OpenConstruction Academy
Logi sisse / Registreeru
ET

Kursuse sissejuhatus · 3 min

Pinnasetööd: kaeve- ja täitemahud, masside veodiagramm ja hinnastamine (Kanada)

Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Väljamõeldud projekt

You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.

Alusta ülesannet 1

Work
Cut, fill, borrow (soil brought in) and haul for two streets
Contract
Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
Story
Tender in October 2026 to a change in June 2027
Töö ERP-s
Ülesandeid 5, umbes 3 h 15 min

Kes annab kellele mida

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Tuleb sinule

  • The Town's engineerIssues sections, checks quantities
    • Cross-sections of Heron DriveÜlesanne 1
    • Mass ordinates of Marlow AvenueÜlesanne 3
    • Order: silt out, Granular B inÜlesanne 5
  • Site superintendentRuns the machines and trucks
    • Excavator, trucks and cycle timesÜlesanne 4
SinaEstimator, earthworks contractor

Läheb sinult

    • Cut and fill quantitiesÜlesanne 1
    • Borrow and waste quantitiesÜlesanne 2
    • Overhaul and surplusÜlesanne 3
    • Rate for haul to wasteÜlesanne 4
    • Change for unsuitable siltÜlesanne 5
    The TownOwner, pays by the unit

Sinu tee läbi projekti

Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.

  1. Quantities

    Ülesanne 1 · 35 min

    Kaeve ja täide otspindade keskmise meetodil

    Sinu tulemus
    Cut and fill volumes, items 02.01 and 02.02
    Dokument
    Ten cross-sections of Heron Drive
    ERP-s
    Bill of Quantities
  2. Quantities

    Ülesanne 2 · 35 min

    Paisumine, kahanemine ja veokikoormad

    Sinu tulemus
    Borrow to bring in, and truck loads to take away
    Dokument
    Soil factors and the engineer's note on wet clay
    ERP-s
    Bill of Quantities
  3. Quantities

    Ülesanne 3 · 40 min

    Veomassi graafik, tasuta vedu ja lisavedu

    Sinu tulemus
    Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
    Dokument
    Mass ordinates of Marlow Avenue
    ERP-s
    Bill of Quantities
  4. Rate

    Ülesanne 4 · 45 min

    Tehnika tootlikkus ühikuhinnaks

    Sinu tulemus
    The unit rate for haul to waste
    Dokument
    Machine costs, fuel and cycle times
    ERP-s
    Bill of Quantities
  5. Change

    Ülesanne 5 · 40 min

    Kõlbmatu materjal: hinnamuudatus

    Sinu tulemus
    The priced change for unsuitable silt
    Dokument
    Test pit sections and agreed rates
    ERP-s
    Variations

How a cross-section becomes a price

Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.

Cut and fill
Ülesanne 1Measured volumesThe areas at each end of a slice times its length give cut and fill, each in its own unit and item.
Borrow and wasteCut and fill
Ülesanne 2Borrow and wasteCut and fill compared in one state of the soil. What is short is imported, what is unusable leaves by truck.
Overhaul and surplusBorrow and wasteCut and fill
Ülesanne 3HaulDistance beyond the free haul is paid as overhaul. What is left at the end is surplus.
Haul to waste, pricedOverhaul and surplusBorrow and wasteCut and fill
Ülesanne 4A rate built upMachine output, hourly cost and the dump's gate fee give a price per bank m³ (soil as it lies in the ground).
Change for siltThe priced bill
Ülesanne 5A changeUnsuitable silt out, granular fill in, at agreed rates and without HST (sales tax).

Sinine on see, mida ülesanne lisab; hall tuleb varasemast.

Lühidalt. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.