Uvod u tečaj · 3 min
Zemljani radovi: zapremnine iskopa i nasipa, dijagram masa i izrada cijena (Kanada)
Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Izmišljeni projekt
You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.
- Work
- Cut, fill, borrow (soil brought in) and haul for two streets
- Contract
- Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
- Story
- Tender in October 2026 to a change in June 2027
- Rad u ERP-u
- Zadataka: 5, oko 3 h 15 min
Tko kome što predaje
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Dolazi vama
- The Town's engineerIssues sections, checks quantities
- Cross-sections of Heron DriveZadatak 1
- Mass ordinates of Marlow AvenueZadatak 3
- Order: silt out, Granular B inZadatak 5
- Site superintendentRuns the machines and trucks
- Excavator, trucks and cycle timesZadatak 4
Odlazi od vas
- Cut and fill quantitiesZadatak 1
- Borrow and waste quantitiesZadatak 2
- Overhaul and surplusZadatak 3
- Rate for haul to wasteZadatak 4
- Change for unsuitable siltZadatak 5
Vaš put kroz projekt
Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.
Quantities
Zadatak 1 · 35 min
Iskop i nasip metodom srednjih površina
- Vaš rezultat
- Cut and fill volumes, items 02.01 and 02.02
- Dokument
- Ten cross-sections of Heron Drive
- U ERP-u
- Bill of Quantities
Quantities
Zadatak 2 · 35 min
Rastresitost, zbijanje i kamionske vožnje
- Vaš rezultat
- Borrow to bring in, and truck loads to take away
- Dokument
- Soil factors and the engineer's note on wet clay
- U ERP-u
- Bill of Quantities
Quantities
Zadatak 3 · 40 min
Dijagram masa, besplatni prijevoz i dodatni prijevoz
- Vaš rezultat
- Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
- Dokument
- Mass ordinates of Marlow Avenue
- U ERP-u
- Bill of Quantities
Rate
Zadatak 4 · 45 min
Proizvodnost opreme u jediničnu cijenu
- Vaš rezultat
- The unit rate for haul to waste
- Dokument
- Machine costs, fuel and cycle times
- U ERP-u
- Bill of Quantities
Change
Zadatak 5 · 40 min
Neprikladan materijal: izmjena cijene
- Vaš rezultat
- The priced change for unsuitable silt
- Dokument
- Test pit sections and agreed rates
- U ERP-u
- Variations
How a cross-section becomes a price
Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.
Plavo je ono što zadatak dodaje; sivo se prenosi od prije.
Ukratko. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.