OpenConstruction Academy
Prijava / Registracija
HR

Uvod u tečaj · 3 min

Zemljani radovi: zapremnine iskopa i nasipa, dijagram masa i izrada cijena (Kanada)

Marlow Heights Phase 1 · Two new subdivision streets, Ontario · Izmišljeni projekt

You are the estimator for the earthworks contractor on two new streets in Ontario. Earthworks means digging soil out where the road is too high (cut) and building it up where it is too low (fill). In five tasks you measure cut and fill, convert soil between its loose and packed states, read a mass haul diagram, build a hauling rate from machine cycles and price a change for poor ground.

Započni zadatak 1

Work
Cut, fill, borrow (soil brought in) and haul for two streets
Contract
Municipal unit-price contract, items in the OPSS style (Ontario standard specifications)
Story
Tender in October 2026 to a change in June 2027
Rad u ERP-u
Zadataka: 5, oko 3 h 15 min

Tko kome što predaje

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Dolazi vama

  • The Town's engineerIssues sections, checks quantities
    • Cross-sections of Heron DriveZadatak 1
    • Mass ordinates of Marlow AvenueZadatak 3
    • Order: silt out, Granular B inZadatak 5
  • Site superintendentRuns the machines and trucks
    • Excavator, trucks and cycle timesZadatak 4
ViEstimator, earthworks contractor

Odlazi od vas

    • Cut and fill quantitiesZadatak 1
    • Borrow and waste quantitiesZadatak 2
    • Overhaul and surplusZadatak 3
    • Rate for haul to wasteZadatak 4
    • Change for unsuitable siltZadatak 5
    The TownOwner, pays by the unit

Vaš put kroz projekt

Three tasks to get the quantities right, one to price a line that has no rate, one to price a change once the ground is open. Start with task 1: in the Bill of Quantities you work out cut and fill from ten cross-sections.

  1. Quantities

    Zadatak 1 · 35 min

    Iskop i nasip metodom srednjih površina

    Vaš rezultat
    Cut and fill volumes, items 02.01 and 02.02
    Dokument
    Ten cross-sections of Heron Drive
    U ERP-u
    Bill of Quantities
  2. Quantities

    Zadatak 2 · 35 min

    Rastresitost, zbijanje i kamionske vožnje

    Vaš rezultat
    Borrow to bring in, and truck loads to take away
    Dokument
    Soil factors and the engineer's note on wet clay
    U ERP-u
    Bill of Quantities
  3. Quantities

    Zadatak 3 · 40 min

    Dijagram masa, besplatni prijevoz i dodatni prijevoz

    Vaš rezultat
    Overhaul (hauling beyond the free distance) and surplus, items 03.01 and 03.02
    Dokument
    Mass ordinates of Marlow Avenue
    U ERP-u
    Bill of Quantities
  4. Rate

    Zadatak 4 · 45 min

    Proizvodnost opreme u jediničnu cijenu

    Vaš rezultat
    The unit rate for haul to waste
    Dokument
    Machine costs, fuel and cycle times
    U ERP-u
    Bill of Quantities
  5. Change

    Zadatak 5 · 40 min

    Neprikladan materijal: izmjena cijene

    Vaš rezultat
    The priced change for unsuitable silt
    Dokument
    Test pit sections and agreed rates
    U ERP-u
    Variations

How a cross-section becomes a price

Each column is the bill after one task. Grey is what it already holds; blue is what that task adds.

Cut and fill
Zadatak 1Measured volumesThe areas at each end of a slice times its length give cut and fill, each in its own unit and item.
Borrow and wasteCut and fill
Zadatak 2Borrow and wasteCut and fill compared in one state of the soil. What is short is imported, what is unusable leaves by truck.
Overhaul and surplusBorrow and wasteCut and fill
Zadatak 3HaulDistance beyond the free haul is paid as overhaul. What is left at the end is surplus.
Haul to waste, pricedOverhaul and surplusBorrow and wasteCut and fill
Zadatak 4A rate built upMachine output, hourly cost and the dump's gate fee give a price per bank m³ (soil as it lies in the ground).
Change for siltThe priced bill
Zadatak 5A changeUnsuitable silt out, granular fill in, at agreed rates and without HST (sales tax).

Plavo je ono što zadatak dodaje; sivo se prenosi od prije.

Ukratko. Measure in bank m³. Convert only to compare or to haul. The slower machine sets the output. Price a change at the agreed rates, HST outside.