Въведение в курса · 3 мин
Земни работи: обем на изкопи и насипи, диаграма на земните маси и ценообразуване (Канада)
Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Измислен проект
You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.
- Work
- Cut, fill, borrow (soil brought in) and haul for two streets
- Contract
- Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
- Story
- Tender in October 2026 to a change in June 2027
- Работа в ERP
- Задачи: 5, около 3 ч 15 мин
Кой какво предава на кого
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Идва при вас
- The Town's engineerIssues sections, checks quantities
- Cross-sections of Heron DriveЗадача 1
- Mass ordinates of Marlow AvenueЗадача 3
- Order: silt out, Granular B inЗадача 5
- Site superintendentRuns the machines and trucks
- Excavator, trucks and cycle timesЗадача 4
Тръгва от вас
- Cut and fill quantitiesЗадача 1
- Borrow and waste quantitiesЗадача 2
- Overhaul and surplusЗадача 3
- Rate for haul to wasteЗадача 4
- Change for unsuitable siltЗадача 5
Вашият път през проекта
Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.
Quantities
Задача 1 · 35 мин
Изкоп и насип по метода на средните челни профили
- Вашият резултат
- Cut and fill volumes, items 02.01 and 02.02
- Документ
- Ten cross-sections of Heron Drive
- В ERP
- Bill of Quantities
Quantities
Задача 2 · 35 мин
Набъбване, слягане и курсове на камиони
- Вашият резултат
- Borrow to bring in, and truck loads to take away
- Документ
- Soil factors and the engineer's note on wet clay
- В ERP
- Bill of Quantities
Quantities
Задача 3 · 40 мин
Преместване на земните маси, безплатен превоз и свръхтранспорт
- Вашият резултат
- Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
- Документ
- Mass ordinates of Marlow Avenue
- В ERP
- Bill of Quantities
Rate
Задача 4 · 45 мин
От производителност на оборудването към единична цена
- Вашият резултат
- The unit rate for haul to waste
- Документ
- Machine costs, fuel and cycle times
- В ERP
- Bill of Quantities
Change
Задача 5 · 40 мин
Негодни материали: остойностяване на промяна
- Вашият резултат
- The priced change for unsuitable silt
- Документ
- Test pit sections and agreed rates
- В ERP
- Variations
How a cross-section becomes a price
Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.
В синьо е това, което задачата добавя; в сиво е пренесеното отпреди.
Накратко. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.