Kursuse sissejuhatus · 3 min
Pinnasetööd: kaeve- ja täitemahud, masside veodiagramm ja hinnastamine (Kanada)
Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Väljamõeldud projekt
You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.
- Work
- Cut, fill, borrow (soil brought in) and haul for two streets
- Contract
- Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
- Story
- Tender in October 2026 to a change in June 2027
- Töö ERP-s
- Ülesandeid 5, umbes 3 h 15 min
Kes annab kellele mida
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Tuleb sinule
- The Town's engineerIssues sections, checks quantities
- Cross-sections of Heron DriveÜlesanne 1
- Mass ordinates of Marlow AvenueÜlesanne 3
- Order: silt out, Granular B inÜlesanne 5
- Site superintendentRuns the machines and trucks
- Excavator, trucks and cycle timesÜlesanne 4
Läheb sinult
- Cut and fill quantitiesÜlesanne 1
- Borrow and waste quantitiesÜlesanne 2
- Overhaul and surplusÜlesanne 3
- Rate for haul to wasteÜlesanne 4
- Change for unsuitable siltÜlesanne 5
Sinu tee läbi projekti
Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.
Quantities
Ülesanne 1 · 35 min
Kaeve ja täide otspindade keskmise meetodil
- Sinu tulemus
- Cut and fill volumes, items 02.01 and 02.02
- Dokument
- Ten cross-sections of Heron Drive
- ERP-s
- Bill of Quantities
Quantities
Ülesanne 2 · 35 min
Paisumine, kahanemine ja veokikoormad
- Sinu tulemus
- Borrow to bring in, and truck loads to take away
- Dokument
- Soil factors and the engineer's note on wet clay
- ERP-s
- Bill of Quantities
Quantities
Ülesanne 3 · 40 min
Veomassi graafik, tasuta vedu ja lisavedu
- Sinu tulemus
- Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
- Dokument
- Mass ordinates of Marlow Avenue
- ERP-s
- Bill of Quantities
Rate
Ülesanne 4 · 45 min
Tehnika tootlikkus ühikuhinnaks
- Sinu tulemus
- The unit rate for haul to waste
- Dokument
- Machine costs, fuel and cycle times
- ERP-s
- Bill of Quantities
Change
Ülesanne 5 · 40 min
Kõlbmatu materjal: hinnamuudatus
- Sinu tulemus
- The priced change for unsuitable silt
- Dokument
- Test pit sections and agreed rates
- ERP-s
- Variations
How a cross-section becomes a price
Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.
Sinine on see, mida ülesanne lisab; hall tuleb varasemast.
Lühidalt. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.