surplusOpdracht 3
    • Rate for haul to wasteOpdracht 4
    • Change for unsuitable siltOpdracht 5
    The TownOwner, pays by the unit

Uw route door het project

Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.

  1. Quantities

    Opdracht 1 · 35 min

    Ontgraving en aanvulling met de gemiddelde profielenmethode

    U levert
    Cut and fill volumes, items 02.01 and 02.02
    Document
    Ten cross-sections of Heron Drive
    In de ERP
    Bill of Quantities
  2. Quantities

    Opdracht 2 · 35 min

    Zelling, krimp en vrachtwagenladingen

    U levert
    Borrow to bring in, and truck loads to take away
    Document
    Soil factors and the engineer's note on wet clay
    In de ERP
    Bill of Quantities
  3. Quantities

    Opdracht 3 · 40 min

    Massalijn, vrije transportafstand en overtransport

    U levert
    Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
    Document
    Mass ordinates of Marlow Avenue
    In de ERP
    Bill of Quantities
  4. Rate

    Opdracht 4 · 45 min

    Materieelproductiviteit naar eenheidsprijs

    U levert
    The unit rate for haul to waste
    Document
    Machine costs, fuel and cycle times
    In de ERP
    Bill of Quantities
  5. Change

    Opdracht 5 · 40 min

    Ongeschikt materiaal: een te prijzen wijziging

    U levert
    The priced change for unsuitable silt
    Document
    Test pit sections and agreed rates
    In de ERP
    Variations

How a cross-section becomes a price

Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.

Cut and fill
Opdracht 1Measured volumesThe areas at each end of a slice times its length give cut and fill, each in its own unit and item.
Borrow and wasteCut and fill
Opdracht 2Borrow and wasteCut and fill compared in one state of the soil. What is short is imported, what is unusable leaves by truck.
Overhaul and surplusBorrow and wasteCut and fill
Opdracht 3HaulDistance beyond the free haul is paid as overhaul. What is left at the end is surplus.
Haul to waste, pricedOverhaul and surplusBorrow and wasteCut and fill
Opdracht 4A rate built upMachine output, hourly cost and the dump's gate fee give a price per bank m³ (soil as it lies in the ground).
Change for siltThe priced bill
Opdracht 5A changeUnsuitable silt out, granular fill in, at agreed rates and without HST (sales tax).

Blauw is wat de opdracht toevoegt; grijs komt uit de stap ervoor.

Kort gezegd. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.